Professional Documents
Culture Documents
• Laboratory testing
– Pile make-up
ANALYSIS AND DESIGN OF
FOUNDATIONS
• Jack-up Rigs
– Estimation of bearing capacity of
soil
– Estimation of Rig footing
penetration
– Recommendations for rig
deployment
ANALYSIS AND DESIGN OF
FOUNDATIONS
• Submarine pipelines
– Stability analysis of submarine pipeline
– Lay analysis
– Freespan Analysis
SPECIAL STUDIES
• Liquefaction potential
• Seabed stability analysis
• Shore protection work
• Punch-through of Jackup rig footings
• Pile refusal studies
Overview of Present
Scenario
BASIC CONCEPT
Suction Anchor Basic Concept ISO 9001
certified
discharge
weight of water
suction pressure
side friction
Driving Force =
weight + suction force
Penetration Resistance =
side + tip resistance
tip
resistance
Suction Penetration Driveability
Penetration Resistance = Driving Force
discharge
weight of water
suction pressure
side friction
Driving Force =
weight + suction force
Penetration Resistance =
side + tip resistance
tip
resistance
Suction Penetration Driveability
20 Bar suction
side friction
Driveability
normally limited
by suction levels
critical for heave
tip of soil plug
resistance
Ample margins against
penetration refusal
280
tons Maximum 1.4 Bar
suction was recorded
during Nkossa installation
As predicted, 50%
side friction
of suction levels
estimated critical
for soil plug heave
where used to reach
tip target penetration
resistance
Alternative Suction
Pile concepts Similar installation
ISO 9001
certified
conditions
pump
Closed for large vertical unit
pump
pump
cyclic load components unit
Hicap
30 30
28 28
26 26
24 24
22 22
20 20
18 18
16 16
14 14
12 12
10 10
8 8
6 6
4 4
2m 2m
seabed
Suction Pile Pump Skid
Mooring
anchors Suction pile
Driven pile
Suction
anchor Fluke anchor
flooding
of leg
Weight/ballast
Touch Down
penetration Suction penetration
Deep-water production
Artificial
seabed buoy
Loading
turret
Flexible
risers
Loading
direction
Loading
direction + - + neutral
+ - neutral -
Multiple-cell
Subsea loading system from
Suction anchor
Subsea templates with skirt foundation
ROV Operated pump unit
Skirt Skirt
foundation foundation
Pipeline supports with skirt footings
Solutions for difficult pipeline routing
Suspended pipe
Buoyancy
element
30 m 30 m 30 m 30 m 30 m 30 m 30 m 30 m 30 m 30 m 30 m 30 m
28 28 28 28 28 28 28 28 28 28 28 28
26 26 26 26 26 26 26 26 26 26 26 26
24 24 24 24 24 24 24 24 24 24 24 24
22 22 22 22 22 22 22 22 22 22 22 22
20 20 20 20 20 20 20 20 20 20 20 20
18 18 18 18 18 18 18 18 18 18 18 18
16 16 16 16 16 16 16 16 16 16 16 16
14 14 14 14 14 14 14 14 14 14 14 14
12 12 12 12 12 12 12 12 12 12 12 12
10 10 10 10 10 10 10 10 10 10 10 10
8 8 8 8 8 8 8 8 8 8 8 8
6 6 6 6 6 6 6 6 6 6 6 6
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2 2 2 2 2 2 2 2 2
World Wide Use
Deep-water sites around the world
Mid
Norway
Suction
piles
Deep
Gulf of Mediterranean
Mexico
NW
Africa Suction
Suction Columbus
piles
piles Barong
Amazon Tarajam
West East
Suction India India
West
Africa
piles
Suction
NW
piles Shelf Suction
Campos piles
Basin
New Zealand
Details of suction anchors & Bucket
Foundation
Suction Suction
anchor pile anchor pile
30 30
28 28
26 26
24 24
22 22
20 20
18 18
16 16
14 14
12 12
10 10
8 8
6 6
4 4
2m 2m
seabed
Suction Pile Pump skid
Suction Pile installation
Positioning and landing of Suction Pile: 10-30 min
10
Deviation from target heading (deg)
30 30
6
28 28
