PRODUCTIVITY

Case Studies & Problem 1.8

Kelompok 2
Adjeng Ayu Setiani
Audi Naufal R
Dwiki Prasetyo

1
Outline
Case Studies : Productivity of
Norwegian salmon processing
facility

Problem 1.8 : Productivity of


Kleen Karpet

2
3
Case Studies :
Norwegian Salmon Processing Facility, Trondheim

1. Berapa besar produktivitas plant dengan system saat ini?


2. Berapa besar produktivitas plant apabila system baru
diterapkan?
3. Berapa pengeluaran untuk peralatan agar besar
produktivitas kedua system sama?
4. Apa yang terjadi apabila biaya energy naik dimasa
mendatang?
4
1. Productivity of Current System
Labor = 5 days x 8 hours x 30 workers x 2 shifts x $10
= $24.000
Energy = 1000 Units x $10
= $10.000
Fish = 1500 pound / hour x 5 days x 8 hours x 2 shifts
= 120.000 pound

120.000
P = = 3,53 pounds / dollar
$24.000 +$10.000

5
2. Productivity of New System
Labor = 5 days x 8 hours x 30 workers x 2 shifts x $10
= $24.000
Energy = 1000 Units x $10 x 50%
= $5.000
Fish = 2000 pound / hour x 5 days x 8 hours x 2 shifts
= 160.000 pound
Installation = $10.000/week

160.000
P = = 4.1 pounds / dollar
$24.000 + $5.000 +$10.000

P =4,1 3,53 = 0.57 pounds / dollar


Maka, dengan menggunakan system baru akan meningkatkan
produktivitas
6
3. Additional Expense to Two Systems

Multifactor Productivity (Current System) = Multifactor Productivity ( New System )

120.000 / 160.000 /
$24.000 $10.000 = $24.000 $5.000 $10.000
( )+( )
+ + +

Additional Expense on New Equipment = $6,333.33/week

7
4. Energy Cost Increase In The Future
Asumsi : New Energy Cost: $10/unit x 2 = $20/unit

Current System
- Energy = (1.000 energy units/week) ($20/energy unit)
= $20.000/week
120.000 /
- Multifactor Productivity= $24.000 $20.000
+

= 2,73 pounds of salmon/dollar
8
4. Energy Cost Increase In The Future (contd)

New System
- Energy =(1.000 energy units/week)($20/energy unit)(0.5)
= $10.000/week
160.000 /
- Multifactor Productivity= $24.000 $10.000 $10.000
+ +

= $3,64 pounds of salmon/dollar

9
10
Labor : 520 hours x $13/hours = $ 6.760
Solvent : 100 gallons x $5/gallons = $ 500
Machine : 20 days x $5/day = $ 1.000

Total Expense = $ 8.260

11
a. Labor Productivity
65
= = 0.0096 /
520 $13/

b. Multifactor Productivity
65
= = 0.0079 /
520 $13 +
100 $5 +
(20 $50)

12
Thank You !!!!!