Professional Documents
Culture Documents
A. Discrepancy in difference brought over as per line 5 of last month memo. As stated in the Audit Observation that, the difference brought over as per last
month’s Memo i.e. April 2019- May 2019 by ₹ 12,60,202/- and May 2019- June
Statement of Part-I Cash remitted and acknowledged of Form-51 for the month of 2019 by ₹ 51,69,089/- having a sum of ₹ 64,29,291/- were noticed. It was
April2019 to June 2019 is shown below : regretted to state that the difference brought over were wrongly shown/entered
Sl. Particular April May 2019 June 2019 on the column 1 and 5, but still either the cash remitted during these months or
No 2019 the amount acknowledged by Treasury North remained the same (unchanged).
1 Difference brought over as per line 5 of
1292325 32123 -5169089
Knowing the conditioned of these discrepancy in difference brought over,
last month memo compilation-III section of the Principal Accountant General Office issued
2 Cash remitted during the month 22267212 15094539 6818499 ‘Broadsheet’ as to Public Works Challans, Based on such broadsheet and
3 Total 20974887 15126662 1549410 reconciled figures, the Division worked out the correct figure as under:-
Month Div.Fig Trea.fig Diff. Prog.
4 Amount acknowledge by Treasury 22267212 1512662 6636652 Balance
5 Difference (line 3-4) as detailed below April-19 22834270 22866309 -32039 32039
1292325 0 -5087242
May-19 15094539 15126662 -32123 64162
June-19 6818499 6636652 +181847 117685
From the above, it is noticed that line 5 i.e., the Difference (Line 3-4) for the Jul-19 21287582 21322893 -35311 82374
month of April 2019 was ₹12,92,325.00. However, the difference brought over as Aug-19 8987010 3717221 +5269789 5352163
per line 5 of the last month memo in the month of May 2019 was only ₹ Sep-19 6457715 6723744 -266029 5086134
32,123.00. Thus, this has resulted in understatement of the difference brought Oct-19 24702227 20445524 +4256703 9342837
over as per line 5 of last month memo in the month of may 2019 by
Nov-19 13783380 13753293 +30087 9372924
₹12, 60,202.00.
Dec-19 12029785 12010220 +19505 9392489
Similarly, line 5 i.e., the Difference (Line 3-4) for the month of May 2019 was Jan-20 17677612 17744446 -66834 9325655
₹0.00 (NIL). However, the difference brought over as per line 5 of the last month Feb-20 15295416 18210312 -2914896 6410759
memo in the month of June 2019 was only (-) ₹51,69,089.00. Thus, this has Mar-20 7608900 13183159 -5574259 836500
resulted in discrepancy in difference brought over as per line 5 of last month Hence, the closing balance at the end of the year 2019-2020 was ₹ 8,36,500/-.
memo in the month of June 2019 by (-) ₹51,69,089.00. Apart from this Form-20 (Accepted figures after having reconciled figure with
While confirming the above facts and figures, comments of the Department and AG Office) during 2019-2020 was resubmitted to AG Office for ready reference
reason thereof may be intimated to audit. Further, this needs to be reconciled with is (enclosed as Annexure-II).
intimation to audit.
B. Arithmetical inaccuracy/wrong entry of figures. As per accepted 8782 reconciled figures for the year 2019-2020. Amendment
Scrutiny of records revealed that the total of the difference brought over as per was made for the month of June 2019 as shown below:
line 5 and cash remitted during the month was ₹ 16,49,410.00 during the month
Sl.No Particulars Amount
of June 2019. However, as per Form-51, the total of the difference brought over
as per line 5 and cash remitted during the month was ₹15,49,410.00 during the 1
Difference brought over as per line 5 of last month
-64162
month of June 2019 resulting in understatement by ₹1,00,000.00. memo
2 Cash remitted during the month 6818499
Similarly, line 5 i.e the difference (Line 3-4) was ₹ 49,87,242/- during the month 3 Total 6754337
of June 2019. However. As per Form-51, line-5 I.e the difference (Line 3-4) was 4 Amount acknowledge by Treasury 6636652
₹ 50,87,242/-, during the month of June 2019. This has resulted in overstatement Difference (line 3-4) as detailed below
5 +117685
ogf line 5(Line 3-4) by ₹1,00,000/- as shown below:-
Sl. June 2019 as Note: To avoid late receipt/lost of Challan etc, the Division changes
Particulars June 2019 Difference the channeling system of Challan Cash Depositor. In
No per Form 51
Difference brought over as per line accordance with this system, the Department acts as the depositor by collecting
1 -5169089 -5169089 0
5 of last month memo the estimated amount of money from the consumers to eradicate the difference
