Document Risk Assessment

Abu Dhabi Future School Program - Phase 8,


Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

Project Abu Dhabi Future School Program - Phase 8, Package 1, Al  Falah KG

Employer MUSANADA Contract No.

Consultant: Al Suweidi Engineering Consultant LLC Date: Rev-00

Contractor Al Eslah General Contracting Est Document No.

RISKASSESSMENT TEAM SITE REPRESENTATIVES

NAME DESIGNATION SIGNATURE NAME DESIGNATION SIGNATURE

Eng. Ayham Sabouni Project Manager Ahmed Hajeer Project Engineer

Eng.Zafeer Arif OSH Coordinator

Subject RISK ASSESSMENT for Blockwork Construction

NOTE:- This Risk Assessment is prepared in line with the METHOD STATEMENT for Blockwork Construction Rev. 00; and it covers all activities
described in this Method Statement.

Page 1 of 1
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Site OSH induction course for every


Parking at live worker working in this project.
road to drop or  Bus should be park at safe area with
carry workers. double indicators and gate should not OSHAD-SF– Codes
open until bust fully stop. Construction of Practice CoP
Unfamiliar with the
local situation and  Worker should not cross the road manager, 44.0 Traffic
the Safety rules until bus is move from road to clear Management and
OSH In Logistics – Version
sight for upcoming traffic.
1 Unfamiliar to the charge, 3.0
Mobilization of  Proper training and guidance for all
nature of work and Employees 1 1 1 L
Employees 3 2 6 M new workers HR staff,
weather condition OSHAD-SF –
 Minimum PPE must be worn at all Supervisor Codes of Practice
Lack of training times CoP 08.0 – General
&
 Follow site safety rules Workplace
Younger workers  Follow the traffic safety regulations Individuals Amenities – Version
Medically not fit  Medical Check up to be done 3.0
 Special care for young people and
should not be involved in high risky
work

2 Material Delivery Falling of Workers, 3 4 12 H  Ensure that all the pickup driver AEGC 1 3 3 L OSHAD-SF–COP
on Site materials Drivers, company/supplier are informed about 1.0 – Hazardous
Collision of Property the project safety requirements prior Materials - V 3.0
delivery damage, to the delivery of the materials. OSHAD-SF–COP
truck/pick up flagman, public  Ensure that the road access from the 2.0 – Personal
with men and site entrance to the storage area will Protective
materials. be properly leveled, maintained and Equipment - V 3.0
OSHAD-SF – COP
Slips, Trips & compacted.
4.0 – First Aid and

Page 1 of 2
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

falls,  Ensure that all drivers and vehicle Medical Emergency


Pickup trucks comply with the safety requirements. Treatment - V 3.0
toppling over  Ensure that the delivery truck is OSHAD-SF –COP
Damaging exiting inspected at the project gate by the 08.0 – General
utilities ( Street security and safety personnel to Workplace
light poles, etc ) check if the load/material is secured Amenities – V 3.0
Unsafe storage of properly, the vehicle doesn’t have any OSHAD-SF –COP
14.0 – Manual
materials. defects ( leaks, damages)
Handling and
Unsafe unloading  Ensure that the drivers have
Ergonomics – V 3.0
of materials adequate PPE
OSHAD-SF –
Delivery during  Ensure that the drivers are provided COP 17.0 – Safety
night time. with a visitor induction at the site Signage and
entrance ( they are instructed/ Signals – V 3.0
informed about the site rules, driving OSHAD-SF- COP
speed limit, storage areas, 22.0 – Barricading
emergency procedures etc) of Hazards – V 3.0
 Ensure that they are guided by OSHAD-SF –COP
trained banksman towards the safe 36.0 – Plant and
storage zone. Equipment – V 3.0
 Ensure that AEGC provides a safe OSHAD-SF–COP
and clear vehicle access for the 44.0 Traffic
delivery trucks/pick ups. Management and
Logistics – V 3.0
 Separate pedestrian access to be
OSHAD-Sf–
used by pedestrians.
Element 2 - Risk
 Ensure that there is adequate lighting
Management
is provided if the delivery is done at OSHAD-SF –
night. Element 3 –

