You are on page 1of 71

Project Integration Management

PMP Prep Course – PMBOK 5th Edition – Version 1.0

PMP Study Group

Project Integration Management

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Project Integration Management Definition

A subset of project management that includes:

“The processes and activities needed to


identify, define, combine, unify, and coordinate the
various processes and project management
activities within the Project Management Process
Groups.”
PMBoK® Guide, 5th Edition, p. 63

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 2
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Project Integration Management is . . .

Primarily concerned with effectively integrating the


processes among the Project Management Process
Groups that are required to accomplish project
objectives within an organization’s defined procedures.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 3
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Project Integration Management Processes

4.1 Develop Project Charter

4.2 Develop Project Management Plan

4.3 Direct and Manage Project Work

4.4 Monitor and Control Project Work

4.5 Perform Integrated Change Control

4.6 Close Project or Phase

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 4
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Develop Project Charter Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Work Integrated
Change
Control

Across Project Management Process Groups

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 5
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1 Develop Project Charter


Definition: “The process of developing a document that formally
authorizes the existence of a project and provides the
project manager with the authority to apply organizational
resources to the project activities”
PMBoK® Guide, 5th Edition, p. 66

PMBoK® Guide, 5th Edition, p. 66

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 6
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1 Develop Project Charter Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 67

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 7
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1.1 Develop Project Charter Inputs


A narrative description of product or services to be supplied by the project:
Project Business need
4.1.1.1 Statement of
Work Product scope description
Strategic plan
The facts that determine whether the project is worth the investment to achieve
the project objectives:
4.1.1.2 Business Case
Used to justify spending organizational assets (resources, time, money, etc.)
Used to select projects from among a list of potential projects
Define the goal of the project. Agreements can be formal or informal:
Contract
SLA’s
4.1.1.3 Agreements
Letter of Intent and Memorandums
eMails
Verbal agreement

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 8
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1.1 Develop Project Charter Inputs


External and internal environmental conditions that influence the project:
Government or industry standards
Enterprise Organization culture
4.1.1.4 Environmental
Factors Organization structure
Existing infrastructure
Marketplace conditions
Process related assets (such as plans, policies, procedures and guidelines) that
can be used for the project.
Organizational The organization’s standard and established policies and procedures
4.1.1.5
Process Assets
Document and report templates
Historical information (including lessons learned)

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 9
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Enterprise Environmental Factors - Example

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 10
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Organizational Process Assets - Example

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 11
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Project Selection Methodologies

Benefit Measurement Constrained Optimization


Methods Methods
Compare and contrast projects Mathematically model the project
against each other outcomes
Murder Board Constrained Optimization Models:
Peer Review Linear Programming
Scoring Models Integer Programming
Dynamic Programming
Economic Models:
Multi-objective programming
Present Value and Net Present Value
Internal Rate of Return
Payback
Benefit Cost Ratio

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 12
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1.2 Develop Project Charter Tools and


Techniques
Expertise provided by any group or individual with specialized knowledge or
training:
Within the organization
Expert Consultants
4.1.2.1
Judgment
Professional associations and industry groups
Subject matter experts (SME)
Project Management Office (PMO)

Used to guide the development of the charter:


Brainstorming
Facilitation
4.1.2.2 Problem Solving
Techniques
Conflict Resolution
Meeting Management

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 13
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1.3 Develop Project Charter Outputs

Formally authorizes the project


Provides the Project Manager with the authority to apply organizational
resources to project activities
4.1.3.1 Project Charter The project charter is issued by the project sponsor:
Sponsor can be an individual or a project portfolio steering committee or
the Project Management Office
The sponsor must have the authority to fund the project

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 14
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

The Project Charter


The Project Charter addresses:
Project purpose or justification Business Needs
• Market Demand
Measurable objectives and success criteria
• Organizational Need
High level requirements • Customer Request
Assumptions and Constraints • Technological Advance
High level project description • Legal Requirement
•Ecological Impacts
High level risks • Social Need
Summary milestone schedule
PMBoK® Guide, 5th Edition, p.69
Summary budget
Stakeholder list
Project approval requirements
Assigned Project Manager
Sponsor(s) of the project with authority level
©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 15
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

The Project Charter (cont’d)

The project cannot be started without a charter because


the charter:
Formally recognizes the existence of the project
Gives the project manager the authority to spend money and
commit resources.
Provides the high level requirements and expectations
Links the project to the organization’s ongoing work

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 16
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1 Develop Project Charter Miscellaneous Facts

Who can issue the A project initiator or sponsor external to the project at an
Project Charter? organizational level appropriate to funding the project.

