Professional Documents
Culture Documents
TC_No._03_2022
TC_No._03_2022
Item No.1: Providing and laying of Hot Mix Dense Asphaltic Concrete
(DAC) using crushed stone aggregate of quality, size and grading as
specified, #filler of quality as specified and Polymer Modified Bitumen (PMB)
(supplied in bulk) in proportions as per job mix formula and laid to specified
levels, grade and camber as per specification, drawings and as directed by
the Engineer-in-Charge including compacting with 8-10 tonne, preferably
vibratory road roller of adequate capacity to achieve the specified values of
compaction, strength, surface accuracy complete [for tendering purpose PMB
of grade *( PMB 64-10, PMB 70-10, PMB 76-10, 82-10, 76-22)
content shall be taken as 135 kg/m3 of mix supplied in bulk produced by
Govt. Refineries and 2% hydrated lime by weight of aggregates as filler
material].
1.0 Materials
1
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
***If the minimum retained tensile strength falls below 80%, use of
anti-stripping agent is recommended to meet the minimum
requirements.
be heat stable, shall not change the viscosity of the binder beyond
specifications, shall contain no harmful ingredients, shall be added in
recommended proportion by approved method and shall satisfy the
requirements as stipulated in MORT&H Appendix-5. The cost of
providing anti-stripping agent shall be borne by the contractor and
nothing extra shall be paid on this account to the contractor.
1.1.3 Some aggregates may contain ferrous sulfides and iron oxides which
can cause stains on exposed concrete surfaces. In areas where
staining has been a problem or is suspected, the Engineer should verify
that producers and aggregate suppliers have taken steps to prevent
the inclusion of any ferrous sulfides or iron oxides in aggregate to be
used in the project.
1.3 Filler
0.6 100
0.3 95 - 100
0.075 85 - 100
The filler shall be inert material free from organic impurities and shall
3
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
have Plasticity Index not greater than 4. PI requirement will not apply
if filler is hydrated lime or cement.
For the purpose of tendering the contractor may base his rate
assuming 2% hydrated lime as filler by weight of aggregates. If the
actual quantity & type of filler required to be used as per mix design is
found to be different from the quantity & type of filler assumed above,
necessary adjustment in cost of extra/short filler shall be made as per
the rate of filler used in actual supply voucher from manufacturer/
authorized dealer at the time of execution. In the case of authorized
distributor the rate may be authenticated by the manufacturer. In the
case of stone dust, the rate as per actual supply voucher shall be used.
The rate of filler exclusive of GST shall only be considered for payment.
1.4 Bitumen
Polymer Modified Bitumen (PMB) conforming to IS:15462-2019,
supplied in bulk by Govt. Refineries/Govt. Refineries having Joint
venture with private firm, shall be used for preparation of Dense
Asphaltic Concrete. However, in region where bulk bitumen is not
available, then packed bitumen may be specified in the tender
document. Use of imported PMB shall not be allowed. The agencies
shall submit copies of the purchase vouchers of the PMB to the
Engineer-in-Charge. The selection of PMB shall be made based upon
the Climatic condition of the area as per Table-1. Wherever PMB is to
be used, that shall be blended at refinery, supplied hot in tankers.
Table-1
Pavement 64 to (-10)0C 70 to (-10)0C 76 to (-10)0C 82 to (-10)0C 76 to (-22)0C
Temperature
Range (Max
and Min) 0C
Grade of PMB 64-10 PMB 70-10 PMB 76-10 PMB 82-10 PMB 76-22
PMB
Since only air temperature are available from weather data, the
following equation may be used to estimate the average maximum
Pavement Temperature (at a depth of 20 mm) from high air
temperature and latitude of the project location:
The contractor shall mandatorily provide weigh bridge at the hot mix
plant for accurate weighing of materials.
In addition to routine tests for PMB as per Codal provisions/
4
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Use of PMB in DAC layer shall be permitted only for those airports
where stringent quality control/quality assurance is feasible as stated
above. The decision of ED Engg., in this regard, shall be final and to
be obtained before call of tenders.
5
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Note: Grading in the JMF shall be near to the mid-point to the extend
possible.
Twenty days prior to the start of work at site, the job mix formula shall
be got determined by the contractor in AAI empanelled or Govt.
Institute/laboratory or in-house by Department of Structure, as
directed by the Engineer-in-Charge, by Marshall Design Method. The
Job Mix Formula (JMF) so determined shall be submitted by the
contractor, in writing, to the engineer–in-charge for his acceptance
before the actual paving work starts at site. The Contractor also shall
intimate, in writing, to the Engineer-in-Charge the details of source and
location of all materials, their sizes, grading and test results. Besides
conforming to the requirements of grading and quality for individual
ingredients, the mix shall meet the requirements enumerated below:
6
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
* The nominal maximum particle size is one size larger than the first
sieve, which retains more than 10% material.
** For intermediate value of designated percentage air voids interpolate
the VMA.
c) The test patch shall also be tested for friction by AAI surface
friction tester at a test speed of 95Km/hour and test water
depth of 1.0mm and the value shall not be less than 0.74.
All the above tolerances are with respect to the Job Mix Formula as the
datum.
For the purpose of tendering, the Contractor may base his rate on the
assumption that the bitumen content of the mixture shall be 135 Kg of
bitumen per Cum. of total mix compacted to 100% density in Marshall
mould. If the actual quantity of bitumen required to be used as a result
of the JMF is found different from the quantity of bitumen that is
assumed above, necessary adjustment in cost of extra/short bitumen
8
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
used shall be made as per the rate worked out for bitumen under
clause 10CA as mentioned in schedule or purchase price of bitumen
at the nearest IOC/HP/Govt. refinery, whichever is lower. The
procurement price of bitumen (basic rate excluding GST) shall be
ascertained by the Engineer-in-charge on submission of documentary
proof by the contractor. The rate of bitumen decided by the Engineer-
in-Charge shall be final and binding. Except adjustment in cost due to
variation in bitumen consumption as stated above, no other factor for
variation in consumption of bitumen, whatsoever shall be considered
for adjustment in quoted rates.
In the event of change in materials available at site due to unforeseen
exigencies, a fresh job mix formula shall be arrived at within the
specified limits in the AAI empanelled laboratory or Govt.
Institute/laboratory as approved by the Engineer-in-Charge. Nothing
extra is payable due to this.
All plants used by the contractor for the preparation of Dense Asphaltic
Concrete should be equipped with the following:
The hot aggregate and binder shall be thoroughly and intimately mixed
together in the correct proportion for at least 30 seconds or longer and
until every particle of aggregates is completely coated and
homogenous mixer is obtained. The total mixing time may be reduced
but not less than 30 seconds in any case, if the Engineer-in-Charge is
satisfied that through mixing can be achieved in less time. In such
cases the contractor shall obtain prior written permission of the
Engineer-in-charge.