Page 1 of 3
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Ensure that the access ways are Management of


demarked with cones and warning Contractors
tape to prevent them from going too OSHAD SF-
close to the edges of the access Element- 5 –
ways. Training &
 Ensure that the pickup truck have awareness and
reverse alarm and beacon light. competency
OSHAD-SF–
 Ensure that there is enough distance
Element 6 -
maintained between the delivery
Emergency
access way and the pedestrian way.
Management
 No unauthorized personnel to enter Musanada Key HSE
the storage area while the material is Requirements
being unloaded.
 Adequate signage is displayed
around the access ways and the
storage areas.
 Ensure that the public property/
materials which are near the storage
area are protected and barricaded
with hard PVC barriers.
 Ensure that the materials are stored
safely on the project and storage is in
location as approved in the logistic
plan.
 Ensure that hazardous material if any
is stored in safe area and proper
precaution is taken as per the MSDS

Page 1 of 4
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

or supplier’s recommendation.
 Ensure that mechanical aid is being
used for unloading materials of
heavy materials
 Ensure that workers wear adequate
ppe while handling/unloading
materials.
 Ensure that there is a certified First
Aider and adequate first aid facility
available on site.

3 Using heavy Falling of Workers, 3 5 15 EH  Ensure that routes, access ways are AEGC 1 3 3 L OSHAD-SF – COP
equipment for materials personnel as per the approved traffic 4.0 – First Aid and
shifting material Collision of nearby, management plan. Medical Emergency
from store to site property Treatment - V 3.0
delivery  Access routes are well lit, maintained,
damage OSHAD-SF –COP
truck/pick up compacted. 08.0 – General
with men and  Designated parking areas to be Workplace
materials. provided for the equipment. Amenities – V 3.0
Slips, Trips &  Ensure that all heavy equipment used OSHAD-SF –COP
falls, to shift blocks & their operators to be 14.0 – Manual
Pickup trucks 3rd party certified. Handling and
Ergonomics – V 3.0
toppling over  All operators and workers involved in
OSHAD-SF –
Damaging exiting shifting blocks to be trained prior to COP 17.0 – Safety
utilities ( Street the start of the works. Signage and
light poles, etc )  Safe access and egress to be Signals – V 3.0
Unsafe storage of provided and maintained at all times. OSHAD-SF– COP
materials.  Separate pedestrian access to be 21.0 – Permit to
Unsafe unloading provided. Work Systems - V
3.0

Page 1 of 5
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

of materials  Demarcation to be done on the OSHAD-SF- COP


Delivery during access routes for the heavy 22.0 – Barricading
night time equipment. of Hazards – V 3.0
OSHAD-SF –COP
 Ensure that certified banksman/
34.0 – Safe use of
flagman are giving signals to the lifting Equipment
operators of heavy equipment. and Lifting
 Ensure adequate lighting is provided accesories – V 3.0
during the night shift or in dark areas OSHAD-SF –COP
while the shifting works are being 36.0 – Plant and
carried out. Equipment – V 3.0
OSHAD-SF–COP
 Blocks to be stored in designated
44.0 Traffic
areas. Safe stacking to be done. Management and
 Ensure that materials (blocks) are not Logistics – V 3.0
stored above head level. OSHAD-SF –
 Only approved palettes from the Element 2 - Risk
manufacturer to be used under the Management
blocks. OSHAD SF-
Element- 5 –
 If the blocks are to be lifted to a
Training and
higher level, ensure that the area is awareness and
cordoned off and signage displayed competency
to prevent workers from standing OSHAD-SF –
beneath the lifting zone. Element 6 -
 Ensure that lifting permit is obtained Emergency
prior to the start of shifting, if the Management
Musanada Key HSE
blocks are to be lifted to a higher level
Requirements
using a mobile crane. Trained and
certified personnel to carry out the

Page 1 of 6
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

lifting activity.
 Loose blocks not to be lifted unless
they are in a certified basket.
 Ensure that the existing utilities are
barricaded to prevent any damage.
 Ensure that traffic is maneuvered
safely .i.e.one way traffic, Convex
traffic mirrors installed at blindspots,
certified flagman giving signals, No
reversing in limited workareas or
near workers etc.
 Speed limit signage to be displayed

