Professional Documents
Culture Documents
Columbia Report On Load-Forecast-And-Substations VR-10
Columbia Report On Load-Forecast-And-Substations VR-10
• Objective
• Planning Criteria and General Considerations
• Spatial Forecast overview
• Spatial Forecast aggregated results
• Substation Size Study
• Summary of Results
• Conclusions
• Study Files
This presentation provides an update to the initial load forecasts to account that the energy efficiency
gains are likely to be limited spatially to places where the existing customers are located. It covers the
following:
Overview of spatial load Allocation Methodology
Load allocation results and reference files.
Overview of changes of substation coverage areas.
Details on changes for each existing substation in terms of proposed coverage areas, new capacity
additions and new substations.
• Present and future load by substation, including two options.
−Proposal I: With no new substation, only expansions.
−Proposal II: With a new substation at south and some expansions.
Summary of capacity additions by substations
Summary of recommendation and conclusions
Details on supporting files including AutoCAD maps and excel files.
The analysis of the substations coverage areas and the need for new substations included the
following considerations:
a) The substations must be able to sustain an outage in one transformer without overloading the remaining
transformers (Firm Capacity or N-1 in the tables); this means that the ratio Load/Firm Capacity should no be
more than 100%. Slight increases are allowed considering that the analysis is done for the substation peak
and there is always the possibility under emergency to transfer load out.
a) When assessing the coverage areas of substations estimated “optimal radius” was considered that would
provide a balance between the cost of technical losses and feeder length and the cost of building a second
substation. This “optimal radius” is used as an indicator of the potential for a new substation, however it is
only one consideration as there should also be enough load in the area to justify two substations.
a) When redefining the coverage area of the substations, we took into account the location of the load centers
and in some cases, proposed a redefinition of boundary in order to bring these load centers closer to the
substation’s location. This resulted in shorter feeders, lower losses and better reliability.
Next step is to asses how much land coverage each Zone represents in every cell.
In Columbia there are 13 different Zones (MU, R-1, etc. see example below)
The column “Other” takes into count the areas outside the city limits that are still served by CWL.
This step identifies for each cell the inherent potential of the load on it to grow. For this we take into
consideration:
1. The percentage of unoccupied terrain in CWL territory; (100% – Used Terrain) * % CWL service Territory.
2. Development Level; this takes into consideration the likelihood of being developed; closer to the downtown
area, other customers of the same type and roads for example results in a higher number. Flooding risks
or distance to roads result in the opposite.
3. Chances to Grow: This takes into consideration the location and suitability of the yet to be developed
terrain. There could be terrain but poorly located results in a low number, the opposite in a high number.
FIJ
FIQ
The cells inherent potential to grow is a function of its characteristics; land available, level of development and
chances to grow as discussed. However, not all will develop at the same time and a further adjustment is made to
assess the final Potential to Grow considering timing:
Only cells with “Chances to Grow” of 4 and 5 were given a Potential to Grow equal to its inherent potential by 2025
This range was expanded to 3 to 5 for 2030; i.e. the Potential to Grow is equal to the inherent potential if Chances to Grow >2
By 2040 the range was expanded to 2 to 5 for 2030; it the chances to grow is 1; it is considered to zero Potential to Grow.
Forecasted New Load YEAR WITH PV (MW) NO PV (MW) DIFF (MW) Diff (%)
Year 2020 273.062 273.090 0.028 0.0%
Demand (MW) (MW)
2025 276.071 276.229 0.158 0.1%
2020 273.09
2030 280.203 281.099 0.895 0.3%
2025 276.23 7.58
2040 302.487 304.611 2.124 0.7%
2030 281.10 15.05
2040 304.61 29.94
Restricted © Siemens 2020
Page 17 2020-02-27 SI DG SW&C PTI
Step 9: Load Forecast allocation using Potential to Grow
Energy Efficiency consideration adjustment
Energy efficiency, i.e. improving the efficiency of the way electricity is used will happen largely on the
existing customers, as new customers are expected to have new efficient facilities and dwellings. The
existing customers demand change is expected to have two components the vegetative growth as more
load is added (very small component) and a decrease due to the energy efficiency. To this load the new
load needs to be allocated, including the EV. The table below shows these load components and the values
used for the allocation. Note that the existing load consumption is expected remain about contant, so the
growth is concentrated on the new load locations
In this final step the load growth for the period (2025, 2030 or 2040) is allocated back to each cell considering the
Potential to Growth and the forecast.
For each term the load ratio adjust the existing and previous located load, and the adjustment factor equals the growth
with the forecasted new load.
The tables below show the adjustment factors and how sum of the adjusted loads in all cell are confirmed to match the
total load.
2020 273.09
2025 276.23 0.98 7.58 35.143 0.21568
2030 281.10 0.96 15.05 123.188 0.12218
2040 304.61 0.98 29.94 169.800 0.17632
Match
Restricted © Siemens 2020
Page 19 2020-02-27 SI DG SW&C PTI
Step 9: Substation Peak Factors
Demand was computed for System peak, but some substations have their peak at different time, so a
Peak factor was computed to cover the real load that one substation could experience for expansion or
change in coverage areas purpose.