The Hot Mix Plant (HMP) employed by the contractor shall be a weigh
batch plant having a minimum capacity of:
a. For work cost >Rs 500 Cr. 200 TPH
b. For work cost >Rs 200 Cr. < Rs. 500 Cr. 160 TPH
c. For work cost < Rs. 200 Cr. 120 TPH
9
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Hot Mix Plant with electronic control of minimum capacity as above and
capable of producing a proper quality mix shall be used for preparing
the mix. The plant shall be batch type having a coordinative set of
essential units such as drier for heating the aggregate, devices for
grading and batching/feeding by weight the required quantities of
aggregates. The plant shall also have a binder heating and control unit
for metering out the correct quantities of heated binder together with
the mechanical mixer for thorough mixing of the binder and the
aggregates. It should preferably have a separate feeder for
incorporating the correct quantity of filler by weight.
Note: In case weigh batch mix plants are not feasible, permission to
use continuous/drum type mix plant shall be taken from the concerned
ED(Engg) while preparing TS.
7.0 Temperature
7.1 Following are the broad range of temperature at different stages when
PMB is used as binder. The exact temperature depends upon the type
and amount of modifier used and shall be adopted as per
recommendation of the manufacturer.
10
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
9.0 Laying
Mix transported from the Hot Mix Plant to the site be spread by means
of self-propelled electronic paver with electronic sensor & hydraulic
control with suitable screeds capable of spreading, temping and
finishing the mix true to the specified width and profile without calling
segregation, dragging, bringing irregularities or other surface defects.
The paver shall be capable of being operated at a speed consistent
with a character of mix and the thickness of the course being laid so as
to produce a surface of having uniform density and surface texture.
The thickness of the single compacted layer shall not exceed 50mm.
The temperature of the mix at the time of laying shall be as per clause
7.0 above.
After the mix being spread, rolling shall be carried in three consecutive
stages as below:
11.1 The initial or Break down rolling shall be done with 8-10 tonne dead weight
smooth wheeled roller. The intermediate rolling will be done with 8-10
static weight or vibratory roller or with a smooth wheel pneumatic tyred
roller of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2. The
contractor shall demonstrate the efficiency of the equipment proposed to
be used by carrying compaction trials. Finish rolling shall be done with 8
to 10 tonne steel wheel roller.
11.2 Bituminous mixes shall be rolled in the longitudinal direction, with the roller
as close as possible to the paver. The overlap on successive passes should
be at least one-third of the width of the rear roll or in the case of pneumatic
wheeled rollers, at least the nominal width of 300 mm.
11.4 The principal function of finish rolling is to remove roller marks. The
surface shall be carefully examined for residual marks which should be
cleanly rolled out. A neat finished appearance shall be obtained. Finish
rolling shall be accomplished with tandem roller.
The final compaction will be carried out with a pneumatic tyred roller
of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2 after the
entire paving operations are completed. This should be done on bright
sunny days such that entire airfield is rolled minimum five times.
12.0 Joints
12
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
joints shall be carefully cut back and trimmed to firm material in the
compacted lane, or for a minimum of one and a half times the layer
thickness, whichever is the greater. All debris/loose material arising
from this operation shall be removed from the pavement and the
underlying surface cleaned and painted with hot bitumen immediately
before laying of the adjacent lane. Nothing extra shall be paid on this
account.
Apart from the quality control tests given in clause 1.1.1, following
additional tests shall be carried out:
S.No. Test Test method Frequency Acceptance
Criteria
1 Quality of IS:15462:2019 Number of samples as As per IS:15462.
binder IRC:SP:53 per lot. IRC:SP:53
13
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
5 Binder content As per 4.0 One test for each 400 As per Clause 3.2
clause tonnes of mix subject to
minimum of two tests per
day per plant.
6 Density of As per 14.0 One test per 700m2 area. As per clause 16.1
compacted layer clause
When the field density achieved in the Field is between 95% and 98%
of the Design Laboratory Density, the work shall be accepted as not up
to the standard and paid at reduced rate on pro-rata basis of Design
Laboratory Density with full rate for 98% density as base.
When the field density works out to be less than 95% of the Design
Laboratory Density, the surface shall be further consolidated till the
required field density is achieved. If this is not found possible, the work
represented by the sample shall be dismantled and redone by the
Contractor at his own cost.
14
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
affected area which shall not be less than 10 Sqm and relaying with
fresh materials. In no case shall depressions be filled up with
screenings or binding material.
17.0 Measurements:
17.1 Before commencement of laying of Dense Asphaltic concrete, levels
shall be taken jointly by the Engineer-in-Charge or his representative
and the Contractor at 3 metre intervals both ways or closer as directed
by the Engineer-in-Charge. These levels shall be recorded in the level
book and plotted on the plan on plain computer sheet by the Contractor
at his own cost and the same shall be signed by the Contractor.
Proposed formation levels of the finished Dense Asphaltic Concrete
surface shall be marked at corresponding points. Tack coat shall then
be applied and Dense Asphaltic Concrete shall then be laid and
compacted to required levels (Tack coat shall be paid separately in the
respective item of BOQ). Levels of the compacted bituminous surface
shall be taken at grid points at which levels were recorded earlier in
the level book and also plotted on the plan. Level books as well as
the plan shall be signed by the Contractor as token of acceptance of
the levels.
17.2 The volume of compacted mix shall be worked out in cubic meter
correct to two places of a decimal as the product of the measured
surface area and average thickness laid. Average thickness shall be
worked out on the basis of actual levels. The length and breadth shall
be measured correct to cm.
17.3 In case DAC is to be laid on SDAC newly laid under this contract, the
finished levels of previous surface shall be taken as initial levels for
this purpose.
18.0 Rate
The rate shall include the cost of all materials, plant machinery and
labour required in all operations described above including all carriage
and lifts involved. The rate also includes all cost of setting up the
laboratory at site and carrying out the quality control measures/tests
enumerated above by the Contractor at his own cost in the presence
of Engineer-in-Charge or his authorised representative and
submission of test results on completion of tests to the Engineer-in-
Charge thereof (The item of Tack Coat shall be paid separately and is
not included in this item).
15
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Item No.2: Providing and laying of Hot Mix Dense Asphaltic Concrete
(DAC) using crushed stone aggregate of quality, size and grading as specified
and #filler as specified and Viscosity Grade Bitumen (supplied in bulk) in
proportions as per job mix formula and laid to specified levels, grade and
camber as per specification, drawings and as directed by the Engineer-in-
Charge including compacting with 8-10 tonne, preferably vibratory road roller
of adequate capacity to achieve the specified values of compaction, strength,
surface accuracy complete [for tendering purpose VG bitumen of grade *(VG-
10/VG-20/VG-30) content shall be taken as 135 kg/m3 of mix supplied in bulk
produced by Govt. Refineries and 2% hydrated lime by weight of aggregates
as filler material].
1.0 Materials
16
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
4 Particle Flakiness & IS:2386 One test per 350 Max. 30%
Shape Elongation Index (Part I) Cum of
(Combined) aggregate for
each source and
whenever there
is change in the
quality of
aggregate
**If the minimum retained tensile strength falls below 80%, use of
anti-stripping agent is recommended to meet the minimum
requirements.
1.3 Filler
0.6 100
0.3 95 - 100
0.075 85 - 100
The filler shall be inert material free from organic impurities and shall
18
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
have Plasticity Index not greater than 4. PI requirement will not apply
if filler is hydrated lime or cement.
