You are on page 1of 1

CEMS MAIN STACK NHON TRACH 3,4

SYMBOLS:

MAIN STACK NT3 MAIN STACK NT4 AIR PIPING


SIGNAL CABLE

ETHERNET LIQUID PIPING

220VAC-1P UPS POWER 220VAC-1P UPS POWER ELECTRICALLY


FIBER OPTIC
(3) SUPPLY SUPPLY (3) HEATED TUBING
BOUNDARY
30HNE10EJ19 40HNE10EJ19
CAMERA PTZ (NOTE 2) CAMERA PTZ (NOTE 2)
(1) MODBUS RS485 SIGNAL LINE
AIT AIT
CAMERA PTZ (NOT 2) 40HNE10CU04 (2) ANALOG 4-20mA SIGNAL LINE
30HNE10CU04 CAMERA PTZ (NOTE 2)
DUST (3) (3) DUST (3) MODBUS TCP/IP
SIGNAL AND SIGNAL AND
(2) (2) AIT
AIT DISTRIBUTION CABINET DISTRIBUTION CABINET (4) DIGITAL SIGNAL LINE
30HNE10CU03 40HNE10CU03
30HNE10GR01 40HNE10GR01 40HNE10EJ20
FLOW
FLOW 30HNE10EJ20 (3) (3)
NOTE:
AIT AIT
30HNE10CU02 40HNE10CU02 1. ETHERNET STATIC IP TO BE USED IN ORDER TO GUARANTEE
O2 O2 CONTINUOUS AND STABLE DATA TRANSMISSION.
AIT AIT
2. PTZ STANDS FOR PAN TILT ZOOM
30HNE10CU05
(2) (2) 40HNE10CU05 3. INSTRUMENT AIR (I.A) SUPPLY: 5 - 6 BAR-G
Temperature Temperature CONNECTION 1/2" NPT(M) WITH ISOLATING HAND VALVE
(1) (1) NT3 & NT4: I.A SUPPLY AT 2 LOCATIONS:
AIT AIT
30HNE10CU06 40HNE10CU06 - EL + 55000
Pressure Pressure - CEMS STATION
4. TIME SYNCHRONISATION TO BE PROGRAMMED INTO PLC.
AIT AIT
30HNE10CU01 40HNE10CU01
ALL DATA TO BE SENT TO THE PLC AND THEY WILL BE ADAPTED WITH THE
Sample SO2 NO2 NO CO CO NO NO2 SO2 Sample SYNCHRONIZED CLOCK INSIDE THE PLC.
Probe Probe
BUILDING AREA NUMBER FOLLOW REFERENCE DRAWING:

1. NT34-S-00ZEN00-P01-0101_NT34_PLOTPLAN&SITE PLAN
EXTRACTIVE MULTI-CHANNEL GAS ANALYZER
EXTRACTIVE MULTI-CHANNEL GAS ANALYZER 40PAB10GH12
30PAB10GH12
DN15-HF2 DN15-HF2
HRSG NHON TRACH 3 STACK HRSG NHON TRACH 4 STACK

CALIBBRATION GAS CALIBBRATION GAS


INSTRUMENT AIR CYLINDERS INSTRUMENT AIR
SUPPLIED BY CLIENT SUPPLY

MAIN GATE CENTRAL CONTROL BUILDING ONLINE MONITORING IN DONRE/ONG KEO IZ/DOWRM

00CFQ10GN02

(3)
LED MONITORING DISPLAY (3) COMPUTER (3) SWITCH FO ETHERNET STATIC IP (NOTE 1)
00CYP10EJ013 00CKA10GK031B DONG NAI DONRE
(3) (STATIC IP)

STAMP / ĐÓNG DẤU

(3) ONG KEO IZ


PRINTER ETHERNET STATIC IP ROUTER
COMPUTER

(2) (2)

CLOCK (GPS) (3) (3) (3) DEPARTMENT OF WATER


SERVER DCS
SYNCHRONIZED TIME RESOURCES MANAGEMENT

MAIN COOLING WATER SYSTEM WASTE WATER DISCHARGE

MAIN COOLING WATER INLET MAIN COOLING WATER DISCHARGE

(3) (3)

(3)
(3) (3)

FOR CONSTRUCTION

(3)
220VAC-1P UPS POWER 220VAC-1P UPS POWER (3) 220VAC-1P UPS POWER 220VAC-1P UPS POWER
SIGNAL AND SUPPLY SUPPLY SIGNAL AND SIGNAL AND SUPPLY SIGNAL AND SUPPLY
DISTRIBUTION CABINET DISTRIBUTION CABINET CAMERA PTZ (NOT 2) (3) DISTRIBUTION CABINET DISTRIBUTION CABINET 0 28/02/2024 FOR CONSTRUCTION T.N.T T.M.N T.M.N
CAMERA PTZ (NOTE 2)
(3)
C 22/11/2023 FOR APPROVAL T.N.T T.M.N T.M.N