2 Cash remitted during the month 6818499 6818499 0 brought over occurred in every month.
3 Total 1649410 -1549410 100000 During the Audit period, the Division used to issued challans to the consumers to
4 Amount acknowledge by Treasury 6636652 6636652 0 deposit the required amount to the Bank. But some consumers neglected
Difference (line 3-4) as detailed returning the remitted challan to the department resulting in different amount of
5 -4987242 -5087242 100000
below total remittance to the part of division as well as Treasury North.
While confirming the above facts and figures, comments of the department and
reasons thereof may be intimate to audit. Further, this needs to be reconciled with Therefore, this para may please be dropped.
intimation to audit.
As per the revised detailed Project for Improvement of Aizawl Water Supply
Scheme under AMRUT was ₹ 1186.00 lakh which was to be executed in a phase
wise manner during the period 2017-2019.
The details of fund received and expenditure thereof under AMRUT is shown
below:
Fund Received Fund yet
Sl. Expenditur
DPR Balance to be
No Date Amount e
received
1 118600000 18.09.2018 46634000 46634000 0
2 09.12.2020 17707000 17707000
118600000 64341000 64341000 0 54259000
The Department has executed and completed various works under AMRUT at an
estimated cost of ₹ 466.34 lakh during the period 2017-2019 as shown below:
Sl. Contract/ Estimate
Name of Works
No Department Cost
1 Pipes Works Departmental 34073270
2 Khatla Tlang Reservoir Departmental 7556300
3 Approach road to Khatla tlang Zonal Tank Departmental 385000
4 Tlangnuam Reservoir Departmental 2683000
5 Water Meter Management Departmental 1500000
6 Chal Tuikhur Departmental 250000
Repair of Site Office @ New Secretariat Departmental
7 Complex
187100
Total 46634670
Scrutiny of records revealed that the Department made payment of ₹ 2.68 lakh to
TP Enterprise for supply of materials- Sluice Valve, However, These details were
not on records in the cash book and as well as the financial status of expenditure.
Hence, whether the expenditure incurred towards payment to the suppliers remain
vague and thus resulted in doubtful expenditure to the tune of ₹ 2.68 lakh.
Bank Authorization for implementation of JJM for the financial year 2020-2021,
under AWDDS was accorded by the E-in-C PHED vide No.G-25022/3/2020-E-
in-C/PHE/JJM/48A dated 12.01.2021 (₹ 2,25,31,697) No.G.25022/3/2020-E-in-
C/PHE/JJM/66A dated 18.01.2021 (₹41,68,980) and No.G No.G25022/3/2020-E-
in-C/PHE/JJM/74A dated 27.01.2021 (₹3,13,372.94) total being (₹2,70,14,050).
And DPR for the same 8 villages viz. Samtlang, Lungleng I, Kelsih, Melriat, N
Lungleng, Falkawn, Hualngohmun and Muallungthu was prepared and approved
on December 2020.
2019-2020 2020-2021
Sl. Name of Village Estimate Proposed Estimate
N Proposed
Amount HWC Amount
o
1 Samtlang 117 2865368 67 2480000
2 Lungleng I 162 3894677 25 1511000
3 Kelsih 189 3519081 25 1928000
4 Melriat 222 4120805 99 2948000
5 N Lungleng 149 3775964 58 2038000
6 Falkawn 284 5340964 374 11781000
7 Hualngohmun 161 3821132 93 4372000
8 Muallungthu 283 5167484 84 3364000
Total 1567 32504905 825 30422000
Scrutiny of relevant file and vouchers of JJM, the following observation were
made:-
I. Award of work without call of tender:
Para 14.1 of Central Public Works Department (CPWD) Works Manual, 2014
(which is being followed by State Govt) provides that tenders should be called for
all works costing more than ₹50,000 except in urgent cases, or when the interest
of works demand, works may be awarded by the EE without calling of tenders
subject to maximum ceiling of works upto ₹4.00 lakh and SE subject to ₹ 12.00
lakh.