For the purpose of tendering, the contractor may base his rate
assuming 2% hydrated lime as filler by weight of aggregates. If the
actual quantity & type of filler required to be used as per mix design is
found to be different from the quantity & type of filler assumed above,
necessary adjustment in cost of extra/short filler shall be made as per
the rate of filler used in actual supply voucher from manufacturer/
authorized dealer at the time of execution. In the case of authorized
distributor, the rate of filler may be authenticated by the manufacturer.
In the case of stone dust, the rate as per actual supply voucher shall
be used. The rate of cement exclusive of GST shall only be considered
for payment.
1.4 Bitumen
The Viscosity Grade Bitumen shall conform to IS:73 and shall be,
supplied in bulk by Govt. Refineries. However, in region where bulk
bitumen is not available, then packed bitumen may be specified in the
tender document. Use of imported Bitumen shall not be allowed. The
agencies shall submit copies of the purchase vouchers of the Bitumen
to the Engineer-in-Charge.
The contractor shall mandatorily provide weigh bridge at the hot mix
plant for accurate weighing of materials.
19
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Note: Grading in the JMF shall be near to the mid-point to the extent
possible.
Twenty days prior to the start of work at site, the job mix formula shall
be got determined by the contractor in AAI empanelled or Govt.
Institute/laboratory or in-house by Department of Structure, as
directed by the Engineer-in-Charge, by Marshall Design Method. The
Job Mix Formula (JMF) so determined shall be submitted by the
contractor, in writing, to the engineer–in-charge for his acceptance
before the actual paving work starts at site. The Contractor also shall
intimate, in writing, to the Engineer-in-Charge the details of source and
location of all materials, their sizes, grading and test results. Besides
conforming to the requirements of grading and quality for individual
ingredients, the mix shall meet the requirements enumerated below:
20
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
* The nominal maximum particle size is one size larger than the first
sieve, which retains more than 10% material.
** For intermediate value of designated percentage air voids interpolate
the VMA.
c) The text patch shall also be tested for friction by AAI surface
friction tester at a test speed of 95Km/hour and test water
depth of 1.0mm and the value shall not be less than 0.74.
21
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
For the purpose of tendering, the Contractor may base his rate on the
assumption that the bitumen content of the mixture shall be 135 Kg of
bitumen per Cum. of total mix compacted to 100% density in Marshall
mould. If the actual quantity of bitumen required to be used as a result
of the JMF is found different from the quantity of bitumen that is
assumed above, necessary adjustment in cost of extra/short bitumen
used shall be made as per the rate worked out for bitumen under
clause 10CA as mentioned in schedule or purchase price of bitumen
at the nearest IOC/HP/Govt. refinery, whichever is lower. The
22
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
All plants used by the contractor for the preparation of Dense Asphaltic
Concrete should be equipped with the following:
The hot aggregate and binder shall be thoroughly and intimately mixed
together in the correct proportion for at least 30 seconds or longer and
until every particle of aggregates is completely coated and
homogenous mixer is obtained. The total mixing time may be reduced
but not less than 30 seconds in any case, if the Engineer-in-Charge is
satisfied that through mixing can be achieved in less time. In such
cases the contractor shall obtain prior written permission of the
Engineer-in-charge.
The Hot Mix Plant (HMP) employed by the contractor shall be a weigh
batch plant having a minimum capacity of:
a. For work cost >Rs 500 Cr. 200 TPH
b. For work cost >Rs 200 Cr. < Rs. 500 Cr. 160 TPH
c. For work cost < Rs. 200 Cr. 120 TPH
Hot Mix Plant with electronic control of minimum capacity as above and
capable of producing a proper quality mix shall be used for preparing
the mix. The plant shall be batch type having a coordinative set of
23
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
essential units such as drier for heating the aggregate, devices for
grading and batching/feeding by weight the required quantities of
aggregates. The plant shall also have a binder heating and control unit
for metering out the correct quantities of heated binder together with
the mechanical mixer for thorough mixing of the binder and the
aggregates. It should preferably have a separate feeder for
incorporating the correct quantity of filler by weight.
Note: In case weigh batch mix plants are not feasible, permission to
use continuous/drum type mix plant shall be taken from the concerned
ED(Engg) while preparing TS.
7.0 Temperature
24
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
9.0 Laying
Mix transported from the Hot Mix Plant to the site be spread by means
of self-propelled electronic paver with electronic sensor & hydraulic
control with suitable screeds capable of spreading, temping and
finishing the mix true to the specified width and profile without calling
segregation, dragging, bringing irregularities or other surface defects.
The paver shall be capable of being operated at a speed consistent
with a character of mix and the thickness of the course being laid so as
to produce a surface of having uniform density and surface texture.
The thickness of the single compacted layer shall not exceed 50mm. The
temperature of the mix at the time of laying shall be as per clause 7.0
above.
After the mix being spread, rolling shall be carried in three consecutive
stages as below:
11.1 The initial or Break down rolling shall be done with 8-10 tonne dead weight
smooth wheeled roller. The intermediate rolling will be done with 8-10
static weight or vibratory roller or with a smooth wheel pneumatic tyred
roller of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2. The
contractor shall demonstrate the efficiency of the equipment proposed to
be used by carrying compaction trials. Finish rolling shall be done with 8
to 10 tonne steel wheel roller.
11.2 Bituminous mixes shall be rolled in the longitudinal direction, with the
roller as close as possible to the paver. The overlap on successive passes
25
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
should be at least one-third of the width of the rear roll or in the case of
pneumatic wheeled rollers, at least the nominal width of 300 mm.
11.4 The principal function of finish rolling is to remove roller marks. The
surface shall be carefully examined for residual marks which should be
cleanly rolled out. A neat finished appearance shall be obtained. Finish
rolling shall be accomplished with tandem roller.
The final compaction will be carried out with a pneumatic tyred roller
of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2 after the
entire paving operations are completed. This should be done on bright
sunny days such that entire airfield is rolled minimum five times.
12.0 Joints
26
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
27
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
5 Binder As per 4.0 One test for each 400 As per clause
content clause tonnes of mix subject 3.2
to minimum of two
tests per day per plant.
When the field density achieved in the Field is between 95% and 98%
of the Design Laboratory Density, the work shall be accepted as not up
to the standard and paid at reduced rate on pro-rata basis of Design
Laboratory Density with full rate for 98% density as base.
When the field density works out to be less than 95% of the Design
Laboratory Density, the surface shall be further consolidated till the
required field density is achieved. If this is not found possible, the work
represented by the sample shall be dismantled and redone by the
Contractor at his own cost.
28
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
17.0 Measurements:
17.1 Before commencement of laying of Dense Asphaltic concrete, levels
shall be taken jointly by the Engineer-in-Charge or his representative
and the Contractor at 3 metre intervals both ways or closer as directed
by the Engineer-in-Charge. These levels shall be recorded in the level
book and plotted on the plan on plain computer sheet by the Contractor
at his own cost and the same shall be signed by the Contractor.
