You are on page 1of 29

KAMALA INSTITUTE OF TECHNOLOGY AND SCIENCE

Affiliated to JNTU, Hyderabad and approved by AICTE


Singapur, Huzurabad, Karimnagar, Telangana - 505468

MINI PROJECT
B.Tech(R16) Civil Engineering

Presentation on
Estimation & Costing of 2bhk Building at Sirsapally (V),
Huzrabad (M), Karimnagar(Dist.),Telangana State.

UNDER THE GUIDANCE OF


Mr. . G.Krishnaparandhama
Asst.Prof.

By
A. Ramya (17285A0101)
B. Nandini(16281A0110)
P.DeepakChary(16281A0138)
K. Sai Kiran(15281A0108)
R. Manideep(16281A0148)
CONTENTS :
 Introduction
 Detailed & Abstract estimate for
1. Earth work excavation
2. Foundation details
 PCC bed , Footing details
3. Pedestal & Plinth beam
4. Columns & Beams
5. walls
6. Slab
7. Plastering & painting
 Overall budget
 Conclusion
INTRODUCTION
Need of construction
Estimate
Data required for preparing of estimate
 Drawings
 Detailed specifications

Estimation involves the following operations


1. preparing the detailed estimate
2. calculate the rate for each item of work
3. preparing an abstract estimate
TECHNICAL DETAILS
Plot area 51.8 sq.m
Grade of concrete
beam ,slab : M20 (1:1.5: 3)
column : M20
footing : M20
 Grade of steel - Fe 500
Cover
beam – 25mm
column- 40mm
footing -50mm
slab -20mm
Contd…
 Type of foundation : shallow foundation
Foundation depth : 1.5 m
Type of footing : isolated footing
Footing size : 1.8 x 1.8 m
Number of columns : 9
Main door : 1 x 2.1 m @ no’s 3
Other doors : 0.9 x 2.1 m @ no’s 3
 Window : 1.5x 1.2 m @ no’s 5
 ventilator : 0.45x0.6 m @ no’s 2
Fig no : 1 PLAN
EARTHWORK EXCAVATION
 Width =2m , length =2m , depth =1.5
Number of pits excavated is 9

DETAILED ESTIMATE
Fig :2 Excavation pit
Sl .no Item of No’s Length Breadt Depth Quanti
work h ty

1 Excavation 9 2 2 1.5 54
for
foundation
ABSTRACT ESTIMATE :

SI.NO ITEM OF QUANTI RATE AMOUN


WORK TY T
1 EARTH 54 207 11178
WORK

EXACAVATI
ON
FOUNDATION
1. PCC bed
2. Footing
PCC BED
M7.5 (1:4:8)
Thickness -0.15 m

Fig : 3 PCC bed Fig : 4 Footing details


FOOTING
size -1.8 x 1.8 m
depth -0.75 m
cover-50 mm
grade of concrete-M20 (1:1.5:3)
Reinforcement details :
10mm dia bars at 150mm c/c
provided in the form of mat

Fig :5 Footing reinforcement


DETAILED ESTIMATE
Sl .No Item of N Length Bread Depth Qu
work o’ th antity
s
1 PCC 9 2 2 0.15 5.4

2 FOOTING 9 1.8 1.8 0.75 21.75

BAR BENDIND SCHEDULE

Item of Length No’s Unit Total


work weight weight
kg/m kg
Reinfor 1.88 26 0.616 30.11
cement
ABSTRACT ESTIMATE :

SL.N DESCRIPTIO QUANTI RATE AMOUN


O N TY T
OF ITEM
1 PCC BED 5.4 2710 14634

2 FOOTING 21.75 4000 87000


PEDESTAL
To carry loads from column
pedestal is constructed.
Size 530 x 600 mm.
Reinforcement details
8 no’s 10mm dia as main bars
8mm dia bars of 150mm c/c as
stirrups

Fig : 6 concrete pedestal


PLINTH BEAM
 This is the portion of structure
between the surface of the
surroundings ground and floor
level of the building.
 Size of plinth beam0.23 x 0.30
m
 Reinforcement details :
3 no’s12mm dia bars provided at
top
2 no’s12mm dia bars provided at
bottom
8mm dia bars of 150 mm c/c
provided as stirrups Fig : 7 Plinth beam
DETAILED ESTIMATE
SI.N ITEM OF NO’S LENGT BREAD DEPTH QUANTI
O WORK H TH

