Professional Documents
Culture Documents
Advanced Concepts in Launching Girder
Advanced Concepts in Launching Girder
2
Methods of Segment Erection
3
Over Slung Erection Under Slung Erection
4
Under Slung Erection
5
Over Slung Erection Under Slung Erection
SVBTC Kolkata
6
Over Slung Erection
7
General Arrangement and
Components of LG
8
Launching Girder Configuration
9
10
Rear Trolley Rear Support Mid Support Front Support
Components of Front Support
Top beam - Transfers load from LG to
Top vertical leg
12
13
Height Adjustment in Front support during auto launching
The middle support should be seated on pier head segment during erection since most of the erection load is
carried by middle support.
15
Knuckle Bearing and cradle beam
16
Auto Launching Arrangement Connected to Middle Support
17
Components of Rear Support
Erection load should not be transferred through rear support since it is designed only to take loads from LG
during hauling
18
Components of Rear Trolley
The rear trolley is located at a fixed distance of 4.5 m from the rear end of the Launching Girder.
19
20
Anchor Bolt – Front Support
22
FABRICATION OF LAUNCHING GIRDER
Procurement of steel
Physical inspection of plates
Testing of steel plates
Cutting plan
Fit up procedure
Welding of joints
23
Fit up procedure
24
WELDING TEST METHOD
DPT Method:- Dye penetrant test is also called liquid penetrant inspection
(LPI) or penetrant testing (PT), is a widely applied and low-cost inspection
method used to locate surface-breaking defects in all non-porous
materials (metals, plastics, or ceramics). The penetrant may be applied to
all non-ferrous materials and ferrous materials.
25
Ultrasonic Test Method
26
Assembly And Erection Of Launching Girder
27
Methods of LG Erection
Tandem Lift Method Single Lift Method
28
Procedure of LG Erection
1. Erection Of Front Support.
2. Erection Of Middle Support
3. Erection Of LG Boxes (S1 to S5)
4. Erection Of Crab Hoist Winch
5. Erection Of Segment Trollies
6. Load Test Of Winch And LG.
7. First Span Erection
8. Erection of Rear Support
9. Part Auto launch and Erection of S6 & S7 box
10.Erection of counter weight over S7 Box
11.Erection of rear trolley
12.Erection of S8 box
13.Placement of all counter weight at S8 box
29
Stage 1:- Erection Of Front Support
Stage 2:- Erection Of Middle Support
30
Mid support Temporary Stool for 1st span Erection
Temporary Stool
32
Stage3:- Erection Of LG Boxes (Single Lift Method)
33
Stage 4:- Erection Of Crab Hoist Winch
Stage 5:- Erection Of Segment Trollies
34
Stage 5:- Load Test Of Winch And Launching Girder
35
Crab Hoist Winch Load Test
• Before starting the Winch load test, Launching Girder is to be in segment
lifting position.
• Here the winch is finally tested by lifting 25% additional load of 50 T and it is
to be certified for its capacity of 80MT.
36
37
Launching Girder Load Test
38
Segment Erection
39
Stressing Frame and Concrete Blisters for Temporary Stressing
Glue is to be applied at the surface of precast segment and a uniform stress of 3kg/cm2
is applied over the entire c/s area of the segment using macalloy bars and jacks
41
CHECKS BEFORE SEGMENT ERECTION
Front anchored with the pier cap by using anchor bars.
Middle supports, Rear support and Rear trolley are anchored with the Span by using
anchor bars.
Supporting jacks of middle support are locked with lock nut provided in the jacks.
42
Brakes are applied at Middle support using breaking assembly provided at their front
side.
Middle support cradles are anchored using the HT stress bars provided over the
main beam so that it doesn’t move in transverse direction during erection of pre-cast
segments.
43
44
45
46
47
48
49
50
Segment Lifting and Side Shifting using Winch System <15m lift
Segment Trolley
Hoist Beam
Strong Back
Stressing frame
53
Dry Matching
54
Epoxy Application on segment surface
Create 300mm gap between S1 segment and S2 segment for applying epoxy glue
between segments.
Apply epoxy glue (Sikadur 31SBA S-02) between segments S1 & S2.
Note: As per FIP (international pharmaceutical federation) Glue consumption is
3.2kg/m2 to 3.6Kg/m2
Do temporary pre stressing of the segments S1 & S2 by stress bars. Applied
pressure during gluing is 3kg/cm2.