Proposed formation levels of the finished Dense Asphaltic Concrete
surface shall be marked at corresponding points. Tack coat shall then
be applied and Dense Asphaltic Concrete shall then be laid and
compacted to required levels (Tack coat shall be paid separately in the
respective item of BOQ). Levels of the compacted bituminous surface
shall be taken at grid points at which levels were recorded earlier in
the level book and also plotted on the plan. Level books as well as
the plan shall be signed by the Contractor as token of acceptance of
the levels.
17.2 The volume of compacted mix shall be worked out in cubic meter
correct to two places of a decimal as the product of the measured
surface area and average thickness laid. Average thickness shall be
worked out on the basis of actual levels. The length and breadth shall
be measured correct to cm.
17.3 In case DAC is to be laid on SDAC newly laid under this contract, the
finished levels of previous surface shall be taken as initial levels for
this purpose.
17.4 Quantity for payment shall be the theoretical quantity (Based on
Proposed formation levels) or the actual quantity (based on actual
finished levels) whichever is less.
18.0 Rate
The rate shall include the cost of all materials, plant machinery and
labour required in all operations described above including all carriage
and lifts involved. The rate also includes all cost of setting up the
laboratory at site and carrying out the quality control measures/tests
enumerated above by the Contractor at his own cost in the presence
of Engineer-in-Charge or his authorised representative and
submission of test results on completion of tests to the Engineer-in-
Charge thereof (The item of Tack Coat shall be paid separately and is
not included in this item).
29
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Item No.3: Providing and laying of Hot Mix Semi Dense Asphaltic
Concrete (SDAC) using crushed stone aggregate of quality, size and grading
as specified and #filler as specified and Viscosity Grade Bitumen (supplied in
bulk) in proportions as per job mix formula and laid to specified levels, grade
and camber as per specification, drawings and as directed by the Engineer-in-
Charge including compacting with 8-10 tonne, preferably vibratory road roller
of adequate capacity to achieve the specified values of compaction, strength,
surface accuracy complete [for tendering purpose VG bitumen of grade *(VG-
10/VG-20/VG-30) content shall be taken as 120 kg/m3 of mix supplied in bulk
produced by Govt. Refineries and 2% hydrated lime by weight of aggregates
as filler material].
1.0 Materials
30
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
(II) Loss
with -do- -do- Max. 18%
Magnesium
Sulphate
with5 cycles
4 Particle Flakiness & IS:2386 One test per 350 Max. 30%
Shape Elongation Index (Part I) Cum of
(Combined) aggregate for
each source and
whenever there
is change in the
quality of
aggregate
1.3 Filler
0.6 100
0.3 95 - 100
0.075 85 - 100
The filler shall be inert material free from organic impurities and shall
have Plasticity Index not greater than 4. PI requirement will not apply
if filler is hydrated lime or cement.
32
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
For the purpose of tendering the contractor may base his rate
assuming 2% hydrated lime as filler by weight of aggregates. If the
actual quantity & type of filler required to be used as per mix design is
found to be different from the quantity & type of filler assumed above,
necessary adjustment in cost of extra/short filler shall be made as per
the rate of filler used in actual supply voucher from manufacturer/
authorized dealer at the time of execution. In the case of authorized
distributor the rate may be authenticated by the manufacturer. In the
case of stone dust, the rate as per actual supply voucher shall be used.
The rate of filler exclusive of GST shall only be considered for payment.
1.4 Bitumen
The contractor shall mandatorily provide weigh bridge at the hot mix
plant for accurate weighing of materials.
Twenty days prior to the start of work at site, the job mix formula shall
be got determined by the contractor in AAI empanelled or Govt.
Institute/laboratory or in-house by Department of Structure, as
directed by the Engineer-in-Charge, by Marshall Design Method. The
Job Mix Formula (JMF) so determined shall be submitted by the
contractor, in writing, to the engineer–in-charge for his acceptance
before the actual paving work starts at site. The Contractor also shall
intimate, in writing, to the Engineer-in-Charge the details of source and
location of all materials, their sizes, grading and test results. Besides
conforming to the requirements of grading and quality for individual
ingredients, the mix shall meet the requirements enumerated below:
34
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
* The nominal maximum particle size is one size larger than the first
sieve, which retains more than 10% material.
** For intermediate value of designated percentage air voids interpolate
the VMA.
35
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
For the purpose of tendering, the Contractor may base his rate on the
assumption that the bitumen content of the mixture shall be 120 Kg of
bitumen per Cum. of total mix compacted to 100% density in Marshall
mould. If the actual quantity of bitumen required to be used as a result
of the JMF is found different from the quantity of bitumen that is
assumed above, necessary adjustment in cost of extra/short bitumen
used shall be made as per the rate worked out for bitumen under
clause 10 CA as mentioned in schedule or purchase price of bitumen
at the nearest IOC/HP/Govt. refinery, whichever is lower. The
procurement price of bitumen (basic rate excluding GST) shall be
ascertained by the Engineer-in-charge on submission of documentary
proof by the contractor. The rate of bitumen decided by the Engineer-
in-Charge shall be final and binding. Except adjustment in cost due to
variation in bitumen consumption as stated above, no other factor for
variation in consumption of bitumen, whatsoever shall be considered
for adjustment in quoted rates.
36
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
5.0 Mixing
All plants used by the contractor for the preparation of Semi Dense
Asphaltic Concrete should be equipped with the following:
The hot aggregate and binder shall be thoroughly and intimately mixed
together in the correct proportion for at least 30 seconds or longer and
until every particle of aggregates is completely quoted and
homogenous mixer is obtained. The total mixing time may be reduced
but not less than 30 seconds in any case, if the Engineer-in-Charge is
satisfied that through mixing can be achieved in less time. In such
cases the contractor shall obtain prior written permission of the
Engineer-in-charge.
The Hot Mix Plant (HMP) employed by the contractor shall be a weigh
batch plant having a minimum capacity of:
a. For work cost >Rs 500 Cr. 200 TPH
b. For work cost >Rs 200 Cr. < Rs. 500 Cr. 160 TPH
c. For work cost < Rs. 200 Cr. 120 TPH
Hot Mix Plant with electronic control of minimum capacity as above and
capable of producing a proper quality mix shall be used for preparing
the mix. The plant shall be batch type having a coordinative set of
essential units such as drier for heating the aggregate, devices for
grading and batching/feeding by weight the required quantities of
aggregates. The plant shall also have a binder heating and control unit
for metering out the correct quantities of heated binder together with
the mechanical mixer for thorough mixing of the binder and the
aggregates. It should preferably have a separate feeder for
incorporating the correct quantity of filler by weight.
Note: In case weigh batch mix plants are not feasible, permission to
use continuous/drum type mix plant shall be taken from the concerned
ED(Engg) while preparing TS.
7.0 Temperature
37
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
9.0 Laying
Mix transported from the Hot Mix Plant to the site be spread by means
of self-propelled electronic paver with electronic sensor & hydraulic
control with suitable screeds capable of spreading, temping and
finishing the mix true to the specified width and profile without calling
segregation, dragging, bringing irregularities or other surface defects.
The paver shall be capable of being operated at a speed consistent
with a character of mix and the thickness of the course being laid so as
to produce a surface of having uniform density and surface texture.
The thickness of the single compacted layer shall not exceed 75mm.
The temperature of the mix at the time of laying shall be as per clause
7.0 above.
