Illustrative Example-Tilapia Pond

0.2x0.2 R.C.C.

6” CHB

Plastered 6” CHB 1.3 m


Ø10mm rebars (inside)

6” CHB

2.5 m

6” CHB
@0.45m BW
0.25 m

4.0 m Conc. slab Wall Footing

6” CHB
Section

Plan Ø10 mm Vert. dowels


@0.4 m

4-Ø16mm Ø10mm Ø10 mm Hor. Dowels


Ties@0.1m Every two layers
rebars 5-Ø16mm 0.1 m
BW
50mm Conc. Reinf. Conc. slab
0.6 m

cover 0.2 m 2-Ø12 mm Long. bars

0.4 m

0.6 m Wall Footing

Column-Footing

Estimate the cost of materials and labor of the tilapia pond. Foundation is 50mm thick compacted gravel.
Also estimate the numbers of days to complete the project.

Material Cost Unit Unit Cost


Portland Cement (40kg) bag 250.00
Gravel 2” m3 800.00
Gravel 3/4” m3 1000.00
Sand m3 600.00
Deformed bars kg/m 60/kg
Tie wires #16 kg 75
½” Plywood sheets 1000
2”x2” coco lumber Bd-ft 30/bd-ft
1” CWN kg 80
2” CWN kg 80

Labor Cost
Skilled Per day 350.00
Un-skilled Per day 500.00
Illustrative Example-Tilapia Pond