4 Use of Hand Striking hand or Workers, 3 3 9 H  Proper body position and safety glass AEGC 1 2 2 L OSHAD-SF –COP
Tools arms when using Personnel with side shields. 08.0 – General
hammer walking nearby  Training to be provided to the workers Workplace
Struck by flying prior to the start of the works. Amenities – V 3.0
object metals  Tool to be suitable for the purpose OSHAD-SF –COP
chips etc. intended and maintained in good 14.0 – Manual
Eye injuries working order. Tools to be inspected Handling and
Ergonomics – V 3.0
Laceration when regularly in accordance with
OSHAD-SF– COP
using sharp tools manufacturer’s instructions.
47.0 – Machine
Defective tools  Hand gloves, Safety glasses should
Guarding Version
be used when using hand tools. 3.0
 All operatives to be given instructions OSHAD-SF – CoP
in the safe use of hand tools as part 36.0 – Plant and
of their skill training. Tools which may Equipment – V 3.0

Page 1 of 7
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

3.0
OSHAD-SF –
COP 35.0 –
Portable Power
deteriorate are to be checked on a Tools – Version 3.0
regular basis and maintained or OSHAD-SF –
replaced as necessary. Element 6 -
 First Aider and First Aid items to be Emergency
made available on site. Management
 Ensure that cables are routed safely OSHAD-SF –
and don’t pose a tripping hazard for COP 4.0 – First Aid
the workers/engineers etc and Medical
Emergency
Treatment - V 3.0
Musanada Key HSE
Requirements

5 Use of Power Electrocution Workers, 3 4 12 H  Ensure that all power tools are AEGC 1 3 3 L OSHAD-SF–COP
Tools Hand Injury Engineers regularly inspected and approved & 2.0 – Personal
Eye Injury tagged with identification number by Protective
Body Injury competent Electrician on regular Equipment - V 3.0
Noise basis prior to the start of the works. OSHAD-SF–COP
Dust  Broken/damaged power tools would 3.0 – Occupational
Slips, Trips, falls, not be used/stored on site. Noise-V 3.0
 Only competent and trained person to OSHAD SF – Codes
use power tools. of Practice CoP
 Ensure that the electrical cables are 15.0 – Electrical
routed safely. Safety – Version 3.0

Page 1 of 8
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Ensure that all connections are OSHAD-SF – COP


industrial type. No domestic plugs 4.0 – First Aid and
and sockets allowed. Medical Emergency
 Ensure that all electrical cables of Treatment - V 3.0
portable equipment are in good OSHAD-SF –COP
condition, without cracks and free of 08.0 – General
non-standard joints. Workplace
 No works to be carried out during Amenities – V 3.0
rain/wet condition. OSHAD-SF –
 Ensure that adequate signage is Codes of Practice
displayed ( PPE Compliance, CoP 35.0 – Portable
Power Tools –
Unauthorized access)
Version 3.0
 Ensure appropriate PPE (Safety OSHAD-SF– Codes
Glasses, safety shoes, Hand gloves, of Practice COP
Ear plugs, etc) is worn by workers 47.0 – Machine
using power tools. Guarding Version
 All Hand tools must be in good OSHAD-SF –
working condition. COP 17.0 – Safety
 Ensure that Noise related signage is Signage and
displayed near the test zone when Signals – V 3.0
grinding works are being carried out. OSHAD-SF –COP
 Ensure that the area is barricaded 53.0 - OHS
and no unauthorized personnel are Management During
allowed in the area. Personnel Construction Work –
V 3.0
working in the test zone to wear dust
OSHAD-SF –
mask.
Element 2 - Risk
Management