11.0 Rolling
After the mix being spread, rolling shall be carried in three consecutive
stages as below:
11.1 The initial or Break down rolling shall be done with 8-10 tonne dead weight
smooth wheeled roller. The intermediate rolling will be done with 8-10
static weight or vibratory roller or with a smooth wheel pneumatic tyred
roller of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2. The
contractor shall demonstrate the efficiency of the equipment proposed to
be used by carrying compaction trials. Finish rolling shall be done with 8
to 10 tonne steel wheel roller.
11.2 Bituminous mixes shall be rolled in the longitudinal direction, with the roller
as close as possible to the paver. The overlap on successive passes should
be at leas tone-third of the width of the rear roll or in the case of pneumatic
wheeled rollers, at least the nominal width of 300 mm.
11.4 The principal function of finish rolling is to remove roller marks. The
surface shall be carefully examined for residual marks which should be
cleanly rolled out. A neat finished appearance shall be obtained.
39
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
of water shall not be permitted. The line of rolling shall not suddenly
be changed, thereby displacing the mix. Roller shall not be left standing
on the new surfacing.
12.0 Joints
5 Binder content As per clause One test for each 400 As per clause 3.2
4.0 tonnes of mix subject
to minimum of two
tests per day per plant.
6 Density of As per clause One test per 700m2 As per clause 16.1
compacted 14.0 area.
layer
Note: One test shall consists of 3 samples.
41
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
When the field density achieved in the Field is between 95% and 98%
of the Design Laboratory Density, the work shall be accepted as not up
to the standard and paid at reduced rate on pro-rata basis of Design
Laboratory Density with full rate for 98% density as base.
When the field density works out to be less than 95% of the Design
Laboratory Density, the surface shall be further consolidated till the
required field density is achieved. If this is not found possible, the work
represented by the sample shall be dismantled and redone by the
Contractor at his own cost.
17.2 The volume of compacted mix shall be worked out in cubic meter
correct to two places of a decimal as the product of the measured
surface area and average thickness laid. Average thickness shall be
worked out on the basis of actual levels. The length and breadth shall
be measured correct to cm.
42
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
18.0 Rate
The rate shall include the cost of all materials, plant machinery and
labour required in all operations described above including all carriage
and lifts involved. The rate also includes all cost of setting up the
laboratory at site and carrying out the quality control measures/tests
enumerated above by the Contractor at his own cost in the presence
of Engineer-in-Charge or his authorised representative and submission
of test results on completion of tests to the Engineer-in-Charge thereof
(The item of Tack Coat shall be paid separately and is not included in
this item).
43
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Item No.4: Providing and laying of Hot Mix Dense Bituminous Macadam
(DBM) using crushed stone aggregate of quality, size and grading as
specified and #filler as specified and Viscosity Grade Bitumen (supplied in
bulk) in proportions as per job mix formula and laid to specified levels, grade
and camber as per specification, drawings and as directed by the Engineer-in-
Charge including compacting with 8-10 tonne, preferably vibratory road roller
of adequate capacity to achieve the specified values of compaction, strength,
surface accuracy complete [for tendering purpose VG bitumen of grade *(VG-
10/VG-20/VG-30) shall be taken as 110 kg/m3 of mix supplied in bulk
produced by Govt. Refineries and 2% hydrated lime by weight of aggregates
as filler material].
1.0 Materials
44
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
(II) Loss
with -do- -do- Max. 18%
Magnesium
Sulphate
with5 cycles
4 Particle Flakiness & IS:2386 One test per Max. 35%
Shape Elongation Index (Part I) 350cum of
(Combined) aggregate for
each source and
whenever there
is change in
quality of
aggregate
1.1.3 Some aggregates may contain ferrous sulfides and iron oxides
which can cause stains on exposed concrete surfaces. In areas
where staining has been a problem or is suspected, the Engineer
should verify that producers and aggregate suppliers have taken
steps to prevent the inclusion of any ferrous sulfides or iron oxides
in aggregate to be used in the project.
If there is a concern that these may exist, an indicator to identify
staining particles is to immerse the aggregate in a lime slurry. If
staining particles are present, a blue-green gelatinous precipitate
will form within five (5) to 10 minutes, rapidly changing to a brown
color on exposure to air and light. The reaction should be complete
in 30 minutes. If no brown gelatinous precipitate forms, there is
little chance of reaction in concrete.
1.2 Fine Aggregates
1.3 Filler
0.6 100
0.3 95 - 100
46
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
0.075 85 - 100
The filler shall be inert material free from organic impurities and shall
have Plasticity Index not greater than 4. PI requirement will not apply
if filler is hydrated lime or cement.
For the purpose of tendering the contractor may base his rate
assuming 2% hydrated lime as filler by weight of aggregates. If the
actual quantity & type of filler required to be used as per mix design is
found to be different from the quantity & type of filler assumed above,
necessary adjustment in cost of extra/short filler shall be made as per
the rate of filler used in actual supply voucher from manufacturer/
authorized dealer at the time of execution. In the case of authorized
distributor the rate may be authenticated by the manufacturer. In the
case of stone dust, the rate as per actual supply voucher shall be used.
The rate of filler exclusive of GST shall only be considered for payment.
1.4 Bitumen
Table-1
Lowest Daily Mean Air Highest Daily Mean Air Temperature
Temperature Less than 200C 20 to 300C More than 300C
More than -100C VG-10 VG-20 VG-30
-100C or Lower VG-10 VG-10 VG-20
The contractor shall mandatorily provide weigh bridge at the hot mix
plant for accurate weighing of materials.
worked out so that the gradation of the final composition shall satisfy
the limits laid down below:
Grading 2
Nominal maximum 26.5 mm
Aggregate size
Layer Thickness 50-75 mm
IS Sieve Size (MM) Cumulative percentage by weight
of percentage passing
37.5 100
26.5 90-100
19 71-95
13.2 56-80
4.75 38-54
2.36 28-42
0.3 7-21
0.075 2-8
Twenty days prior to the start of work at site, the job mix formula shall
be got determined by the contractor in AAI empanelled or Govt.
Institute/laboratory or in-house by Department of Structure, as
directed by the Engineer-in-Charge, by Marshall Design Method. The
Job Mix Formula (JMF) so determined shall be submitted by the
contractor, in writing, to the engineer–in-charge for his acceptance
before the actual paving work starts at site. The Contractor also shall
intimate, in writing, to the Engineer-in-Charge the details of source and
location of all materials, their sizes, grading and test results. Besides
conforming to the requirements of grading and quality for individual
ingredients, the mix shall meet the requirements enumerated below:
48
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
* The nominal maximum particle size is one size larger than the first
sieve, which retains more than 10% material.
** For intermediate value of designated percentage air voids interpolate
the VMA.
49
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
All the above tolerances are with respect to the Job Mix Formula as the
datum.
