Professional Documents
Culture Documents
2-2 Injectable Water-Stop Development
2-2 Injectable Water-Stop Development
Korea University
September 21st, 2022
Table of Contents
1. Motivation
2. Brief Review
▪ Multi-Disciplinary Partners:
- Samsung C&T Civil Engineering Dept. (Primary Investigator)
- Daeryong Ind. Co., Ltd. (Manufacturer)
Identifying
Grouting Material
Video Clip 2
Polymer Urethane
Injection Test
Video Clip 3
Test Results Summary
Modified
Type Water Micro Cement PU PU PU
Acryl
Viscosity
1 28 17 300 200 150
(poise)
Material
Temperature
10 21 24 10 18 22
(°C)
Quantity
0.015 0.020 0.015 0.015 0.017 0.012
(m3)
Pressure at Bottom
1st Filling 3.0 4.0 4.0 3.0 3.0 3.0
(bar)
Time to Fill
21 23 27 300 204 192
(sec)
Pressure at Bottom
3.0 5.0 7.0 NA 4.0 3.0
(bar)
2nd Injection
Time to Injection Completion
65 246 180 NA 322 203
(sec)
Flow Rate
0.340 0.090 0.098 NA 0.144 1.091
(m3/sec)
As material viscosity increases,
time to filling in the 1st stage takes longer.
As material viscosity increases,
the quantity of grouting material in the 2nd stage is reduced.
Video Clip 4
Long-Term Back-Flow Pressure Resistance Test
ground level.
15 months.
Long-Term Back-Flow Pressure Resistance Test
Backflow Resistance Results
Video Clip 5
6. 30 M – Real Scale Vertical Injection
Test (at Sea Water Intake Shaft)
Primary Difference Between 15 m and 30 m Tests
Digital Pressure
Camera Gage
④ The 30-m water-stop was lifted by 25 ton cargo crane.
⑤ Lifted water-stop was laid down inside the shaft.
⑤ Lifted water-stop was laid down inside the shaft.
⑤ Lifted water-stop was laid down inside the shaft.
⑥ Completion of water-stop installation.
30 m
Indication
Pressure
Gage
Digital
Camera
⑦ Inlet tude of water-stop was connected to nozzle of injection.
Injection
Injection Tool Material
Pressure
Measured Pressure
Time Injection Stage
at the Bottom (Level of -30 m)
≒
1 min 40 sec Continue NA
Test 2 Results
≒
8 min 00 sec 0 bar
Test 2 Observation
Nitrogen
1 Chamber 27 L 4 bar NA b 100 sec NA b
Pressure
High-Power
3 80 L High Power 17 sec 420 sec 1.5 ~ 1.7 bar
Injection Pump
a Substantially, the ‘time’ means when the bottom is subjected by a certain level of pressure.
It is inferred that the grouting material arrived much earlier than the indicated time.
b In the test 1, the pressure could not be recorded due to misalignment during water-stop laying down.
Discharging Rate (L/sec) as to Injection Capacity
Grouting Material Arrival Time to the Bottom (sec)
NA
※ Note :
In the test 1, the pressure could not be recorded due to misalignment during water-stop laying
down. Arrival time for the “Nitrogen Pressure” test is inferred to be the earliest.
Findings
Mark – II Mark – X
Air Compressor
(Graco Company) (Graco Company)
FEL
Section Water-Stop Design
▪ Water-Stop Design Case for the Lb3 Section Temporary Slab
Roof Slab
→ ‘Condition 2 : No Fissure Grouting’
Base Slab
Final Excavation
Level
Water-Stop
Termination Level
▪ Grouting Time
- When water leakage is
‘observed’ after GWT recovery
▪ Grouting Direction
- Tunnel Side
Pressure (kg/cm2)
Depth (m)
Standard Bedrock
Monitoring of Injection Mode (P~Q~t Chart)
▪ Typical injection mode will be monitored.
▪ Two types of injection pump were recommended by BASF for Singapore grouting works.