You are on page 1of 1

QUOTATION

NO Discription Quantity Unit Price (Rp) Item Cost(Rp)


I FOUNDATION INTALLATION 64 MTS
1 Measurement installation of bowplank 24 m2 15,000.00 360,000.00
2 Excavation soil foundation 65.5 m3 45,000.00 2,947,500.00
3 Work beak fill soil in Foundation 15.40 m3 25,000.00 385,000.00
4 Install sand under Fondation 3.2 m3 160,000.00 512,000.00
5 Foundation River stone installation -8.5 M3 28.33 m3 550,000.00 15,581,500.00
6 Concreat coloum 20cm x 20 cm 1.7 m3 1,600,000.00 2,720,000.00
7 Metal iron intallation @12mm,6mm 21.3 m1 45,000.00 958,500.00

TOTAL COST 23,464,500.00

II SHELTER WATER FILTER


1 Shelter 1, inclued gutterand water profing 1 unt 12,500,000.00 12,500,000.00
2 Shelter 2, inclued gutterand water profing 1 unt 16,700,000.00 16,700,000.00
TOTAL COST 29,200,000.00

III INSTALL WATER STOP ALUMINIUM 13 M1 110,000.00 1,430,000.00


TOTAL COST 1,430,000.00

IV INSTALL GLASS WATER STOP 22 M1 95,000 2,090,000.00


TOTAL COST 2,090,000.00

V PARKING AREA
1 Measurement of bowplank 6 M2 45,000 270,000.00
2 Excavation soil 9 M3 150,000 1,350,000.00
3 Foundation stone installing 4.5 m3 550,000 2,475,000.00
4 Slab akses installing 1.5 m1 800,000 800,000.00
5 screet floor 7 m2 45,000 315,000.00
6 paving brick installing 6 m2 160,000 960,000.00
7 stair 1.5 m1 1,400,000 1,400,000.00

TOTAL COST 7,570,000.00

GRAND TOTAL 65,844,500.00


READY PAY SHELTER 11,000,000

FINISH TOTAL 54,844,500.00

You might also like