For the purpose of tendering, the Contractor may base his rate on the
assumption that the bitumen content of the mixture shall be 110 Kg of
bitumen per Cum. of total mix compacted to 100% density in Marshall
mould. If the actual quantity of bitumen required to be used as a result
of the JMF is found different from the quantity of bitumen that is
assumed above, necessary adjustment in cost of extra/short bitumen
used shall be made as per the rate worked out for bitumen under clause
10 CA as mentioned in schedule or purchase price of bitumen at the
nearest IOC/HP/Govt. refinery, whichever is lower. The procurement
price of bitumen (basic rate excluding GST) shall be ascertained by the
Engineer-in-charge on submission of documentary proof by the
contractor. The rate of bitumen decided by the Engineer-in-Charge
shall be final and binding. Except adjustment in cost due to variation in
bitumen consumption as stated above, no other factor for variation in
consumption of bitumen, whatsoever shall be considered for
adjustment in quoted rates.
50
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
5.0 Mixing
The hot aggregate and binder shall be thoroughly and intimately mixed
together in the correct proportion for at least 30 seconds or longer and
until every particle of aggregates is completely quoted and
homogenous mixer is obtained. The total mixing time may be reduced
but not less than 30 seconds in any case, if the Engineer-in-Charge is
satisfied that through mixing can be achieved in less time. In such
cases the contractor shall obtain prior written permission of the
Engineer-in-charge.
The Hot Mix Plant (HMP) employed by the contractor shall be a weigh
batch plant having a minimum capacity of:
a. For work cost >Rs 500 Cr. 200 TPH
b. For work cost >Rs 200 Cr. < Rs. 500 Cr. 160 TPH
c. For work cost < Rs. 200 Cr. 120 TPH
Hot Mix Plant with electronic control of minimum capacity as above and
capable of producing a proper quality mix shall be used for preparing
the mix. The plant shall be batch type having a coordinative set of
essential units such as drier for heating the aggregate, devices for
grading and batching/feeding by weight the required quantities of
aggregates. The plant shall also have a binder heating and control unit
for metering out the correct quantities of heated binder together with
the mechanical mixer for thorough mixing of the binder and the
aggregates. It should preferably have a separate feeder for
incorporating the correct quantity of filler by weight.
Note: In case weigh batch mix plants are not feasible, permission to
use continuous/drum type mix plant shall be taken from the concerned
ED(Engg) while preparing TS.
51
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
7.0 Temperature
9.0 Laying
Mix transported from the Hot Mix Plant to the site be spread by means
of self-propelled electronic paver with electronic sensor & hydraulic
control with suitable screeds capable of spreading, temping and
finishing the mix true to the specified width and profile without calling
segregation, dragging, bringing irregularities or other surface defects.
The paver shall be capable of being operated at a speed consistent
with a character of mix and the thickness of the course being laid so as
to produce a surface of having uniform density and surface texture.
The thickness of the single compacted layer shall not exceed 75mm.
The temperature of the mix at the time of laying shall be as per clause
52
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
7.0 above.
After the mix being spread, rolling shall be carried in three consecutive
stages as below:
a) Break down rolling
b) Intermediate rolling
c) Finish rolling
11.1 The initial or Break down rolling shall be done with 8-10 tonne dead weight
smooth wheeled roller. The intermediate rolling will be done with 8-10
static weight or vibratory roller or with a smooth wheel pneumatic tyred
roller of 15 to 30 tonne capacity having tyre pressure 7 kg/cm2. The
contractor shall demonstrate the efficiency of the equipment proposed to
be used by carrying compaction trials. Finish rolling shall be done with 8
to 10 tonne steel wheel roller.
11.2 Bituminous mixes shall be rolled in the longitudinal direction, with the roller
as close as possible to the paver. The overlap on successive passes should
be at least one-third of the width of the rear roll or in the case of pneumatic
wheeled rollers, at least the nominal width of 300 mm.
11.4 The principal function of finish rolling is to remove roller marks. The
surface shall be carefully examined for residual marks which should be
cleanly rolled out. A neat finished appearance shall be obtained.
53
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
12.0 Joints
55
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
When the field density works out to be less than 95% of the Design
Laboratory Density, the surface shall be further consolidated till the
required field density is achieved. If this is not found possible, the work
represented by the sample shall be dismantled and redone by the
Contractor at his own cost.
17.2 The volume of compacted mix shall be worked out in cubic meter
correct to two places of a decimal as the product of the measured
56
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
17.3 In case DBM is to be laid on WMM newly laid under this contract, the
finished levels of previous surface shall be taken as initial levels for
this purpose.
18.0 Rate
The rate shall include the cost of all materials, plant machinery and
labour required in all operations described above including all carriage
and lifts involved. The rate also includes all cost of setting up the
laboratory at site and carrying out the quality control measures/tests
enumerated above by the Contractor at his own cost in the presence
of Engineer-in-Charge or his authorised representative and
submission of test results on completion of tests to the Engineer-in-
Charge thereof (The item of Tack Coat shall be paid separately and is
not included in this item).
57
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Item No 5: Providing and applying primer coat with bitumen emulsion SS1
grade conforming to IS:8887 on prepared surface of Granular Base including
clearing of surface and spraying primer at the rate of 0.70 kg/sqm using
mechanical means complete in all respects as per direction of Engineer-In-
Charge. The contractor shall quote his rates assuming quantity of bitumen
emulsion as 0.70 Kg/Sqm. If the actual quantity of bitumen emulsion varies
from the quantity assumed above, necessary cost adjustment for deviation in
the quantity of bitumen emulsion shall be done as per rate in actual supply
voucher from nearest refinery at the time of execution. The rate of bitumen
emulsion exclusive of GST shall only be considered for payment.
1.2 Materials
1.2.1 The primer shall be cationic bitumen emulsion SS1 grade conforming
to IS: 8887.
1.2.2 The correct quantity of primer shall be decided by the Engineer and
shall be such that it can be absorbed by the surface without causing
run-off of excessive primer and to achieve desired penetration of
about 8-10 mm.
Primer shall not be applied during a dust storm or when the weather
is foggy, rainy or windy or when the temperature in the shade is less
than 100C. Surface which are to receive primer should be damp, but
no free or standing water shall be present. Surface can be just wet by
very light sprinkling of water.
1.4 Construction
1.4.1 Equipment
The primer shall be applied by a self-propelled or towed bitumen
pressure sprayer equipped for spraying the material uniformly at
specified rates and temperatures. Hand spraying shall not be allowed
except in small areas, inaccessible to the distributor, or in narrow strips
where primer shall be sprayed with a pressure hand sprayer, or as
directed by the Engineer.
58
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
59
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
1.7 Rate
The contract unit rate for prime coat shall be payment in full for
carrying out the required operations including full compensation for all
components as described above including testing and as applicable to
the work specified in these Specifications. Payment shall be made on
the basis of the provision of prime coat at an application rate of
quantity at 0.7 kg per square meter or at the rates specified in the
Contract, with adjustment, plus or minus, for the variation between
this quantity and the actual quantity approved by the Engineer after
the preliminary trials referred to in Clause 1.2.2.
60
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
1.2 Materials
The binder used for tack coat shall be cationic bitumen emulsion (RS1)
complying with IS: 8887 or suitable low viscosity paving bitumen of VG
10 grade conforming to IS:73. The type and grade of binder for tack
coat shall be as specified in the contract or as decided by the Engineer-
in-Charge.