Page 1 of 9
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key HSE
Requirements
6 Use of concrete Eye injury, Workers, 3 5 15 EH  Ensure that all workers are trained by AEGC 1 3 3 L OSHAD-SF–COP
nail gun Noise Personnel a representative of manufacturer prior 2.0 – Personal
Hand Injury working nearby to the start of the works. Protective
Body Injury  Ensure that only competent & train Equipment - V 3.0
personnel carry out nail gun works. OSHAD-SF – COP
 Ensure that the gun is inspected and 3.0 – Occupational
approved and tagged by competent Noise – V 3.0
electrician & HSE on site. OSHAD-SF – COP
 Ensure that only approved cartridge 4.0 – First Aid and
is used i.e should be from an Medical Emergency
approved supplier. Treatment - V 3.0
 Ensure that adequate ppe is worn OSHAD-SF –COP
while handling of concrete nail gun 08.0 – General
( Ear plugs, Hand gloves and safety Workplace
Amenities – V 3.0
glasses ).
 Ensure that if there are any defects in OSHAD-SF –
the gun, the work should be stopped COP 17.0 – Safety

Page 1 of 10
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

and the supervisor to inform the HSE Signage and


department immediately. Also no Signals – V 3.0
repairs to be carried out on site. The
OSHAD-SF – COP
gun has to be sent to the supplier/ 35.0 – Portable
manufacturer for repair. Power Tools – V 3.0
 Ensure that issue of cartridge tools OSHAD-SF –
and cartridges shall be strictly Element 2 - Risk
controlled. Management
 Ensure that cartridge tools and OSHAD SF-
cartridges shall remain in the Element- 5 –
possession of the person to whom Training and
they are issued; awareness and
competency
OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key HSE
Requirements
7 Blockworks Back injury while Workers , 3 4 12 H  Ensure that all workers carrying out OSHAD-SF–COP
lifting/ shifting Engineers, block work to be trained prior to the 2.0 – Personal
blocks. Consultants, start of their works Protective
Crush injury Personnel  Ensure that the workers are getting Equipment - V 3.0
( Fingers, Hand, working nearby daily Toolbox talks from competent OSHAD-SF – COP
Foot ) foreman & HSE Representative. 3.0 – Occupational
Falling of block  Ensure that the block cutting is done Noise – V 3.0
(s) on personnel by a Motor Driven Saw and not by OSHAD-SF – COP
working below. 4.0 – First Aid and

Page 1 of 11
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Falling of men angle grinder. Medical Emergency


( from  Only trained personnel to carry out Treatment - V 3.0
scaffolding/highe the cutting works.
OSHAD-SF –COP
r platform).  All Electrical connections for the 08.0 – General
Slips, Trips and cutting machine to be done by Workplace
falls competent Electrician. Amenities – V 3.0
Waste  Ensure that the cutting machine OSHAD-SF –COP
Management guards are tampered with. 14.0 – Manual
Electrocution  Ensure adequate signage is Handling and
displayed in the cutting zone. Ergonomics – V 3.0
 Ensure the cutting area is barricaded OSHAD SF –COP
to prevent unauthorized access. 15.0 – Electrical
 Ensure that the workers carrying out Safety – V 3.0
cutting works comply to the PPE OSHAD-SF –
requirements (Hand Gloves, Safety COP 17.0 – Safety
face shield, Ear plugs, Dust mask). Signage and
 All Electrical Cables to be routed Signals – V 3.0
safely to prevent tripping hazard. OSHAD-SF- COP
 Ensure that the blocks are carried on 22.0 – Barricading
of Hazards – V 3.0
site using mechanical aid. Prevent
workers from carrying heavy blocks. OSHAD-SF– COP
 Manual handling training to be given 23.0 – Working at
Heights– V 3.0
to workers who are handling blocks.
 Ensure adequate PPE is worn by OSHAD-SF –COP
workers who are handling blocks. 26.0 – Scaffolding –
V 3.0
 Ensure that safe working platform is
provided for the masons, workers to OSHAD-SF – COP
35.0 – Portable

