You are on page 1of 4

BLASTING

BLASTING&&PAINTING
PAINTINGREPORT
REPORT
Client : PT. PUPUK ISKANDAR MUDA Report No. : BPR-AT-RP-04
Project : PEMBANGUNAN TANGKI AMMONIA Project No. : P05-001/09-23
Drawing No. : PA-6442-T2-DW-64FB2002.1-2005-R-IFA Page : 1 of 4
Item name : ANNULAR PLATE AMMONIA TANK (EXTERNAL)

SURFACE PREPARATION
BLASTING STANDART : SSPC SP 10 TESTEX O FILM
INITIAL RUST GRADE : A
ABRASIVE MATERIAL : STELL GRID
ROUGHNESS PROFILE : 78 mm
WEATHER CONDITION
FINE CLOUDY RAIN ✘ CLEAR
A. MICROCLIMATE READINGS (ISO 8502-4)
Check Item Specs. / Time 9:00 AM 2:00 PM REMARKS
Air (Dry Bulb) Temp. (°C) 20 To 35 35.2 36.3
Wet (Bulb) Temp. (°C) - 26.3 26.4
Relative Humidity (%) 85 Max 50.3 44.9
Dew Point Temp. (°C) 3-5 Below St 23.3 22.4
Steel Surface Temp. (°C) 3-5 Above DP 35.2 36.7
B. PAINTING SPECIFICATION
LAYER NO. DATE BRAND BATCH NUMBER TYPE DFT (µm) COLOR / RAL
PRIMER 17/4/2024 JOTUN 2736749-1 EPOXY POLYAMINE 100 BLACK
-
FINISH COAT 18/4/2024 JOTUN 2736749-1 EPOXY POLYAMINE 100 BLACK
C. RESULTS
DFT CHECK ( mm )
DESCRIPTION MARK Qty (ea) REMARKS
PRIMER INTERMEDIATE FINISH
126 210
110 226
ANNULAR PLATE OBP09 4 118 211 Acc
115 217
110 221

104 208
110 209
ANNULAR PLATE OBP10 1 106 210 Acc
107 211
110 212

104 208
108 209
ANNULAR PLATE OBP11 1 108 210 Acc
100 211
101 212

107 208
108 209
ANNULAR PLATE 0BP12 2 109 210 Acc
100 211
107 212

103 208
106 209
ANNULAR PLATE 0BP13 2 102 210 Acc
101 211
102 212

TOUCH UP
VERIFIED N/A
Inspected by Checked by Witnessed by / Reviewed by

Achmad Adnan AL. Irianto


Date : 22-04-2024 Date : 22-04-2024 Date : Date :
F7.5-30 Rev.0
PAINTING INSPECTION REPORT : BPR-AT-RP-04

17-04-2024 17-04-2024

AFTER BLASTING CLEANLINESS

17-04-2024 17-04-2024

TESTEX O FILM ROUGHNESS PROFILE 78 µm

17-04-2024 17-04-2024

PENGUARD UNIVERSAL COMP A PENGUARD UNIVERSAL COMP B


PAINTING INSPECTION REPORT : BPR-AT-RP-04

17-04-2024 17-04-2024

AFTER PRIMER DFT PRIMER 126 µm

17-04-2024 17-04-2024

DFT PRIMER 110 µm DFT PRIMER 118 µm

25 - 12 - 2020
17-04-2024 17-04-2024

DFT PRIMER 115 µm DFT PRIMER 110 µm


PAINTING INSPECTION REPORT : BPR-AT-RP-04

18-04-2024 18-04-2024

AFTER FINISH DFT FINISH 210 µm

18-04-2024 18-04-2024

DFT FINISH 226 µm DFT FINISH 211 µm

18-04-2024 18-04-2024

DFT FINISH 217 µm DFT FINISH 221 µm