1.4 Construction
1.4.1 Equipment
The tack coat shall be applied by a self-propelled or towed bitumen
pressure sprayer, equipped for spraying the material uniformly at a
specified rate. Hand spraying shall not be permitted except in small
areas, inaccessible to the distributor, or narrow strips, shall be sprayed
with a pressure hand sprayer, or as directed by the Engineer in Charge.
61
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
62
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
1.7 Rate
The contract unit rate for tack coat shall be payment in full for carrying
out the required operations including for all components as listed
above including testing and as applicable to the work specified in these
specifications. The rate shall cover the provision of tack coat, at
0.20/0.30 kg per square meter or at the rate specified in the Contract,
with the provision that the variation between this quantity and actual
quantity of bitumen used will be assessed and the payment adjusted
accordingly.
63
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
Annexure I
2. Testing Equipment
a) Vacuum container, vacuum pump, manometer, and other accessories
as specified in ASTM D2041, “Theoretical Maximum Specific Gravity
and Density of Bituminous Paving Mixtures”.
b) Balance or scale accurate to 0.1 percent of the test load
c) Two water baths capable of maintaining temperatures of 60º C +/- 1º
C and
25º C +/- 0.5º C
d) Freezer maintained at –18º C ( +/- 3º C)
e) 10-ml graduate cylinder
f) Loading jack and ring dynamometer (Marshall stability testing machine
can be used) to provide a vertical rate of deformation of 50 mm (2
inches) per minute and capable of reading the maximum failure load.
g) Steel loading strips with a concave surface having a radius equal to the
normal radius of the test specimen. The loading strips shall be 12.7
mm (0.5inch) wide for specimens 100 mm (4 inches) in diameter. The
loading strips for 150 mm (6 inches) diameter specimens shall be
19.05 mm (0.75 inch) wide. The length of the loading strips shall
exceed the thickness of the specimens. Steel strip are provided at the
top and bottom of specimens during indirect tensile testing.
3. Test Procedure
64
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
c) Separate the 6 specimens into 2 subsets so that the average air voids
of the two subsets are approximately equal.
d) One set will be tested dry. Keep it at room temperature and then place
in a 25º C (+/- 0.5 C) water bath for 2 hours prior to determining their
indirect tensile strength.
65
AAI Specifications for Bituminous Mix for Flexible Airfield
Pavements (July 2022)
66
Item No.1: Providing and laying of Hot Mix Dense Asphaltic Concrete (DAC) using crushed stone aggregate of quality, size and grading
as specified, #filler of quality as specified and Polymer Modified Bitumen (PMB) (supplied in bulk) in proportions as per job mix formula
and laid to specified levels, grade and camber as per specification, drawings and as directed by the Engineer-in-Charge including
compacting with 8-10 tonne, preferably vibratory road roller of adequate capacity to achieve the specified values of compaction, strength,
surface accuracy complete [for tendering purpose PMB of grade *( PMB 64-10, PMB 70-10, PMB 76-10, 82-10, 76-22) content shall be
3
taken as 135 kg/m of mix supplied in bulk produced by Govt. Refineries and 2% hydrated lime by weight of aggregates as filler
material].
# Filler in order of preference shall be hydrated lime, stone dust or cement. The necessary cost adjustment shall be made based on JMF
& availability of filler.
* strike out whichever is not applicable.
67
(i) 18 cum capacity t.km 450.76 x L1
(ii) 14 cum capacity t.km 450.76 x L1
(iii) 10 cum capacity t.km 450.76 x L1
viii For loading and unloading time
(i) 18 cum capacity hour 6.01
(ii) 14 cum capacity hour 7.513
(iii) 10 cum capacity hour 10.017
ix) Smooth steel wheeled tandem roller for static and hour 16.902 16.902 16.902
vibratory passages
x) Pneumatic tyre roller hour 2.404 3.005 4.007
c) Labour
i) Mate day 0.44 0.44 0.44
Sub Total
Add water charges 1%
Sum after adding water Charges
CP & OH 15%
Sum after adding CP&OH
Labour cess %
Cost for 191 cum
Cost for 1 cum
Say Rs.
1 Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.
2 Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative
overheads of the contractor.
3 The individual density for each size of aggregates to be used for construction i.e. 13.2 mm Nominal maximum Aggregate Size should be
found in the laboratory and accordingly the quantities should be amended for use in field. The average density of 1.5 tonne/cum is only a
reference density.
4 The individual percentage of aggregates and filler should be calculated from the total weight of dry aggregates i.e. excluding the weight of
bitumen in accordance with Job Mix Formula.
68
Item No.2 Providing and laying of Hot Mix Dense Asphaltic Concrete (DAC) using crushed stone aggregate of quality, size and grading as
specified and #filler as specified and Viscosity Grade Bitumen (supplied in bulk) in proportions as per job mix formula and laid to specified
levels, grade and camber as per specification, drawings and as directed by the Engineer-in- Charge including compacting with 8-10 tonne,
preferably vibratory road roller of adequate capacity to achieve the specified values of compaction, strength, surface accuracy complete [for
tendering purpose VG bitumen of grade *(VG- 10/VG-20/VG-30) content shall be taken as 135 kg/m3 of mix supplied in bulk produced by
Govt. Refineries and 2% hydrated lime by weight of aggregates as filler material].
69
(iii) 10 cum capacity t.km 450.76 x L1
viii For loading and unloading time
(i) 18 cum capacity hour 6.01
(ii) 14 cum capacity hour 7.513
(iii) 10 cum capacity hour 10.017
ix) Smooth steel wheeled tandem roller for static and hour 16.902 16.902 16.902
vibratory passages
x) Pneumatic tyre roller hour 2.404 3.005 4.007
c) Labour
i) Mate day 0.44 0.44 0.44
Sub Total
Add water charges 1%
Sum after adding water Charges
CP & OH 15%
Sum after adding CP&OH
Labour cess %
Cost for 191 cum
Cost for 1 cum
Say Rs.
1 Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.
2 Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative
overheads of the contractor.
3 The individual density for each size of aggregates to be used for construction i.e. 13.2 mm Nominal maximum Aggregate Size should be
found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a
reference density.
4 The individual percentage of aggregates and filler should be calculated from the total weight of dry aggregates i.e. excluding the weight of
bitumen in accordance with Job Mix Formula.
