ALUR PENAMBANGAN

PT.AKT
(OPEN PIT MINING)

1. Pembersihan lahan
2. Pengangkutan Top Soil
3. Penyimpanan Top Soil & Reklamasi 5. Pengangkutan tanah penutup (OB) 7. Pembersihan lapisan batubara
4. Pengeboran dan Peledakan 6. Penimbunan tanah penutup 8. Pengangkutan Batubara
ALUR COAL HAULING & BARGING PT.AKT
Transfer to Tongkang melewati S. Barito
Mother Vessel + 321km
3.000-5.000 ton Port Coal barging

ISP Damparan
Port Stockpile
7.000-10.000 ton
S. Barito

+ 215km

Kapasitas 20-30 Ton

ROM Stockpile Coal blending & crushing Coal Hauling + 38km


CHPP