1 Pedestal 9 0.53 0.53 0.6 1.52

2 Plinth 1 27.88 0.23 0.3 1.92


beam
2(6.77+7.17)

BAR BENDING SCHEDULE


ITEM OF QUANTITY UNIT WEIGHT TOTAL
WORK WEIGHT

Pedestal 123 0.616 75.768


Plinth beam 139.5 0.88 122.76
ABSTRACT ESTIMATE :

SL.N DESCIPTION QUANTIT RATE AMOUNT


O OF ITEM Y

1 PEDESTAL 1.52 6456 9813

2 PLINTH BEAM 1.92 8269 15876


COLUMNS
 Column is a vertical member in
structure.
 Which transfer the loads from the slabs
and beams to the foundation.
 column size 230x300 mm.
 Number of columns provided is 9

 Column reinforcement
6 no’s of 16 mm dia provided as main
bars
8mm dia stirrups provided at 200 mm
c/c
Fig : 8 column
BEAMS
Beam is a structural
member which is normally
placed horizontally .
It provides resistance to
bending when loads are
applied on it .
Size of beam is 230 x 300
mm

Fig 9 BEAM
REINFORCEMENT DETAILS :
 2-16mm dia straight bars are provided at top & bottom
 1-16mm dia crancked bar is provided at bottom
 8mm dia stirrups are provided at 125mm c/c

DETAILED ESTIMATE :

Sl.n Item of No’s Length Breadth Depth Quantit


o work y

1 Columns 9 0.23 0.3 3 1.863

2 Beams 1 27.88 0.23 0.3 1.923


BAR BENDING SCHEDULE
Item of work Unit weight Total weight
Quantity kg/m
Columns 25.66 1.57 40.28
Beams 41.23 1.57 64.73

ABSTRACT ESTIMATE :

SL.N DESCRIPTION QUANTIT RATE AMOUNT


O OF ITEM Y
1 COLUMNS 1.863 7616 14188

2 BEAMS 1.923 6899 13266


WALLS
Brick masonry with cement mortar of (1:6)
Thickness of wall is 230 mm
for partition walls is 110 mm
Deductions in brick masonry
 Main door 1x2.1 m
Door 0.9x2.1 m
Window 1.5x 1.2 m
 ventilator 0.45x0.6 m
DETAILED ESTIMATE

Sl.n Item of work No Length Breadth Depth Quantity


o ’s

1 Brick masonry 1 27.88 0.23 3 19.23

Partition walls 10.2 0.11 3 3.366

deductions 4.99
=17.606

ABSTRACT ESTIMATE :
SL. DESCRIPTION OF QUANTITY RATE AMOUNT
NO ITEM

1 BRICK MASONRY 17.606 5049 88892


SLAB
Two way slab is provided.
Thickness of slab is 120mm.
Reinforcement details :
 8mm dia bars 150 mm c/c as
main reinforcement .
Fig : 10 SLAB
 8mm dia 30 mm c/c as REINFORCEMENT
distribution steel.
DETAILED ESTIMATE
Sl.n Item of No’ Length Breadth Depth Quantit
o work s y

1 RCC SLAB 1 7 7.4 0.12 6.126

ABSTRACT ESTIMATE
SL.NO DESCRIPTON QUANTITY RATE AMOUNT
OF ITEM

1 RCC SLAB 6.216 9500 59052


PLASTERING
Cement plaster of one coat
Thickness of coat is 15mm
Cement mortar ratio of 1:3
DETAILED ESTIMATE
Item of No’ Length Breadth Depth Quantity
work s
External 1 28.8 3.12 89.856
walls
=2(7+7.4)
Internal 36.68 3 110.04
walls
Deductions 10.36
=189.536
PAINTING
Painting protect the walls from water & sun
Emulsion paint is used of 2coats
 Quantity painting same as plastering

ABSTRACT ESTIMATE

SL.N DESCRIPTION QUANTITY RATE AMOUNT


O OF ITEM
1 PLASTERING 189.536 87 16489

2 PAINTING 189.536 91 17247


OVERAL BUDGET
 Total cost of material 258743
Cost towards engaging
labours and equipments 219000
 L.S provisions 12018
Total amount for 2BHK 600900
CONCLUSION
Based on the project work on 2BHK carried out the
following conclusions are drawn
Detailed estimate for different item of work
 Abstract estimate for different item of work