Page 1 of 12
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

carry out their works. The platform to Power Tools – V 3.0


be erected by competent Scaffolders
OSHAD-SF–COP
and approved and tagged by
47.0 – Machine
Competent Scaffolding supervisor. Guarding V 3.0
The working platform to have
OSHAD-SF –COP
adequate fall protection ( Top rail, Mid 53.0 - OHS
rail etc) Management During
 The working platform to have toe Construction Work –
boards to ensure that the materials V 3.0
don’t fall on workers below. OSHAD-SF–COP
 Ensure that workers on platform 54.0 – Waste
above 1.8 meters don a safety Management – V –
harness and tie them to a safe 3.0
anchorage point. OSHAD-SF –
 Ensure that the area beneath the Element 2 - Risk
block work is barricaded and Management
adequate signage is displayed. OSHAD SF-
 Ensure that only inspected and Element- 5 –
approved hand tools are used by the Training and
awareness and
workers.
competency
 Regular housekeeping to be done
near the block cutting area to prevent OSHAD-SF –
Element 6 -
trip hazard.
Emergency
 Ensure that the cut pieces are Management
segregated away and are stored in a
Musanada Key HSE
designated area. Requirements
 Ensure that the block left overs/

Page 1 of 13
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

debris are disposed of as per the


requirements of Center of waste
Management.

8 Using Block Noise Workers, 3 5 15 EH  Ensure that trained and competent AEGC 1 3 3 L OSHAD-SF–COP
cutting Saw Vibration personnel personnel carry out block cutting 2.0 – Personal
Cut injury nearby work. Protective
Electrocution  No unauthorized personnel to carry Equipment - V 3.0
Slips, trips and out block cutting works. OSHAD-SF – COP
falls  Ensure that workers comply to the 3.0 – Occupational
Foreign particles PPE requirements while doing block Noise – V 3.0
OSHAD-SF – COP
cutting works ( safety glasses, ear
3.1 – Vibration – V
plugs, dust masks etc)
3.0
 Ensure that block cutting workers are
OSHAD-SF – COP
allowed to take frequent breaks. Or 4.0 – First Aid and
works to be carried out in shifts to Medical Emergency
prevent hand arm vibration. Treatment - V 3.0
 Ensure that a designated area is OSHAD-SF –COP
assigned for block cutting 08.0 – General
 Signage and barrication to be Workplace
provided to prevent unauthorized Amenities – V 3.0
access. OSHAD-SF –COP

Page 1 of 14
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Ensure regular housekeeping is done 14.0 – Manual


in order to prevent slip, trip hazard. Handling and
 Ensure that all the electrical Ergonomics – V 3.0
connections are done by competent OSHAD SF –COP
electricians and no modifications and 15.0 – Electrical
connections are done by Safety – V 3.0
unauthorized personnel. OSHAD-SF –
COP 17.0 – Safety
 Ensure that all electrical cables are
Signage and
routed safely and there are no cracks,
Signals – V 3.0
unsafe joints on the electrical cables.
SHAD-SF- COP
 Ensure that the cutting zone is away 22.0 – Barricading
from access ways and traffic routes. of Hazards – V 3.0
 Ensure that no guards or enclosures OSHAD-SF –COP
are removed from the block cutting 36.0 – Plant and
machine. Equipment – V 3.0
OSHAD-SF–COP
44.0 Traffic
Management and
Logistics – V 3.0
OSHAD-SF –
Element 2 - Risk
Management
OSHAD SF-
Element- 5 –
Training and
awareness and
competency
OSHAD-SF –

Page 1 of 15
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Element 6 -
Emergency
Management
Musanada Key HSE
Requirements
9 Using motor Noise Workers, 3 4 12 H  Ensure that only trained and AEGC 1 3 3 L OSHAD-SF–COP
mixing machine Contact with personnel competent personnel using the motor 2.0 – Personal
chemicals nearby mixing machine. Protective
Risk of  Ensure that workers comply to the Equipment - V 3.0
Entanglement PPE requirements( Hand gloves, ear OSHAD-SF – COP
plugs, Dust Mask etc ). No loose 3.0 – Occupational
clothing. Noise – V 3.0
OSHAD-SF – COP
 Ensure that trained and competent
4.0 – First Aid and
personnel carry out motor mixing
Medical Emergency
machine.
Treatment - V 3.0
 No unauthorized personnel to carry OSHAD-SF –COP
out motor mixing works. 08.0 – General
 Ensure that workers are allowed to Workplace
take frequent breaks. Or works to be Amenities – V 3.0
carried out in shifts OSHAD-SF –COP
 Ensure that a designated area is 14.0 – Manual
assigned for motor mixer Handling and
 Signage and barrication to be Ergonomics – V 3.0
provided to prevent unauthorized OSHAD SF –COP
access. 15.0 – Electrical
 Ensure regular housekeeping is done Safety – V 3.0
in order to prevent slip, trip hazard. OSHAD-SF –
COP 17.0 – Safety

