3003 3 Months Look Ahead Schedule 6-April-2023 Site Readiness R-1
3003 3 Months Look Ahead Schedule 6-April-2023 Site Readiness R-1
Activity
Road 1 to 3
Site Readiness
Backfilling
Sanitary Wastewater Network 9-Apr-23 9-May-23
Irrigation Middle line
Irrigation System 10-May-23 9-Jun-23
Telecom North side Duct bank with Crossing &MH
Telecommunication System 10-May-23 9-Jun-23
Crossing
Electrical Power Distribution System 10-May-23 25-May-23
Outfall and All Crossings CB, and Backfill
Storm Drainage System 10-Jun-23 30-Jul-23
Basecourse
Road Construction 31-Jul-23
Utilities
Must complete line, MH and backfilling 30-May-2023
Sanitary Wastewater Network Baseline 3-Oct-22 11-Nov-24 88% 100%
Storm Drainage System Baseline 15-Feb-23 25-Oct-23 0% 4% All Crossing CB and Backfill
Actual/Forecast 23-Jun-22 30-Jul-23 73% 65% Completion of Line B & C including CB &Backfill
All Crossings
Telecommunication System Baseline 15-Mar-23 23-May-24 0% 0%
Actual/Forecast 0% 0%
Road 3 to 5
Sanitary Wastewater Network Baseline 5-Mar-23 3-Nov-24 0% 33%
Potable and Fire Water System Baseline 11-Jul-23 3-Nov-24 0% 0% Trenching, Pipe Laying, Valve Chambers Backfill
2nd Line (300mm Dia Pipe) work will start ahead of
Actual/Forecast 20-May-23 19-Jul-23 30% 50%
schedule
Telecommunication System Baseline 30-Jan-24 29-Oct-24 0% 16% Tranching, Duct Bank,MH , Backfilling
Actual/Forecast 0% 0%
Intersection at Road 3
Construction of Road 8 Between Road 1 and 5 DATE: 6-April-2023
Actual/Forecast 0% 0%
Construction of Road 8 Between Road 1 and 5 DATE: 6-April-2023
Actual/Forecast 0% 0%
Actual/Forecast 3%
Actual/Forecast 0% 0%
Actual/Forecast 0% 0%
Actual/Forecast 0% 0%
Actual/Forecast 0% 0%
Intersection at Road 1
Potable and Fire Water System Baseline 16-Apr-24 17-Oct-24 0% 0%
Actual/Forecast 0% 0%
Actual/Forecast 0% 0%
Actual/Forecast 0% 0%
Progress Status on 6-April-2023 Forecast Progress Status on 30 June 2023 as per Look-Ahead
Scheduled Progress 32.47% Scheduled Progress 42%
Actual Progress 42.45% ON TARGET Forecast Progress 49% ON TARGET
Variance % 9.98% Variance % 7%