55
56
Temporary pre stressing in
between lifting frame of the
segment at top level
57
Technical specification of Epoxy (Sikadur-31 SBA-02)
58
59
Checklist for Gluing
Span No. Epoxy Brand Name Batch No. Shelf life Upto
1) Epoxy Batch tested at site lab. & Found O.K. within last twelve Months
YES / NO / NA
4) Sufficient Trained manpower available for gluing and pre stressing. YES / NO / NA
60
Glue/Epoxy application format
S. Joint Date Temp Epoxy Batch No. Epoxy Harden Start End Theoret Actual POT Open
No. No (o C) Base Hardene Temp er Type time of time of ical Qty. consum Life time
Batch r Batch range gluing temp. of glue ption (Limit (Limit
No. (o C) pre (kg /Lit) (kg/Lit) 20 min) 60 min)
stressin
g
01
02
03
04
05
06
07
08
09
10
11
61
Stressing method
62
STRESSING METHOD
Following are the properties of 15.2Φ Low Relaxation High Tensile Strands
Conforming to IS: 14268 LRPC Class- II.
63
STRESSING EQUIPMENT DATA
Wedges
The basic raw material for manufacture of wedges is alloy steel. The individual high tensile
strands passing through the bearing plate is anchored by the wedges. The 3 segments of the
wedges are held together around the strand by means of special wire circlips for better
functioning, easy placement and storage.
64
Multi strand jack and Power pack unit
65
Storage of pre stressing Materials
All pre stressing steel, sheathing, anchorages and couplers shall be protected during
transportation, handling and storage. Following are the precautions to be taken.
High Tensile strand in the coil form shall be handled by crane using wire slings.
Sheathing ducts are flexible and hence should be handled with care to avoid any damage
against deformation due to mis- handling.
Pre stressing materials like sheathing ducts, anchorages shall be kept in stores under dry
and covered place. They should be stored at least 100mm above the ground level to
avoid corrosion.
Jacks & Pumps, hoses shall be kept under cover.
High tensile strand shall be stacked over raised platforms more than 300mm and
covered.
Strand dispenser is to be used while uncoiling the HT Strand coil to avoid accidents & an
abrasive cutting wheel mounted on a grinder is to be used for cutting strands as per
required lengths.
66
STRESSING OPERATION
Once the segments are glued and span is ready for stressing, strands will be threaded
individually into the ducts.
Anchor heads are assembled on both sided and strands are threaded on to the same by
securing strands with compact wedges.
Multi strand jack will be fixed at the one end and stressed to design force.
Since the elongation to be achieved is above 200 mm, stressing will be done in two
stages.
67
In 1st stage the stress will be applied to approximate 50% of total pressure ~ 200 Kg/cm²-
During this operation elongation of tendon shale be noted at intervals of 50, 100, 150
and 200 Kg/cm².
After applying a pressure of 50 Kg/cm², a mark at distance of 100 mm shall be done on
passive end to measure the wedge draw in.
Then the tendon will be locked and the ram will be retracted.
After retraction of ram, the master heads of jacks shall be fixed back to ram and stress
will be continued until the pressure reached previous force of 200 Kg/cm².
After noting down the ram readings at 200 Kg/cm², the balance force shall be applied in
equal increments of 200, 250, 300, 350 , and final pressure depends on the (type of
tendon or ) serial number of tendon.
68
Initial reading of 2nd stage will be considered as starting reading to calculate cumulative
elongations. Elongations will be checked for any variance after applying actual young’s
modulus and cross sectional area of strands.
After removal of jack a mark will be done on strands at distance of 100 mm to observe
24 hours – for any further wedge draw-in.
Once the stressing is completed, strands are cut & the tendon prepared for grouting.
69
DON’Ts of Stressing
DON’T stress any tendon which contains concrete slurry inside the anchor cavity.
Concrete slurry in the anchor cavity will prevent proper seating of the wedges.
DON’T use the jack when it is not positioned properly on the face of the anchor.
DON’T overstress tendons in order to achieve proper elongation.
DON’T allow obstruction in the path of the jack extension.
DON’T use extension cords longer than 100 ft. (30 m), 2 wire cords or cords less than 12
gauge.
DON’T continue stressing if you suspect that something is not working properly.
DON’T stand in the immediate vicinity of the jack, or between the jack and pump during
stressing or DE tensioning.