Page 1 of 16
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Signage and
Signals – V 3.0
SHAD-SF- COP
22.0 – Barricading
of Hazards – V 3.0
OSHAD-SF –COP
 Ensure that all the electrical 36.0 – Plant and
connections are done by competent Equipment – V 3.0
electricians and no modifications and OSHAD-SF–COP
connections are done by 44.0 Traffic
unauthorized personnel. Management and
 Ensure that all electrical cables are Logistics – V 3.0
routed safely and there are no cracks, OSHAD-SF –
unsafe joints on the electrical cables. Element 2 - Risk
 Ensure that the motor mixing zone is Management
away from access ways and traffic OSHAD SF-
routes. Element- 5 –
 Ensure that no guards are removed Training and
awareness and
from the motor mixer.
competency
OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key HSE
Requirements
10 Working at Falling of men Workers, 3 4 12 H  Ensure that safe working platform is AEGC 1 3 3 L OSHAD-SF–COP
Heights ( Near and materials personnel provided for the workers carrying out 2.0 – Personal
edges, on Collapse of Protective

Page 1 of 17
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Scaffolds etc) scaffolds. nearby etc. the block works Equipment - V 3.0
 Ensure that the working platform is OSHAD-SF–COP
erected, modified and dismantled only 2.0 – Personal
by competent, certified and trained Protective
Scaffolders. Equipment - V 3.0
 The platform to be inspected and
approved tagged by a competent OSHAD-SF –
COP 17.0 – Safety
scaffolding supervisor
Signage and
 Ensure that the working platform has
Signals – V 3.0
adequate fall protection ( Toe boards,
SHAD-SF- COP
Mid rails, Top rails) NO Works to be 22.0 – Barricading
carried out on scaffolds with no of Hazards – V 3.0
edge/fall protection. OSHAD-SF– COP
 All workers to comply with PPE 23.0 – Working at
requirements ( Safety harness –with Heights– V 3.0
double lanyard, hand gloves etc while OSHAD-SF –COP
working about 1.8 meters secured to 26.0 – Scaffolding –
a safe anchorage point. V 3.0
 When works are carried out near the OSHAD-SF –COP
edges at height, fall preventing 36.0 – Plant and
control measures to be adopted like Equipment – V 3.0
safety harness anchored to a safe OSHAD-SF–COP
44.0 Traffic
anchorage point, retractable fall
Management and
arrestors etc.
Logistics – V 3.0
 Training to be provided to workers for
OSHAD-SF –
working at heights, PPE compliance. Element 2 - Risk
Management

Page 1 of 18
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

OSHAD SF-
Element- 5 –
 Adequate signage to be displayed Training and
 Unauthorized access into the area to awareness and
be controlled. competency
 Regular housekeeping to be done in OSHAD-SF –
the area to ensure that there are no Element 6 -
slips, trip hazard. Emergency
Management
Musanada Key HSE
Requirements
11 Handling of Contact with Workers, Staff, 3 3 9 H  MSDS for Portland cement, bitumen AEGC 1 3 L OSHAD-SF –
chemicals chemicals Visitors waterproofing, to be made available CoP 1.0 –
( preparation & 3 Hazardous
and the workers to be trained
mixing, regarding the safe usage ( PPE, Materials - Version
application of emergency preparedness ) 3.0.
mortor, Bitumin  Ensure that PPE (Respirators, Hand OSHAD-SF – CoP
waterproo-fing ) Gloves, Safety glasses etc) is worn 2.0 – Personal
Protective
as mentioned in the MSDS while
Equipment - Version
handling the chemicals.
3.0
 Ensure that Chemicals are stored in a
OSHAD-SF –
safe storage area as recommended in Element 2 - Risk
the MSDS (Material Safety Data Management
Sheet). OSHAD SF-
 Ensure that the area is barricaded Element- 5 –
while carrying out the works. Training and
awareness and
competency

