Project: ACQ- GRU Road Network (Phase 1)

Subject: Progress Report as of March 21, 2022

Duration Status of Revised/ Adjusted


No. Activity Inclusive Date Remarks Schedule
(days) Completion
1 Lay-outing of road network in the topographic map 3 February 25-28 100% February 25-28
2 Profiling of the road and elevation 4 March 1- 5 100% March 1- 5
Detailing of cut/fill for the portion of the road from
3 Cross sectioning, detailing of the cut/ fill per station 10 March 6- 16 60% rotonda going to Medical building was suspended March 6- 30
since there is a revision of the proposed plan.
4 Mobilization 1 March 7- 8 100% March 7- 8
5 Temporary facility (Field Office) 2 March 8- 10 100% March 8- 10
6 Earthworks (Excavation, backfilling, embankment) 7 March 14- 23 5% Earthwork activity started March 18. March 16- 30
7 Drainage and Slope protection Structure 15 April 1- 16 0% Not yet started March 21- April 10
8 Aggregate sub-base Coarse 6 March 20- 26 0% Not yet started March 30- April 15
9 Installation of forms 4 March 22- 26 0% Not yet started April 15 - 20
10 PCC Pavement (Unreinforced) 12 March 24- April 5 0% Not yet started April 18- 30

Project: ACQ- GRU Road Network (Phase 1)


Subject: Bar Chart (Updated)

Duration Week 1 Week 2 Week 3 (Mar Week 4 (Mar Week 5 (Mar Week 6 (Mar Week 7 Week 8 Week 9 Week 10
No. Activity
(days) (Feb 21-28) (Mar 1-6) 7-13) 14-20) 21-27) 28-Apr 3) (Apr 4-10) (Apr 11-17) (Apr 18-24) (Apr 25-31)
1 Lay-outing of road network in the topographic map 3
2 Profiling of the road and elevation 5
3 Cross sectioning, detailing of the cut/ fill per station 10
4 Mobilization 1
5 Temporary facility 2
6 Earthworks (Excavation, backfilling, embankment) 7
7 Drainage and Slope protection Structure 15
8 Aggregate sub-base Coarse 6
9 Installation of forms 4
10 PCC Pavement (Unreinforced) 12