DON’T permit other workman in the immediate area of the jack, or pump, or along the
tendon during stressing application.
DOESN’T hammer or beat on the jack or jack cylinders.
DON’T activate equipment if you are not sure.
70
WORK SHEET
Stressing calculation for Tendon-1
Values as per drawing
• Capacity of jack:- 415t
• Effective Ram area:- 659.7 cm2
• Efficiency of jack:- 98%
• Theoretical area of strand:- 140 mm2
• Theoretical modulus of elasticity of strand (E):- 1.95 x 105 Mpa
• Theoretical elongation:- 204 mm
• Load for Tendon-1 :- 239t
• Slip = (10mm at live end, 3mm at dead end)
71
Stressing Record format
Elongation in mm
Applied
Cable no: Cable no:
Pressure
Reading Difference Cumulative Reading Difference Cumulative
(kg/ Remarks
(mm) difference (mm) difference
sq.cm)
(mm) (mm)
Total Elongation :
Slip (Live end + Dead end) :
Net Elongation :
Percentage variation of Elongation :
72
73
Stress calculation (Modified pressure is applied on each tendon)
Modified pressure (kg/cm2) = [Load (ton) X 1000] / [Effective ram area (cm2) X Jack
efficiency]
= [239 x 1000]/ [659.7 x 0.98]
= 369.67 kg/cm2
Maximum (+5%) = 388.16 kg/cm2 Minimum (-5%) = 351.18 kg/cm2
74
Bridge data : Strand data : Jack data :
Required Modified Pressure : 369.67 kg/cm2 Max (+5%): 388.16 kg/cm2 Min (-5%): 351.18 kg/cm2
Required Modified Elongation : 197.94mm Max (+5%): 207.84 mm Min (-5%): 188.04 mm
Elongation in mm
Applied
Cable no: Cable no:
Pressure
Reading Difference Cumulative Reading Difference Cumulative
(kg/ Remarks
(mm) difference (mm) difference
sq.cm)
(mm) (mm)
50 44
100 75 31
150 105 30 61
200 139 34 95
Avg. 31 126
200 30
250 55 25 151
300 78 23 174
350 100 22 196
360 114 14 210
370 120 6 216
380
Total Elongation : 216 mm
Slip (Live end + Dead end) : 10+3= 13 mm
Net Elongation : 216-13 = 203 mm
Percentage variation of Elongation : 2.56%
75
GROUTING
76
CABLE GROUTING
The purpose of grouting is to provide a permanent protection to the high tensile steel
against corrosion and develop bond between pre stressing steel and surrounding
concrete. The grout ensures encasement of high tensile steel for corrosion protection &
fills the duct space to prevent ingress of water or air.
Grouting Operation
The anchorage pockets should be capped with concrete or suitable capping material
prior to grouting operation
After the anchorage has been capped the tendon shall be water flushed through the
grout hole which projects from the top of the duct
Grout mix shall have the mix proportion of water/cement ratio as specified by the
weight. The additive admixture is mixed with cement in proportion as recommended by
additive manufacture.
77
Typical proportions of grout mix are as follows.
Water cement ratio = 0.40% by weight. Admixture used is Cebex-100 ( 1 pack per
bag of cement, 200gm) is mixed to Cement of weight 50 kilograms, Tap water (w)
20 liters is added to the grouting cement.
Grout samples shall be collected and tests to be carried for compressive strength
at7 days and 28 days and the results should satisfy 17 N/mm2 and 27 N/mm2
respectively.
After completion of grouting the projected portion of grout vent shall be cut flat to
the top of segment level by means of abrasive disc.
78
Lowering of Span to Permanent Bearings
79
Lowering of Span to Permanent Bearings
80
Auto launching of
launching girder
81
Check before Auto launching
At front support
Front support should be detached from pier.
Lift the bottom beam of front support up to 1.2m or required height and insert pin in
telescopic leg.
Remove all the loose material from front support.
At middle support
Middle support must be aligned properly.
Both knuckle bearing of middle support should be water levelled.
Knuckle bearing should be locked at 1.7m c/c by clamp plate bolts at bottom and by Mac
alloy bar at middle.
82
Knuckle top clamp anchoring with LG
Box girder should be removed.
Remove pin from braking assembly of
support.
Middle support should be anchored
properly with the pier head segment by
32mm dia Mac alloy bars.
83
At Rear trolley
Anchor the rear trolley with LG box girder by mac alloy bars.
