NO OF WEEKS ACTIVITY

1) Learn Safety Precaution Methods 2)


WEEK 1 Plastering 3)
Curing 4)
Shuttering

1) Mortar 2)
WEEK 2 Lintel Beam 3)
Mullion column 4)
Sill Level

ACKNOWLEDGEMENT
This Project is done as a major Project Titled IN PLANT
TRAINING (IPT) , a Part of Course CIVIL ENGINEERING.
I am Really Thankful to The HOD JAHANKEER . A , GMS
ELEGANT BUILDERS PVT LTD . Without His Invaluable
guidance And assistance ,The Accomplishment of the Task
Never been Possible. And also I am Thankful to the Project
Managers for Providing Relevant information, necessary
clarifications, and great support .
PROJECT DETAIL
Project Name : Kauvery hospital Located at C/0.52,Alexandria
road Contonment , Trichy Central bus Stand – 620 001 and
Contract for This Building Awarded to GMS ELEGANT
BUILDERS PVT LIMITED

Driven By
Excellence
We define excellence as being true to ourselves,
exceeding client expectations, and being led by the
spirit of innovation and sustainability.

SCOPE : ALL TYPES OF CONTRUCTION OF


BUILDINGS WITH OWN EQUIPMENTS

1) No of Floors : 7
2) Estimated cost – 40 crores