Illust. Ex. Tilapia Pond
Illust. Ex. Tilapia Pond
0.2x0.2 R.C.C.
6” CHB
6” CHB
2.5 m
6” CHB
@0.45m BW
0.25 m
6” CHB
Section
0.4 m
Column-Footing
Estimate the cost of materials and labor of the tilapia pond. Foundation is 50mm thick compacted gravel.
Also estimate the numbers of days to complete the project.
Labor Cost
Skilled Per day 350.00
Un-skilled Per day 500.00
Illustrative Example-Tilapia Pond