Splicing of rails should be proper and maintain a proper gauge 4.7m c/c between the
rails.
While crossing over expansion joint, provide proper packing at bottom of rails.
84
Slider beams
All Slider beams should be moved at rear end of launching girder before auto launching.
85
Auto launching equipment's.
Launching girder is pulled by a fixed hydraulic jack mounted on middle support and a
pulling bracket hanging in monorail of launching girder.
Details of hydraulic jack.
Capacity – 40t
Stroke length – 1200mm
Closed length – 1500mm
Power pack – Double acting (5HP).
Detail of monorail
Monorail is a I-section beam which is welded at bottom center of LG Girder along the
length.
55mm dia holes @500mmc/c are provided in monorail for fixing 50mm dia pin in pulling
bracket for LG movement.
86
Auto launching operation:
Connect the hydraulic jack (40t) with power pack (5HP) unit.
Forced out/push the ram of jack outside along with connected pulling bracket up to 1m.
Match the hole of pulling bracket with monorail hole and insert 50mm dia pin with split
pins.
87
Remove the 50mm dia pins from pulling bracket
and again Forced out/push the ram of jack
outside along with connected pulling bracket
upto 1m.
Continue this operation up to 20m auto
launching.
At 20m Stop auto launching process and insert
pin in braking assembly and fix wedges in rear
trolley wheel.
Release load from Rear support and shift it at S3
segment near middle support.
Fix and anchor the rear support properly as done
before.
Before start auto launching process remove pin
from braking assembly and wedges from rear
trolley wheel.
Start auto launching again and continue it until
front support reaches at next pier.
Anchor the front support with pier cap.
88
A u to L a u n c h i n g a n d
S e g m e nt E re c t i o n i n
Curved Span
89
CURVED SPAN LAUNCHING
Jack up Rear support and shift middle support over pier head segment of the erected span
Jack up the Middle support and Release Front support
91
CURVED SPAN LAUNCHING
92
CURVED SPAN LAUNCHING
93
CURVED SPAN LAUNCHING
Shift Rear Support behind Middle support over the erected span
Continue auto launching till LG reaches the next Pier
94
95
96
CURVED SPAN LAUNCHING
97
98
99
CURVED SPAN ERECTION
100
CURVED SPAN ERECTION
101
Transverse Side shifting of Segment during Curved Span Erection
Segment trolley
Segment
102
103
104
D e s i g n co n c e p t o f
L a u n c h e r p a r t s fo r
S e g m e nt E re c t i o n
105
Design Concepts – General Components
Counter Weight
Counter weight is provided to counter balance the girder during Auto launching. The
counter weight is fixed based on the net possible uplift at rear trolley location.
Segment Trolley
Size and Self weight of segment
Minimum curvature in the alignment
Space available to occupy the segment trolley during erection
• The width of segment trolley has to be fixed considering the Size of the strand
wedges which occupies space of about 150mm between two adjacent
segment trolleys.
106
Design Concepts – General Components
Winch system
The capacity of winch is fixed considering the maximum weight of segment and
corresponding stressing frame self weight
107
Design Concepts – LG supports
Front Support
The front support will be connected to launcher with bolts and moves along with
launcher during Auto launching
Designed to take maximum reaction to be transferred during segment erection of the
maximum span length over the entire alignment
The torsion generated in girder during erection of curved spans (Eccentricity in load at
segment trolley) is also considered for design
Anchor slots in bottom beam has to be fixed based on the minimum curvature and the
dimension of the pier
The maximum height of telescopic leg should be finalized considering the Height of
bearing pedestal, segment height and the height of rear trolley
The minimum height of front support should be such that the bottom of front support
should not touch the shear key in pier cap or the inserts provided in pier cap during
Auto launching
• Deflection at Front support location during auto launching to maximum
span length should also be considered to fix the minimum height of Front
Support
108
Design Concepts – LG supports
The space between the inner face of front support and the End segment should
be considered in designed based on the available post tensioning jack
dimensions.
The Inserts provided in pier cap to anchor front support shall be of two types
• Sleeve with threads anchored inside the pier cap and removable bolt
screwed into the sleeve (Sleeve to be filled after erection)
• Fixed bolt anchored inside the pier cap (Should be removed after erection)
109
Design Concepts – LG supports
Middle Support
Rear Support
110
Design Concepts – LG supports
111
THANK YOU
112