4 Touch 26 26
Down 24 24
2
22 22
0 Target heading 20 20
18 18
-2 16 16
14 14
-4
12 12
-6 10 10
8 8
-8
6 6
-10 4 4
2m 2m
-4 -3 -2 -1 0 1 2 3
seabed
Elapsed time after Touch Down (min)
Suction Pile installation
Weight penetration with free water evacuation
5-20 min
30 30
28 28
26 26
24 24
22 22
20 20
18 18
16 16
14 14
12 12
10 10
8 8
6 6
4 4
2m 2m
Suction Pile installation
Weight penetration with free water evacuation
5-20 min
30 30
28 28
26 26
24 24
22 22
20 20
18 18
16 16
14 14
12 12
10 10
8 8
6 6
4 4
2m 2m
Suction Pile installation
Slack lifting wire and close valves
10-30 min
30 30
28 28
26 26
24 24
22 22
20 20
18 18
16 16
14 14
12 12
10 10
8 8
6 6
4 4
2m 2m
Suction Pile installation
Pump out entrapped water and ISO 9001
certified
30 30
19
28 28
20
26 26
21
Penetration depth (m)
24 24
22 22 22
23 20 20
24 18 18
25 16 16
14 14
26
12 12
27
10 10
28
8 8
29
6 6
30 4 4
31 2m 2m
0 -20 -40 -60 -80 -100 -120 -140
Differential pressure (kPa)
Suction Penetration Driveability
20 Bar suction
side friction
Driveability
normally limited
by suction levels
critical for heave
tip of soil plug
resistance
Ample margins against
penetration refusal
280
tons Maximum 1.4 Bar
suction was recorded
during Nkossa installation
As predicted, 50%
side friction
of suction levels
estimated critical
for soil plug heave
were used to reach
tip target penetration
resistance
COMPARISON OF
INSTALLATION ASPECTS
• PILES • SUCTION CAISSONS
• HEAVY LIFT CRANE • TWO AHTs
BARGE and UNDER • LESS PER DAY COST
WATER HAMMERS • SELF CONTAINED PUMP
• HIGHER PER DAY COST SKID OR ROV MOUNTED
OF VESSEL and MORE PUMP
INSTALLATION TIME • LESS INSTALLATION
• GUIDE FRAME IS TIME AND COST
REQUIRED • POTENTIAL FOR
REMOVAL AND REUSE
DESIGN ASPECTS
Failure Modes for Suction Anchors
z
opt
zopt
zlow
z
opt
zlow
anchor top
skirt wall
Phmax
skirt wall
Phmax
skirt wall
Phmax
skirt wall
Phmax
Pvmax
Top loaded True vertical
anchor load
skirt wall
Phmax
Pvmax
Reversed True vertical
bearing load
failure
skirt wall
Phmax
Undrained loading
Undrained loading in soft
in soft clay clay
(deformations are
(deformations are exaggerated)
exaggerated) center
line
Failure modes and
Load
relative load capacity vector
diagram
Pvmax
Top loaded anchor 60o load angle
skirt tip moment to the mudline
skirt wall
Phmax
Pvmax
Top loaded anchor 60o load angle
skirt tip moment to the mudline
Rotational failure
skirt wall
Phmax
Pvmax
Top loaded anchor 30o load angle
skirt tip moment to the mudline
Rotational failure
skirt wall
Phmax
Pvmax
Top loaded anchor True horizontal
skirt tip moment load
Rotational failure
skirt wall
Phmax
Pvmax
Loading point below True horizontal
optimal position load
skirt wall
Phmax
Pvmax
Loading point below True horizontal
optimal position load
Rotational failure
skirt wall
Phmax
40o angle
Special conditions : to mudline
skirt wall
• Combination of permanent & cyclic
loads (pre-tensioning) True
horisontal
• Partly drained failure conditions load
(sand)
center
line
Gradients and seepage in sand
C
L Drained suction penetration
more critical
for heave of
soil plug
lifting
sling
umbilical pump
skid
hydraulic supply
20" for cover release
outlet and evacuation system
mooring
chain
Suction
pile
padeye
Hover position prior to pump
unit
touch Down
Adjust position
and heading
-3 .0
-2 .0
Final check of heading
Penetration depth (m)
-1 .0
0 .0
1 .0
2 .0
3.0
-5 -4 -3 -2 -1 0 1 2 3 4 5
8 NKP Barge
Deviation from target heading (degr.)