Scrutiny of the record revealed that Executive Engineer Office, AWDDS, Aizawl PHE Department used to call Quotation/Tender for fixation of rates of
while implementing JJM under its Division, engage suppliers for providing GI pipes and GI specials through competitive bidding. Accordingly, the
pipes and GI special. The supplier were awarded supply orders value at ₹3.28
selected rates are approved through State Purchase Advisory Board
crore ranging from ₹68,290/- to ₹45,55,375 without calling for the tenders for the
execution of works. The supply order.
(SPAB) and Departmental Purchase Advisory Board (DPAB)
respectively. During the period covered by this audit also, rates and
corresponding firms are approved both for GI pipes and GI specials in
favour of NEZONE Pipes and Structure Gwahati, CL Enterprise Dawrpui
Aizawl and KT Thanga & Sons Aizawl respectively (copies of minutes of
SPAB enclose as annuxure???)
Accordingly, a majority of supply order amounting to ₹2.66 crore against
the supply orders value of ₹3.28 crore are (as per annexure I) indicated by the
audit were placed by only by the competent authorities like Engineer-in-Chief,
Chief Engineer and Superintending Engineer of PHE Department in favour of
those approved Firms only. As supply order were placed against these approved
firms, there is no question of calling tender or quotation again for these items for
the execution of works as far as supply order against NEZONE Pipes and
Structure Gwahati, CL Enterprise Dawrpui Aizawl and KT Thanga &
Sons Aizawl are concerned. Moreover, the competent authorities awarded
order against these approved firms within their financial delegated power
only. As such work order against these firms within the financial
delegated powers of the said competent authorities seems appropriate and
justified.
On the other hand, it is agreed with the audit that some supply orders were
placed beyond the financial delegated power of the officers without
calling tender. The balance amount of supply order valuing ₹ 62.15 lakh
out of ₹ 3.29 crore placed without tender mainly due to the following reasons:
1. Extreme urgency of works which necessitate availability of sufficient quantity
in time of GI special to complete the work for which sufficient time is not
available for calling and processing of Tender/Quotation.
2. Materials of the same brand and quality as that of the materials supplied by the
approved firm could also be supplied by the other firms for which work orders
were allotted to make the materials available as demanded.
3. As the financial power delegated to Sr.Executive Engineer PHED as per
CPWD manual is very limited it is practically not possible to make supply order
for sufficient quantity of GI materials within a short period for which necessary
approval was obtained from the competent authority to issue the supply orders in
the best interest of in the best the public and works
20mm U/Socket 602 752 150 109 16350 utilization of the material could be traced. Site Account of MR No.1/SD-II/JJM
40mm ɸ W/Valve 0 15 15 3106 46590
of 25.11.2019 and the page No. 1-5 of MB No.JJM/SDO-II (A) are enclosed as
40mm ɸ E/Tee 0 15 15 192 2880
40mm ɸ Socket 0 100 100 107 10700 annexure??? For ready reference.
Total 8,51,472
As seen in the table above, the department procure materials in excess of its actual
utilization for GI pipes and GI specials resulting in excess consumption of
expenditure amounting to ₹8,51,472/-.
As seen in Table above, the rate for Sl.No.1,2 and 3 includes cost of pipes, labour
charge and GI specials. As per E-in-C circular vide.
D-15015/1/2016-E-in-C/PHE/20 Dt. 05.02.2019 on rate of pipes and
W.12015/19/2008-E-in-C/PHE/105 Dt.21.02.2019 on laying rate, it can be
assumed that 40mm pipes were laid at a depth of 100 cm and 20mm pipes at
50cm depth. However, breakup of each component included in the rate could not
be ascertained as the estimates were not based on SOR of MPWD and the
department’s analysis of rate was not produced to audit.
It was also noticed that the average expenditure incurred on Labour (MR) during
2019-20 and 2020-21 was 46.80% and 51.08% of the total expenditure. But in the
absence of vital records, audit could not verify the admissibility of the estimated
rates.
The department may intimate the basis on which these estimates were prepared.