Professional Documents
Culture Documents
Progress Report As of March 21, 2022
Progress Report As of March 21, 2022
Duration Week 1 Week 2 Week 3 (Mar Week 4 (Mar Week 5 (Mar Week 6 (Mar Week 7 Week 8 Week 9 Week 10
No. Activity
(days) (Feb 21-28) (Mar 1-6) 7-13) 14-20) 21-27) 28-Apr 3) (Apr 4-10) (Apr 11-17) (Apr 18-24) (Apr 25-31)
1 Lay-outing of road network in the topographic map 3
2 Profiling of the road and elevation 5
3 Cross sectioning, detailing of the cut/ fill per station 10
4 Mobilization 1
5 Temporary facility 2
6 Earthworks (Excavation, backfilling, embankment) 7
7 Drainage and Slope protection Structure 15
8 Aggregate sub-base Coarse 6
9 Installation of forms 4
10 PCC Pavement (Unreinforced) 12