4 Touch
Down
2
0 Target Heading
-2 North
Padeye
-4
Suction
-6 pile
-8
-1 0
-5 -4 -3 -2 -1 0 1 2 3 4 5
2 .0 Tilt in X-direction
1 .0 pump
unit
0 .0 vertical axis
-1.0
Tilt in Y-direction
-2 .0
-3 .0
-2 .0
Final check of heading
Penetration depth (m)
-1 .0 Touch
Down
0 .0
1 .0
2 .0
3.0
-5 -4 -3 -2 -1 0 1 2 3 4 5
2 .0 Tilt in X-direction
1 .0
0 .0
-1.0
Tilt in Y-direction
-2 .0
X-tilt
-3 .0
-2 .0
Penetration depth (m)
-1 .0 Touch
Down
0 .0
1 .0
2 .0
3.0
-5 -4 -3 -2 -1 0 1 2 3 4 5
2 .0 Tilt in X-direction
correcting
1 .0 X-tilt
0 .0
-1.0 pump
Tilt in Y-direction unit
-2 .0
-3 .0
-2 .0
Penetration depth (m)
-1 .0 Touch
Down
0 .0
1 .0
2 .0
3.0
-5 -4 -3 -2 -1 0 1 2 3 4 5
2
Penetration depth (m)
4
weight penetration
10
12
2
Penetration depth (m)
4
weight penetration
6
suction penetration
8
10
12
2
Penetration depth (m)
4
weight penetration
6
suction penetration
8
10
12 target depth
3
4 SUCTION
5 PILE
6
7
8
9
10
11
12
6000
30
7750
13800
1000 t
150
Pad eye
Pile Anchor Configuration
11300 mm
MUDLINE
10800 mm 10500 mm
30 mm THICK
PILE CONFIGURATION
25 m
MUD LINE
116 m
91 m
Manifolds Well-head
Suction anchor
foundations
Suction anchor
Subsea manifolds
with satellites
Anchor Penetration
pumping
out water
Fsuctio
n
Fsidefriction
Weight
Ftipresistance
Exxon Diana
Suction Pile installation 1999
Houston
1500 m
Diana field
water depth
Gulf of Mexico
Exxon Diana
Platform
Diana Spar
floating storage
and production
platform
Downtown Houston
Exxon Diana
Mooring system
Downtown Houston
Suction Suction
piles piles
Exxon Diana - Suction Pile installation
Gulf of Mexico, 18 October to 12 November 1999
Cylindrical
caisson
open bottom
Installation Sequence
Anchor brought to
location
g
Installation Sequence
Anchor being lowered and
penetrates under self weight
Installation Sequence
Anchor at final penetration
Installation Sequence
Anchor left in place
3 D Finite Element Mesh
3D FEM DEFORMED MESH FOR DESIGN
Depth
0m
1000 ton
12
16
80
60
40
20
0m
Finite Element Results
10000
9000
Ultimate Load (KN)
8000
mid-level (1/2)
7000
below mid-level
lower (2/3)
6000
0 20 40 60 80 100
Load angle (degrees)
Efforts under OIDB funded projects
Suction anchors (or suction piles) are deep water anchors for
floating structures or offshore oil installations. The pile consists
of a hallow cylinder which has a top cap and a relatively thin
wall.
D
L
In-place Holding Capacity
for Nkossa anchors
Load attachment point
5.5 m above bottom of Ultimate chain load
suction pile giving optimal with 15o inclination
capacity (translation failure)
36
tons