Page 1 of 19
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

OSHAD-SF –
Element 6 -
Emergency
Management
Musanada Key HSE
Requirements
 Ensure all materials are stored safely OSHAD-SF – CoP
 Access and egress to be kept clear at 8.0 – General
Workers, Staff all times. Workplace
Tripping hazards 2 4 8 H AEGC 1 2 2 L
 Regular housekeeping to be carried Amenities Version
out. 3.0

OSHAD-SF - CoP
22.0 – Barricading
 Ensure the area is barricaded and of Hazards –
Workers, Suitable Signage is displayed to Version 3.0
Unauthorized
Public, Staff 2 4 8 H prevent unauthorized access is AEGC 1 2 2 L
access OSHAD-SF –
prohibited. CoP 17.0 – Safety
Signage and
Signals – V 3.0

12 Disposal of Environment Environment 3 3 9 H  All chemicals must be received, AEGC 1 3 3 L OSHAD-SF – CoP
concrete blocks, Concerns. stored and handled according to 54.0 – Waste
chemicals in Noncompliance to prescribed procedures in the MSDS. Management –
normal trash Estidama ,  All workers will be trained how to Version – 3.0
Centre of waste segregate hazardous waste and its OSHAD-SF– CoP
management proper disposal as per the Main 1.0 – Hazardous
guidelines Contractors and Abu Dhabi

Page 1 of 20
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Municipality guidelines. Materials - V 3.0


 TBT to be conducted and instructions
OSHAD SF-
to be given to workers regarding the
Element- 5 –
safe disposal of waste as mentioned
Training and
in the MSDS. awareness and
competency

13 Emergency Fire All personnel 3 4 12 H  All personnel to be safety inducted. AEGC 1 3 3 L OSHAD-SF –
situations Collision  Train and inform all employees Codes of Practice
Electrocution regarding fire Emergency Evacuation CoP 17.0 – Safety
Failure to Plan. Signage and
Evacuation  Initiate and maintain good Signals – Version
housekeeping 3.0
 Ensure that all materials used in porta OSHAD-SF –
Codes of Practice
cabin construction are fire rated.
CoP 43.0 –
 Ensure that enough firefighting
Temporary
equipment are made available on
Structures - Version
site. ( Fire Ex., Fire Hose Reel) 3.0
 Ensure that fire alarm and Fire siren OSHAD-SF –
are available on site and are fully Codes of Practice
functional. CoP 08.0 – General
 No smoking in non-designated areas. Workplace
 Ensurre that smoke detectors are Amenities – Version
installed inside all offices. 3.0
 Ensure that workers are trained- how OSHAD SF-
to fight fire, what to do in case of an Element- 5 –
emergency Training and
awareness and

Page 1 of 21
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

 Ensure that enough assembly points


are made available on site and
access to them is kept clear at all
competency
times.
OSHAD-SF –
 Ensure emergency numbers are
Element 6 -
posted at strategic locations.
Emergency
 Ensure that Evacuation plan is posted Management
on notice boards and all are informed
about it during inductions.

Method Statement & Risk Assessment handover


Date: _ _ / _ _ /_ _ _

I have read, understood and accept the conditions of this method statement & Risk Assessment.
Name of Job Supervisor/Foremen/Site Engineer: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
Signature: _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _
All operatives involved with this job must sign below
I have read, understood and accept the conditions of this method statement and Risk Assessment.

Page 1 of 22
RISK ASSESSMENT
Document Risk Assessment
Abu Dhabi Future School Program - Phase 8,
Ref: No AEGC-KG-RA - 019
Package 1, Al  Falah KG Sector 1C plot P3
Rev. 00
Date.

RISK LEVEL RESIDUAL RISK LEVEL


S.No Activity HAZARD & RISK Groups Exposed Control Measures Action By Legal Reference
P S R RL P S R RL

Sr. Emirates ID
Name Emp. No. Designation Date Signature Remarks
No. No
1
2
3
4
5
6
7
8
9
10
11
12
13