70
Item No.3 Providing and laying of Hot Mix Semi Dense Asphaltic Concrete (SDAC) using crushed stone aggregate of quality, size and grading
as specified and #filler as specified and Viscosity Grade Bitumen (supplied in bulk) in proportions as per job mix formula and laid to specified
levels, grade and camber as per specification, drawings and as directed by the Engineer-in- Charge including compacting with 8-10 tonne,
preferably vibratory road roller of adequate capacity to achieve the specified values of compaction, strength, surface accuracy complete [for
tendering purpose VG bitumen of grade *(VG- 10/VG-20/VG-30) content shall be taken as 120 kg/m3 of mix supplied in bulk produced by
Govt. Refineries and 2% hydrated lime by weight of aggregates as filler material].
b) Machinery
i) Batch Type Hot mix Plant
(i) HMP 200 TPH hour 3.005
(ii) HMP 160 TPH hour 3.756
(iii) HMP 120 TPH hour 5.008
ii) Mechanical Broom (2.1 m sweeping width) hour 1.137 1.137 1.137
iii) Air compressor 250 cfm hour 1.137 1.137 1.137
iv) Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240HP) hour 3.005
(ii) Paver (240 HP) hour 3.756
(iii) Paver (174HP) hour 5.008
v) Electric Generator
(i) 500 KVA hour 3.005
(ii) 400 KVA hour 3.756
(iii) 250 KVA hour 5.008
vi) Front end loader for feeding the plant
(i) 3.1 cum capacity hour 5.078
(ii) 2.1 cum capacity hour 7.506
(iii) 1 cum capacity hour 15.694
vii) Tipper For Transportation
71
(i) 18 cum capacity t.km 450.76 x L1
(ii) 14 cum capacity t.km 450.76 x L1
(iii) 10 cum capacity t.km 450.76 x L1
viii For loading and unloading time
(i) 18 cum capacity hour 6.01
(ii) 14 cum capacity hour 7.513
(iii) 10 cum capacity hour 10.017
ix) Smooth steel wheeled tandem roller for static and hour 11.831 11.831 11.831
vibratory passages
x) Pneumatic tyre roller hour 2.404 3.005 4.007
c) Labour
i) Mate day 0.44 0.44 0.44
Sub Total
Add water charges 1%
Sum after adding water Charges
CP & OH 15%
Sum after adding CP&OH
Labour cess %
Cost for 191 cum
Cost for 1 cum
Say Rs.
1 Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.
2 Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative
overheads of the contractor.
3 The individual density for each size of aggregates to be used for construction i.e. 19.0 mm Nominal maximum Aggregate Size should be
found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a
reference density.
4 The individual percentage of aggregates and filler should be calculated from the total weight of dry aggregates i.e. excluding the weight of
bitumen in accordance with Job Mix Formula.
72
Item No.4: Providing and laying of Hot Mix Dense Bituminous Macadam (DBM) using crushed stone aggregate of quality, size and grading as
specified and #filler as specified and Viscosity Grade Bitumen (supplied in bulk) in proportions as per job mix formula and laid to specified
levels, grade and camber as per specification, drawings and as directed by the Engineer-in- Charge including compacting with 8-10 tonne,
preferably vibratory road roller of adequate capacity to achieve the specified values of compaction, strength, surface accuracy complete [for
tendering purpose VG bitumen of grade *(VG- 10/VG-20/VG-30) shall be taken as 110 kg/m3 of mix supplied in bulk produced by Govt.
Refineries and 2% hydrated lime by weight of aggregates as filler material].
b) Machinery
i) Batch Type Hot mix Plant
(i) HMP 200 TPH hour 3.003
(ii) HMP 160 TPH hour 3.754
(iii) HMP 120 TPH hour 5.005
ii) Mechanical Broom (2.1 m sweeping width) hour 0.663 0.663 0.663
iii) Air compressor 250 cfm hour 0.663 0.663 0.663
iv) Paver finisher hydrostatic with sensor control
compatible with the hot mix plant
(i) Paver (240HP) hour 3.003
(ii) Paver (240 HP) hour 3.754
(iii) Paver (174HP) hour 5.005
v) Electric Generator
(i) 500 KVA hour 3.003
(ii) 400 KVA hour 3.754
(iii) 250 KVA hour 5.005
vi) Front end loader for feeding the plant
(i) 3.1 cum capacity hour 5.112
(ii) 2.1 cum capacity hour 7.556
(iii) 1 cum capacity hour 15.799
73
vii) Tipper For Transportation
(i) 18 cum capacity t.km 450.45 x L1
(ii) 14 cum capacity t.km 450.45 x L1
(iii) 10 cum capacity t.km 450.45 x L1
viii For loading and unloading time
(i) 18 cum capacity hour 6.006
(ii) 14 cum capacity hour 7.508
(iii) 10 cum capacity hour 10.01
ix) Smooth steel wheeled tandem roller for static and hour 9.663 9.663 9.663
vibratory passages
c) Labour
i) Mate day 0.44 0.44 0.44
Sub Total
Add water charges 1%
Sum after adding water Charges
CP & OH 15%
Sum after adding CP&OH
Labour cess %
Cost for 195 P 147-149
Cost for 1 cum
Say Rs.
1 Quantity of Bitumen has been taken for analysis purpose. The actual quantity will depend upon job mix formula.
2 Labour for traffic control, watch and ward and other miscellaneous duties at site including sundries have been included in administrative
overheads of the contractor.
3 The individual density for each size of aggregates to be used for construction i.e. 26.5 mm Nominal maximum Aggregate Size should be
found in the laboratory and accordingly the quantities should be ammended for use in field. The average density of 1.5 tonne/cum is only a
reference density.
4 The individual percentage of aggregates and filler should be calculated from the total weight of dry aggregates i.e. excluding the weight of
bitumen in accordance with Job Mix Formula.
74
Item No 5: Providing and applying primer coat with bitumen emulsion SS1 grade conforming to IS:8887 on prepared surface of Granular Base
including clearing of surface and spraying primer at the rate of 0.70 kg/sqm using mechanical means complete in all respects as per direction of
Engineer-In-Charge. The contractor shall quote his rates assuming quantity of bitumen emulsion as 0.70 Kg/Sqm. If the actual quantity of bitumen
emulsion varies from the quantity assumed above, necessary cost adjustment for deviation in the quantity of bitumen emulsion shall be done as
per rate in actual supply voucher from nearest refinery at the time of execution. The rate of bitumen emulsion exclusive of GST shall only be
considered for payment.
Sub Total -
Add 1% water charges -
Sum after adding water Charges -
15% CP & OH -
Sum after adding 15% CP&OH -
Labour cess @1% -
Cost for 7000 Sqm -
Cost for 1 Sqm -
Say Rs. -
75
Item No 6: Providing and applying tack coat (*using bitumen emulsion (Rapid setting) complying with IS:8887 or suitable low viscosity paving bitumen
of VG 10 grade conforming to IS:73), spraying the bitumen with mechanically operated spray unit at the rate specified below, cleaning and preparing
the existing pavement surface as per specifications complete in all respects as per direction of Engineer-In-Charge. If the actual quantity of bitumen
varies from the quantity specified, necessary cost adjustment for deviation in the quantity of bitumen shall be done as per rate in actual supply
voucher from nearest refinery at the time of execution. The rate of bitumen exclusive of GST shall only be considered for payment.
a) 0.20 Kg/Sqm on existing bituminous surface
b) 0.30 Kg/Sqm on existing concrete surface
strike out whichever is not applicable.
Sub Total -
Add 1% water charges -
Sum after adding water Charges -
15% CP & OH -
Sum after adding 15% CP&OH -
Labour cess @1% -
Cost for 7000 Sqm -
Cost for 1 Sqm -
Say Rs. -
b) Tack Coat on existing cement concrete pavement with Bitumen Emulsion @ 0.30Kg/Sqm
Sub Total -
Add 1% water charges -
76
Sum after adding water Charges -
15% CP & OH -
Sum after adding 15% CP&OH -
Labour cess @1% -
Cost for 7000 Sqm -
Cost for 1 Sqm -
Say Rs. -
77