0% found this document useful (0 votes)
296 views7 pages

Inspection Test Plan for Storage Tanks

Uploaded by

abulabbu444
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
296 views7 pages

Inspection Test Plan for Storage Tanks

Uploaded by

abulabbu444
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd

Inspection and Test Plan

ITP
DOC_No.: ITP-C-003 Page_No.: 1 Of 7

Site Inspection and Test Plan

ITP

Above Ground
Storage Tank
Rev.
0 Rev. Date: 08.06.2012 Total Pages: 7 Prepared By: M.Shariat
No.

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad


Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 2 Of 7 Rev._No.: 0

Reference Code & Party Involved


Row

Construction Activity Inspection / Testing Activity


Acceptance Criteria Contractor TPI MC Owner

1.1 Test Plan Welding Control


Welding Procedure
1 1.2 Visual Inspection
Qualification Test
1.3 Radiographic Test "Film Rev."

2.1 Test Plate Welding Control


Welder
2 2.2 Visual Inspection
Qualification Test
2.3 Radiographic Test "Film Rev."

3.1 Material Identification


Material Control
3
(General)
3.2 Visual Inspection, Dimension Check
Welding Monitoring
4.0 4.1 Baking & Holding Of Electrodes
(General)
4.1. Weld Seam Check
4.1 Before Process
4.1.2 Preheat Temperature

4.2.1 Welder Certificate

4.2 After Process 4.2.2 Welding Sequence

4.2.3 Interpass Temperature

5.1 Levelness Of Ring Wall

5.2 Center Point & Radius

5 Foundation 5.3 Flatness & Slope

5.4 Orientation (Zero Point, Drain Sump)

5.5 Anchor Bolts (Distance, Projection & Etc.)

6.0 Bottom Erection 6.1 Orientation Check

6.1.1 Erection Marking Check


6.1 Annular Plate
6.1.2 Arrangement Check

6.2.1 Fit-Up Check

6.2.2 Welding Monitoring

6.2 Annular Plate 6.2.3 Visual Inspection Of Weldment

6.2.4 Radiographic Test "Film Rev."

6.2.5 Vacuum Box Test

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad


Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 3 Of 7 Rev._No.: 0

Reference Code & Party Involved


Row

Construction Activity Inspection / Testing Activity


Acceptance Criteria Contractor TPI MC Owner

6.3.1 Erection Marking Check

6.3.2 Arrangement Check

Bottom Plate 6.3.3 Fit-Up Check


6.3 &
Sketch Plate 6.3.4 Welding Monitoring

6.3.5 Visual Inspection Of Weldment

6.3.6 Vacuum Box Test

6.4.1 Erection Marking Check

Miscellaneous 6.4.2 Orientation Check


6.4 Attachment Weld
on Bottom 6.4.3 Visual Inspection Of Weldment

6.4.4 Vacuum Box Test

7.0 Shell Erection


7.1.1 Erection Marking Check

7.1.2 Orientation Check

7.1.3 Arrangement Check

7.1.4 Fit-Up Check


First Course
Of 7.1.5 Level,Roundness,Plumbness Check
7.1 Shell Plates
& 7.1.6 Welding Monitoring
Vertical Joint
7.1.7 Visual Inspection Of Weldment

7.1.8 Peaking Check

7.1.9 RT: Radiography Test "Film Rev."

7.1.10 PT "After Back Grinding". (If Need)

7.2.1 Fit-Up Check

7.2.2 Welding Monitoring


Shell
7.2 to 7.2.3 Visual Inspection Of Weldment
Bottom Joint
7.2.4 OPT (Tank Inside Weld)

7.2.5 Initial Pass Weld & Finished Surface

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad


Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 4 Of 7 Rev._No.: 0

Reference Code & Party Involved


Row

Construction Activity Inspection / Testing Activity


Acceptance Criteria Contractor TPI MC Owner

Upper Shell Course ( 2nd to top course vertical Joint )


7.3.1 Erection Marking Check

7.3.2 Marking Check

7.3.3 Arrangement & Orientation Check

7.3.4 Fit-Up Check

7.3 7.3.5 Plumbness Check


Vertical Joint
7.3.6 Welding Monitoring

7.3.7 Visual Inspection Of Weldment

7.3.8 Peaking & Banding Check

7.3.9 RT: Radiography Test "Film Rev."

7.3.10 PT "After Back Grinding" (If Need)

7.4.1 Fit-Up Check

7.4.2 Welding Monitoring


Shell
7.4 7.4.3 Visual Inspection Of Weldment
Horizontal Joints
7.4.4 RT: Radiography Test "Film Rev."

