PROMISED ACTUAL

Groundbreaking, February 2024 Date Missed, TBD

Substan al Comple on, September 2024 JTA’s 2030 Deadline extension request
denied by FTA.
Cost: $44 million $66.6 Million

Combo of federal/state/local $ Spent: $1.49 million federal, $0 State,


$15,768,803 local, to date

Ridership: 2,500 people/day 250-300/day at best, per FDOT

12-15 federally compliant autonomous vehicles Ford E-Transit vans with AV kit and driver

6 new, branded sta ons TBD

20 connected intersec ons TBD

14 flood sensors TBD

39 Pedestrian sensors TBD

Mixed use safety surveillance/CCTV cameras TBD

$500,000 maintenance building Rendering es mated to cost $9.4 million

Modernized traffic lights with signal priority TBD

*Upon request I can provide a packet with the data used to compile this table and the
primary public records associated.