PROJECT PLANNING &

MANAGEMENT
CE 407, CH = 2
PREPARED BY
ENGR. ZIA UR RAHMAN

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 1


LECTURE-05
NETWORK PLANNING
TECHNIQUES

2
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus
3
INTRODUCTION

•It is one of the powerful project


management techniques.
•A variety of titles have been given to this
technique, like
•PNT (Project Network Techniques)
•CPA (Critical Path analysis)
•CPM (Critical Path Method

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus


INTRODUCTION

•AOA (Activity on Arrow)


•AON (Activity on node)
•APDM (Activity Precedence diagram)
•PERT (Program Evaluation and Review
Technique)
•GERT (Graphical Evaluation and
Review Technique)
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 4
INTRODUCTION

• PEP (Project Evaluation Procedure)


• LCES (Least Cost Estimating and Scheduling)

• Network planning identifies the critical


activities that needs special attention for its
control because the completion of the project
on its due date depends upon these activities.

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 5


9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 6
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 7
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 8
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 9
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 10
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 11
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 12
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 13
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 14
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 15
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 16
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 17
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 18
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 19
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 20
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 21
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 22
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 23
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 24
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 25
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 26
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 27
Variance =(( b-a)/6)2 Project Variance

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 28


9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 29
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 30
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 31
DUMMY ACTIVITY

• It is a simulated activity with zero duration


• It is created solely for the purpose of demonstrating
a specific relationship and path of action on the
network diagram.
•EXAMPLE: E and F are the two ending
activities in aproject and C precedes E while
D precedes F. at the same time B is the
predecessor of both E and F.

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 32


DUMMY ACTIVITY

C E

F
D

B
9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 33
DUMMY ACTIVITY

C E

F
D

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 34


MILESTONE

• They are tools used in project management to mark


specific points along a project timeline.
• These points may signal the project start and end
dates/need for external review/input and budget
checks.
• They have got no impact on the duration of the
projects

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 35


FLOAT

• The amount of time an activity can bedelayed


without affecting the overall duration of the
project.
• Critical path activities by default posses no
flot.
• The manager responsible for critical activity
must ensure that it is done within the allotted
time unless it will cause a delay in the
completion of the project.

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 36


TOTAL FLOAT/SLACK
• The maximum time which is available to
complete an activity Without affecting the
duration of the entire project.
• Knowing the amount of total float enables the
manager to reschedule the activity for efficient
utilization of resources and cope with the risks
like illness, machinery breakdown, departmental
overload.
Total Float = LF – LS or EF - ES

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 37


FREE FLOAT

•It is the amount of time that allows an activity


to complete by some delay without affecting
the earliest start time of the succesor.
•It is totally based upon the earliest times of
the activities.
Free float=(ES)succesor – ES - duration

9/24/2017 Engr. Zia ur Rahman. CED, UET, Bannu campus 38


THAT’S ALL THANKS