30PAB20EZ07 B 27/09/2023 FOR APPROVAL T.N.T T.M.N T.M.N

FE (2) 00GUA10EZ07
A 23/08/2023 FOR APPROVAL T.N.T T.M.N T.M.N
30PAB20CF01

(2) (2) REV. DATE / DESCRIPTION DESIGNER RVWD DES.LEA ENG. MAN.
OUTLET PHIÊN BẢN NGÀY MÔ TẢ THIẾT KẾ KIỂM TRA C.T.T.K C.N.T.K
AE
00PAA10CU01
FLOW (2) (2) (4) (2) (2) (4)
Project / Dự Án

CHLORINE TEMPERATURE AE
(2) AIT
NHON TRACH 3 AND NHON TRACH 4 POWER PLANT /
00PAA10CU02 pH 00GUA10CU01
NHÀ MÁY ĐIỆN NHƠN TRẠCH 3 VÀ NHƠN TRẠCH 4
COOLING WATER DISCHARGE NT3 Owner / Chủ đầu tư Project Technical Consultant /
FE Tư Vấn Kỹ Thuật của CĐT
30PAB20CF02 CAMERA PTZ (NOTE 2) SAMPLE TANK -
OUTLET WASTEWATER

DN25-HH1

DN50-HH1
FLOW 00PAB20KD04
AE AE
00PAB10AP10A &
30PAB20CQ01 40PAB20CQ01
00PAB10AP10B
00GUA10EZ08
PUMP x 2 O
W
P)R
EVP( O
NITO
A
R
PCO
W
PR
EMA
NTEIO
R
VTEP
AUTO SAMPLER SAMPLE TANK - AUTO SAMPLER SAMPLE TANK - 00GUA10CP09A & )PVP( DR
O
ABTMN
G
EA
M
NTC EO
R
JPO
W
PR
E
CHLORINE TEMPERATURE - NT3 COOLING WATER CHLORINE TEMPERATURE - NT4 COOLING WATER 00GUA10CP09B
EPC Contractor / Nhà Thầu EPC
30PAB20KD12 NHON TRACH 3 40PAB20KD13 NHON TRACH 4 PUMP x 2
30PAB20KD12 40PAB20KD13 SAMSUNG C&T VIETNAM MACHINERY
Engineering & Construction Group INSTALLATION CORPORATION - JSC
DN25-HH1 DN50-HH1 DN25-HH1 DN50-HH1

SIGNAL AND Sub-Contractor / Nhà Thầu Phụ


220VAC-1P UPS POWER DISTRIBUTION CABINET FT
SUPPLY
CAMERA PTZ (NOT 2) 00GUA10CF02
VIET AN ENVIRONMENT TECHNOLOGY JOINT STOCK COMPANY
30PAB20AP09A & 40PAB20AP09A &
30PAB20AP09B 40PAB20AP09B OUTLET FLOW
DN200
PUMP x 2 PUMP x 2
30PAB20EZ08
Stage / Giai Đoạn
FE
40PAB20CF01
WASTE WATER DN200-HH1
SYSTEM TERMINAL POINT WASTE WATER
CONSTRUCTION DESIGN
(2)
OUTLET THIẾT KẾ BẢN VẼ THI CÔNG
FLOW
(2)
Drawing Title / Tên Bản Vẽ
RIVER RIVER
BY CLIENT

INLET FLOW INLET FLOW

COOLING WATER DISCHARGE NT4


FE Designer / Reviewer / Des. Lead / Eng. Man. / Owner's Drawing Number /
OUTLET 40PAB20CF02 Thiết Kế Kiểm Tra Chủ Trì TK Chủ Nhiệm TK Scale / Tỉ Lệ Số hiệu bản vẽ của Chủ đầu tư
FLOW
Name / Tên Name / Tên Name / Tên Name / Tên NT34-LI01-00CZB10-J06-0027
TO DISCHARGE POINT
T.N.THI T.M.NHUT T.M.NHUT
COOLING WATER INLET COOLING WATER INLET OUTFALL PIT OUTFALL PIT
OF ONG KEO IZ
Signature Signature Signature Signature Sheet No. Contractor's Drawing Number / Rev. / P. bản
OF NHON TRACH 3 OF NHON TRACH 4 Chữ ký Chữ ký Chữ ký Chữ ký Số trang Số hiệu bản vẽ của Nhà thầu
NT34-LI01-00CZB10-J06-0027 0
A3 (420 x 297)