Kelompok 2
Adjeng Ayu Setiani
Audi Naufal R
Dwiki Prasetyo
1
Outline
Case Studies : Productivity of
Norwegian salmon processing
facility
2
3
Case Studies :
Norwegian Salmon Processing Facility, Trondheim
120.000
P = = 3,53 pounds / dollar
$24.000 +$10.000
5
2. Productivity of New System
Labor = 5 days x 8 hours x 30 workers x 2 shifts x $10
= $24.000
Energy = 1000 Units x $10 x 50%
= $5.000
Fish = 2000 pound / hour x 5 days x 8 hours x 2 shifts
= 160.000 pound
Installation = $10.000/week
160.000
P = = 4.1 pounds / dollar
$24.000 + $5.000 +$10.000
120.000 / 160.000 /
$24.000 $10.000 = $24.000 $5.000 $10.000
( )+( )
+ + +
7
4. Energy Cost Increase In The Future
Asumsi : New Energy Cost: $10/unit x 2 = $20/unit
Current System
- Energy = (1.000 energy units/week) ($20/energy unit)
= $20.000/week
120.000 /
- Multifactor Productivity= $24.000 $20.000
+
= 2,73 pounds of salmon/dollar
8
4. Energy Cost Increase In The Future (contd)
New System
- Energy =(1.000 energy units/week)($20/energy unit)(0.5)
= $10.000/week
160.000 /
- Multifactor Productivity= $24.000 $10.000 $10.000
+ +
= $3,64 pounds of salmon/dollar
9
10
Labor : 520 hours x $13/hours = $ 6.760
Solvent : 100 gallons x $5/gallons = $ 500
Machine : 20 days x $5/day = $ 1.000
11
a. Labor Productivity
65
= = 0.0096 /
520 $13/
b. Multifactor Productivity
65
= = 0.0079 /
520 $13 +
100 $5 +
(20 $50)
12