7.4.5 PT "After Back Grinding" (If Need)

7.5.1 Erection Marking Check

7.5.2 Arrangement & Orientation Check


Shell
Stiffener
7.5 7.5.3 Fit-Up Check
Com. Ring
Top Angle
7.5.4 Welding Monitoring

7.5.5 Visual Inspection Of Weldment

7.6 Completed Shell 7.6.1 Roundness, Plumbness Check

7.7.1 Erection Marking Check

7.7.2 Location Check


Miscellaneous
7.7.3 Fit-Up Check
Erection & Welding
on
7.7 7.7.4 Welding Monitoring
Shell Plate
7.7.5 Visual Inspection Of Weldment

7.7.6 MT/PT
Scar Of Temporary
7.7.7 Visual Inspection Of Weldment
Attachment Weld
Petrochemical Industries Design & Engineering Co. Shariat.Mohammad
Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 5 Of 7 Rev._No.: 0

Reference Code & Party Involved


Row

Construction Activity Inspection / Testing Activity


Acceptance Criteria Contractor TPI MC Owner

8.1 Erection Marking Check

8.2 Opening Location Check

Shell Nozzle 8.3 Fit-Up Check


8.0 &
Manhole 8.4 Welding Monitoring

8.5 Visual Inspection Of Weldment

8.6 Pneumatic Leak Test

9.0 Roof Structure


9.1.1 Erection Marking Check

9.1 Per Assembly 9.1.2 Fit-Up Check

9.1.3 Visual Inspection Of Weldment

9.2.1 Orientation Check

9.2 Erection 9.2.2 Fit-Up Check

9.2.3 Visual Inspection Of Weldment

10.1 Erection Marking Check

10.2 Arrangement & Orientation Check

10.0 Roof Plate 10.3 Fit-Up Check

10.4 Welding Monitoring

10.5 Visual Inspection Of Weldment

11.1 Erection Marking Check

11.2 Location And Level Check


Roof Nozzle
11.0 & 11.3 Fit-Up Check
Manhole
11.4 Welding Monitoring

11.5 Visual Inspection Of Weldment

Miscellaneous 12.1 Erection Marking Check


Accessories Tank Spiral
12.0 Stairway, Ladder, Platform
Handrail, Anchor Chair,
Earth Lug, Etc.. 12.2 Visual Inspection Of Weldment

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad


Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 6 Of 7 Rev._No.: 0

Reference Code & Party Involved


Row

Construction Activity Inspection / Testing Activity


Acceptance Criteria Contractor TPI MC Owner

13.0 Hydrostatic Test


13.1.1 Inside Cleaning Check
Preparation
13.1 Of 13.1.2 Closing Of Opening
Tank
13.1.3 Settlement Measurement

13.2.1 Settlement Measurement


13.2 Water Filling
13.2.2 Leak Check

13.3 Hydrostatic Test 13.3.1 Water Level, Holding Time

13.4 Roof Test 13.4.1 Pneumatic Leak Test

13.5 Water Discharging 13.5.1 Check Roof Manhole Open

13.6.1 Cleaning Check


13.6 After Discharging
13.6.2 Seal Check

14.1 Inside
14.0 Sandblast & Painting
14.2 Outside

15.0 Tank Calibration 15.1 Marking & Measuring

16.1 Ensure The Completion Of All Required


16.0 Final Inspection
16.2 Construction Inspection And Testing

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad


Site Inspection and Test Plan "ITP"
Storage Tank Work Activities
DOC_No.: ITP-C-003 Page_No.: 7 Of 7 Rev._No.: 0

Action Key And Abbreviation:

H: Hold Point

W: Witness

RA: Random Inspection

RD: Review Document

N.A: Not Applicable

ITP-C-003:
PIDEC: Petrochemical Industries Design & Engineering Co.
ITP: Inspection and Test Plan
C: Construction
003: Document Number

Petrochemical Industries Design & Engineering Co. Shariat.Mohammad

You might also like