The table below shows the factors to apply to the sum of all distribution transformers for each
substations.
In order to make the feeders analysis and to have a better granularly, the cell growth is applied to the
transformers inside the cell proportionally to the previous load.
After this step the transformers will have the future load allocated
The partial view of the excel file bellow shows how this is done for all the transformers and for each term.
Below is another example of expected growth on an industrial area and we observe that this cell will
experience a high growth by 2040 due the proximity to main roads and space available for new constructions.
Observation: The load presented is the individual substation peak and we observe that it needs a capacity expansion (from 2
X 22.4 to 3 X 22.4 MVA) by 2025 as the firm capacity (22.4 MVA) is already exceeded by the substation peak (27.5 MW).
No other changes expected.
2.2 MVA
Year South PC PC Load PC load Without Firm Cap Result/ Firm Cap
Load (MW) Load (MW) South (MW) (MVA) (%)
2025 7.17 35.01 27.84 22.40 1.24
2030 6.51 34.35 27.84 22.40 1.24
2040 7.33 35.42 28.08 22.40 1.25
One option to address the over extension of feeders out of Perche Creek and reliability issues is to create
microgrids with local generation (PV + Storage). A high level review identified approximately 10.6 MW that could
be served locally and reduce the load at Perche Creek to 27.84 MW by 2025 and 28.08 MW by 2040, which is
still over the firm capacity . This will also be assessed as a option during the network studies.
Restricted © Siemens 2020
Page 45 2020-02-27 SI DG SW&C PTI
Columbia Spatial Load Forecast and Substation Assessment
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1) before any of the recommended changes. As shown earlier Perche Creek, Power Plant and Rebel Hill
capacity is already exceeded under N-1. Other substations like Bolstad have this capacity exceeded but by an
small value and this would be acceptable as load could be transferred in the unlikely effect of a transformer
failure at the time of the peak.
Summary Results for 2020
Capacitors Transformers Transformers Coincident Coincidence Peak Load PRESENT LOAD Nº TRX
NAME N-1
Installed Load Load Load (2020) Factor (2020) CAP. /CAP. 2020
[MVAR] [MW] [MVAr] [MVA] [MW] [MVA] [%] [%]
Bolstad 12.90 14.28 8.57 14.28 1.6961 24.22 44.8 54% 108% 2
Blue Ridge 10.80 23.84 9.23 23.84 1.0000 23.84 44.8 53% 106% 2
Grindstone 15.00 34.90 15.33 34.90 1.1956 41.73 67.2 62% 93% 3
Harmony Branch 29.70 40.55 17.59 40.55 1.0000 40.55 67.2 60% 91% 3
Hinkson Creek 20.10 45.15 18.57 45.15 1.0004 45.17 67.2 67% 101% 3
Perche Creek 13.50 35.08 10.89 35.08 1.0285 36.08 44.8 81% 161% 2
Power Plant 19.50 47.56 23.93 47.77 1.0749 51.34 67.2 76% 115% 3
Rebel Hill 16.95 31.72 14.13 31.72 1.0000 31.72 56 57% 113% 2
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1), before any of the recommended changes. By 2030 Blue Ridge is added to the list of substation requiring
attention.
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1), before any of the recommended changes. Grindstone and Hickson creek start becoming overloaded
under N-1 and both over loads are addressed by reducing the coverage areas of these substations.
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1) with the recommended changes but not including the new substation (Proposal I). Note the solutions in
terms of a) new capacity additions, b) substation areas expanded (taking load from other substations) and c)
areas reduced (transferring load to other substations).
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1) with the recommended changes but not including the new substation (Proposal I).
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1) with the recommended changes but not including the new substation (Proposal I).
The tables below summarize the present and future load, capacity by substation and loadings over firm capacity
( N-1) with the recommended changes and including the new substation (Proposal II).
1. Expand in capacity four substations : Perche Creek (22.4 MVA in 2025), Harmony Branch (22.4
MVA by 2040), Bolstad (22.4 MVA by 2025) and Rebel Hill (28 MVA by 2025) and redistribute the
service area of the affected substations to warrant the firm capacity of each substation and
reliability of the system
2. If a new substation is to be built (Proposal II), it should be build at S Scott BLVD . It would require
a 2x22.5 MVA bank and would address overextension of feeders out of Perche Creek, however
Perche Creek Substation would still need to be expanded, making this option less likely to be on
the optimal plan.
3. Non-Wire- Alternatives could be used to address the supply of loads during emergency conditions
south of Perche Creek and could delay the need for the expansion of this substation. However as
the expansion is still needed in the long term, this option needs to be assessed by more detail
during the network studies.
Maps with Spatial load for each term Files used in data analysis and Transformers Load check
• Zoning-Indexes-Spatial-Transformers-Allocation-VR-9.xlsx
• Columbia_SS_Proposal-1.1-Solution.dwg
• Columbia_SS_Proposal-2.1-New-SS-Solution.dwg
Restricted © Siemens 2020
Page 60 2020-02-27 SI DG SW&C PTI