Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Manual handling Back pain, Work related upper ☒Employees Approved method Statement / Risk assessment must be in place ☒ Project Manager
A59 of Blocks and lower limb disorders, hand prior to start the work activity
☒ Construction
injuries/ bruises, back, chest Ensure Job safety analysis (JSA) /Prestart briefing/TBT is given.
(Shifting, Lifting) ☒Contractor Manager
pain Mechanical aid like Trolley suitable tools and equipment must be
s / Sub used on site ☒ Project Engineer
Regular breaks should be ensured to limit the frequency of ☒ Foremen
Cut, skin contamination leading 2 3 6 handling blocks ☒ HSE for monitoring
to dermatitis Workers should be trained in steps for safe handling of blocks
and proper posture to follow during lifting and shifting of blocks.
1 2 2
Hand gloves should be worn for firm grip and help prevent cuts
Dust from block debris
Adequate platform should be provided when shifting blocks on
leading to respiratory work areas
problems, eye irritation The risks involved should be properly communicated to workers
in regard to the risks involved in bad postures
Heavy blocks should not be carried by one workers, assistance
should be given by pairing 2 workers to a block. (multiple person
Approved by Name Nasser Ahour Designation Project Manager Signature Date 09-07-19
Note: Risk assessment should be completed by a site team member and a member of the safety department if possible
PIC-HSE-FRM-RA-001
RISK ASSESSMENT FORM
Project: Park Point 5AB Date: 09.07.2019 Reference Number: A59
Revision Number: 00
Risk Assessment completed by: Legislation: This risk assessment is in compliance with:
Name: Everistus Chukwumaeze Federal Law No8, Year 1980, Ministerial Order No 32 and (Tick box):
☐OSHAD ☒Dubai municipality ☐EHS Trakhees
Designation: HSE Manager Signature: ☐Other (List)……………………………………
Description of the Task: RISK ASSESSMENT FOR BUILDERS WORK
RISK RATING RISK LIKELIHOOD
RATING
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
lifting)
Workers should be selected prior lifting or shifting blocks and only
workers that are fit enough should engage in such.
Pre-employment screening should be ensured to help detect
those masons that already have ill health effect due to manual
handling and regular health surveillance should be ensured.
Mask should be worn to prevent dust inhalation, Safety goggles
should be worn to prevent particles from entering the eyes.
A59 Working at height Manual Handling – Poor postures ☒Employees Ensure Job safety analysis (JSA) /Prestart briefing/TBT is given. 1 2 ☒ Project Manager
using scaffolding leading Injury to Personnel Mechanical methods to be used where possible, or multiple ☒ Construction
structure for fixing ☒Contractor person lifting. 2 Manager
Collapse of scaffolding leading to Toe board should be put in place around scaffolding structures to
blocks injury, Fatality and damage of s / Sub ☒ Project Engineer
prevent materials/blocks from falling from height
property ☒ Foremen
Approved by Name Nasser Ahour Designation Project Manager Signature Date 09-07-19
Note: Risk assessment should be completed by a site team member and a member of the safety department if possible
PIC-HSE-FRM-RA-001
RISK ASSESSMENT FORM
Project: Park Point 5AB Date: 09.07.2019 Reference Number: A59
Revision Number: 00
Risk Assessment completed by: Legislation: This risk assessment is in compliance with:
Name: Everistus Chukwumaeze Federal Law No8, Year 1980, Ministerial Order No 32 and (Tick box):
☐OSHAD ☒Dubai municipality ☐EHS Trakhees
Designation: HSE Manager Signature: ☐Other (List)……………………………………
Description of the Task: RISK ASSESSMENT FOR BUILDERS WORK
RISK RATING RISK LIKELIHOOD
RATING
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Scaffolding should not be overloaded with materials/Blocks and ☒ HSE for monitoring
2 4 8 should be used only for its purpose.
Heat stress leading to personal ill
Scaffolding structure used in block work should be inspected
health, fainting, dehydration,
fatality Manual Handling assessment prior to use of tools. And good
postures should be maintained.
Fall of materials / blocks from The risk involved in working under direct sunlight should be well
height leading to body part injury communicated to workers and precautions like taking cool
drinking water, taking rest in shaded area frequently, job rotation,
Falling of workers from height light clothing appropriate for the weather should be worn etc.
leading to fractures, Fatality Adequate job planning should be ensured with supervision and
monitoring of task
Access on scaffolding platform should not be blocked to prevent
slip, trip and falling from height, proper housekeeping
arrangement and material/block stacking should be ensured
Only competent trained Scaffolders (from Trakhees / DM
approved 3rd party training provider) should erect the scaffolding.
Approved by Name Nasser Ahour Designation Project Manager Signature Date 09-07-19
Note: Risk assessment should be completed by a site team member and a member of the safety department if possible
PIC-HSE-FRM-RA-001
RISK ASSESSMENT FORM
Project: Park Point 5AB Date: 09.07.2019 Reference Number: A59
Revision Number: 00
Risk Assessment completed by: Legislation: This risk assessment is in compliance with:
Name: Everistus Chukwumaeze Federal Law No8, Year 1980, Ministerial Order No 32 and (Tick box):
☐OSHAD ☒Dubai municipality ☐EHS Trakhees
Designation: HSE Manager Signature: ☐Other (List)……………………………………
Description of the Task: RISK ASSESSMENT FOR BUILDERS WORK
RISK RATING RISK LIKELIHOOD
RATING
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Water storage in Hearing Loss, Tinnitus prior start e.. Hand gloves, Rubber shoes to prevent water from Manager
tank, use of hose ☒Contractor entering the leg which can cause foot problems ☒ Project Engineer
Trip, slip and fall resulting to injury s / Sub Water Storage tank should be assessed to prevent formation of
pipe Legionella bacteria due to stagnation of water for long period of ☒ Foremen
time. Hence the water should flow regularly from the water ☒ HSE for monitoring
storage tank.
The pumping machine should be well protected from noise and
maintenance should be done regularly.
The rotating parts of the curing machine should be protected with
guard to prevent entanglement.
The water hose should be inspected to prevent leakage, waste of
water and water logging of the workplace which can cause slip
injury.
The water hose should be properly routed to prevent trip hazard
and good housekeeping to be ensured
Approved by Name Nasser Ahour Designation Project Manager Signature Date 09-07-19
Note: Risk assessment should be completed by a site team member and a member of the safety department if possible
PIC-HSE-FRM-RA-001
RISK ASSESSMENT FORM
Project: Park Point 5AB Date: 09.07.2019 Reference Number: A59
Revision Number: 00
Risk Assessment completed by: Legislation: This risk assessment is in compliance with:
Name: Everistus Chukwumaeze Federal Law No8, Year 1980, Ministerial Order No 32 and (Tick box):
☐OSHAD ☒Dubai municipality ☐EHS Trakhees
Designation: HSE Manager Signature: ☐Other (List)……………………………………
Description of the Task: RISK ASSESSMENT FOR BUILDERS WORK
RISK RATING RISK LIKELIHOOD
RATING
Severity-S Likelihood-L
3 2 1
Risk Rating = S X L = R
Legal Description of Task Hazard / Risk / Consequences Evaluation Person’s Actions required Evaluation Action by (Name & Date)
& RR before at risk. To reduce or control risks After
ref LXS= (Place X in LXS=
Risk box) Risk
Rating Rating
Approved by Name Nasser Ahour Designation Project Manager Signature Date 09-07-19
Note: Risk assessment should be completed by a site team member and a member of the safety department if possible
PIC-HSE-FRM-RA-001