New - Heat Stress Plan - Fire Water Line Tank #107
New - Heat Stress Plan - Fire Water Line Tank #107
PURPOSE: to standardize the preparation of Heat Stress Management Plans and to verify that ALL MINIMUM requirements are considered & implemented.
SCOPE: applicable to any SA facility. Each Contractor shall prepare a HSMP for its activities. SAPO may be required to prepare a general HSMP applicable to
the T&I/Project site.
MARK EACH BOX WITH A WHERE APPLICABLE, AND WITH AN X WHERE IS NOT APPLICABLE.
HEAT STRESS MANAGEMENT PLAN WILL NOT EXCEED 30 DAYS
(CRDD)-Central Region Distribution
DEPARTMENT/PROJECT START DATE 07/05/23 END DATE 08/04/23
Department
EQUIPMENT New OME Building ENTITY EXECUTING THE JOB Mastoura Company
UNIT North Riyadh Tank Unit NUMBER OF EMPLOYEES As per the work permit
DIVISION NRTU-DISTRIBUTION OPS DIV. NUMBER OF SUPERVISORS As per work Activity
MANUAL EXCAVATION TO INSTALL CAMERA FROM OME BUILDING TO FIRE WATER LINE TANK #107
SCOPE OF WORK
EXCAVATION – (DEPTH .60 CENTIMETER) (WIDTH40.CENTIMETER)
WORK SCHEDULE From 07:00 AM □ PM 03:30 □ AM PM 24 hrs. SCHEDULE □ Yes No Notes:08-HRS 30mins
STOP
BREAK PERIODS 10-minutes every 45-minutes(1-cup every 15-mins From:12:00 □AM PM To: 13:00 □ AM PM
PERIODS
For Confined Space: __________________ MINIMUM 2-MEN TEAM “BUDDY SYSTEM” PROTOCOL
ROTATIONS OF IN PLACE (MANDATORY DURING CATEGORY 4 – RED)
PERSONNEL For Sun-exposed personnel:
Yes □ No Activity
30-mins minimum 2-Men Team “Buddy System Rotation”
TYPES OF SHELTERS PROVIDED (describe structure type, dimensions, covering material, ventilation or A/C). INCLUDE NUMBER OF
SHELTERS/SHADING FOR INDIVIDUALS (e.g.: Flagman, Manual Ground Breaking, others) SHELTERS
2. Rest Shelter is 4-meter length with 4-meter width 1. (1)Rest Shelter
4. Rest Shelter is Approximately 30 to 40 meter away at working area. 2. (1)-Umbrella
6. Standby Man /Heat stress Device and Checklist and for Monitor Heat stress Flag 3.
8. 1-pcs of Portable Umbrella shading for standby man 4.
Rotation □ Mechanical Ventilation AIR TEMPERATURE AND HUMIDITY
PRECAUTIONS FOR CSE
□ A/C □ Water Supply inside □ Cooling Vests □ Others MONITOR ON SITE
Daily Talks Signs Displays Flags □ Others Standby
AWARENESS Yes □ No (Hour Inspection)
man
WATER SUPPLY Cool Water Dispensers within 100 m:Yes Individual Disposable Cups □ Individual 2 liters Bottle
OTHER □ Can Mechanical/powered assistance replace manual labor? Specify:___ □ Shaded Jobsites (Specify):
CONTROLS: Others Umbrella single shade for standby man & Rest shelter for workers
Above 43°C (110°F), air chillers or A/C shall be provided on Confined Spaces or similar enclosed work areas
NOTES: