You are on page 1of 1

BOQ of 33KV line project (15 KM matambo-jindal project)

Sr.
Description of activity Materials Unit Installed Qty unit price Total Price
No.
1 Erection of Wooden treated poles 1.1 12 Meter poles ,180mm dia minimum No 71 1,959.00 139,089.00
2.1 Cross arms single poles No 64 245 15,680.00
2.2 cross arms for H poles No 8 295 2,360.00
2.3 post insulators No 187 155 28,985.00
2.4 spindle/bolts for post insulators No 187 35.1 6,563.70
2.5 Long road insulator (tension insulators) No 30 125.3 3,759.00
2 Erection of insulators
2.6 Eye bolts for epoxy insulators No 15 55.5 832.50
2.7 Clevis ball No 30 25.5 765.00
2.8 Eye Nut No 15 35.5 532.50
2.9 suspension clamp No 0 27 0.00

3.1. Stay set anchoring pole with base plate No 21 150.00 3,150.00
3.2. Stay wire 7x4mm m 273 15 4,095.00
3.3. Pole make off No 21 75.00 1,575.00
3 Installation of stay wire set
3.4. Guy grip No 63 75 4,725.00
3.5. 33kV Stay insulator No 21 55 1,155.00
3.6. Coach Screw - No 21 15 315.00
4.1. 150mm2 malberry Conductor km 17.94 22,950.40 411,730.18
4 Stringing of conductor 4.2. Parralel groove clamp 197 122.00 24,034.00
4.3 Pistol Grip No 30 232.80 6,984.00

5 Other accessories Please add the other accessories if any No 656,329.88