Market demand
Organizational need
What factors are Customer request
projects taken to Technological advance
address? Legal or regulatory requirement
Ecological impacts
Social need

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 17
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.1 Develop Project Charter Terms


Factors that are considered to be true, real or certain without proof or
demonstration.
Assumptions Assumptions need to be identified, documented and validated
Part of progressive elaboration of the project
Factors that limit the project team’s options to complete the project and
Constraints produce the required deliverables

Opportunity Cost The benefit ($$$$) lost by selecting another project

Money already spent that cannot be recovered


Sunk Cost
Sunk costs are not considered when deciding whether to continue an effort
Law of Productivity and resources are not linked in a 1:1 relationship
Diminishing At some point adding resources does not yield a corresponding increase in
Returns productivity
The funds available for use by an organization
Working Capital
Calculated by subtracting current liabilities from current assets
Accounts for the fact that assets lose value over time.
Types of depreciation:
Depreciation Straight line
Accelerated

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 18
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:

Inputs for a Project Charter include all of the following EXCEPT:

A. Detailed schedule
B. Product scope description
C. Organizational need
D. Strategic plan

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 19
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Develop Project Management Plan Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Execution Integrated
Change
Control

Across Project Management Process Groups

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 20
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2 Develop Project Management Plan


Definition: “The process of defining, preparing, and coordinating
subsidiary plans and integrating them into a
comprehensive project management plan.”
PMBoK® Guide, 5h Edition, p. 72

PMBoK® Guide, 5th Edition, p. 72

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 21
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2 Develop Project Management Plan


Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 73

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 22
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2.1 Develop Project Management Plan Inputs


4.2.1.1 Project Charter Defined in Section 4.1.3.1

Outputs from
4.2.1.2 Planning Defined in Sections 5 through 13
Processes

Government of industry standards


Project Management Information System (PMIS)
Enterprise Organizational structure
4.2.1.3 Environmental
Factors Organizational culture
Existing infrastructure
Personnel administration policies and guidelines
Standardized guidelines, work instructions, proposal evaluation criteria, and
performance measurement criteria
Project management plan template
Organizational Change control procedures
4.2.1.4
Process Assets
Project files from previous projects
Historical information and lessons learned from previous projects
Configuration management

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 23
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2.2 Develop Project Management Plan Tools &


Techniques
When developing the project management plan use expert judgment to:
Decide which processes are needed for the project and to what degree do
they need to be applied
Expert
4.2.2.1 Determine resources needed and the level of involvement to complete the
Judgment
project work the plan
Develop the technical details to be included in the plan
Prioritize work to ensure resources are allocated appropriately

Facilitation
4.2.2.2 Used to guide developing the project management plan.
Techniques

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 24
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2.3 Develop Project Management Plan Outputs


Integrates and consolidates all of the subsidiary management plans and baselines
from the planning processes. It documents the outputs of the subsidiary
management plans.
It includes:
Project management processes selected by the project management team
The level of implementation of each selected process
The tools and techniques to be used to accomplish the selected processes
Project
4.2.3.1 Management How the selected processes will be used to manage the project
Plan How work will be executed to accomplish the project objectives
How changes will be monitored and controlled
How configuration management will be performed
How integrity of performance baselines will be maintained and used
The need and technique for communication among stakeholders
The selected project life cycle and associated project phases
Key management reviews for content, extent and timing

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 25
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

The Project Management Plan must have:

Buy in from all stakeholders

Approved (with signatures)

Realistic

Formal

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 26
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

The Project Management Plan

Projects are managed to baselines:

Schedule Baseline

Cost Baseline

Scope Baseline

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 27
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.2 Develop Project Management Plan Terms


Persons and organizations, such as customers, sponsors, performing
organizations and the public, that are actively involved in the project, or whose
Stakeholder interests may be positively or negatively affected by execution or completion of
the project. They may also exert influence over the project and its deliverables.

Documents not part of the project management plan that are used to manage
the project such as:
Project Charter
Project
Documents Contracts, Agreements, Statements of Work, etc.
Work Performance Reports
Risk and Issue Logs

A meeting of all parties to the project (customers, sellers, project team, senior
management, agencies, functional management, sponsor) to make certain
everyone is familiar with the details of the project and the people working on the
Kickoff Meeting project.
It is held at the end of the planning process group, just before beginning work on
the project.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 28
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:

As Project Manager your concern is to ensure the project


management plan integrates the following:

A. Subsidiary management plans


B. Outputs from the PMBOK planning processes
C. Life cycles selected and the processes applied to each phase until
project closure
D. All of the above

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 29
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Direct and Manage Project Execution Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Work Integrated
Change
Control

Across Project Management Process Groups

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 30
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work


Definition: “The process of leading and performing the work defined
in the project management plan and implementing
approved changes to achieve project objectives.”
PMBoK® Guide, 5th Edition, p. 79

PMBoK® Guide, 5th Edition, p. 79

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 31
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work


Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 80

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 32
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work


Directing and managing project work involves:
Performing activities to accomplish project requirements
Creating project deliverables
Staffing, training and managing project team members
Obtaining, managing, and using resources (materials, tools, equipment and facilities)
Implementing the planned methods and standards
Establishing and managing project communication channels (external and internal)
Issuing change requests (corrective, preventive and defect repair)

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 33
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work


Directing and managing project work involves: (continued)
Managing risk and implementing risk response activities
Managing sellers and suppliers
Including approved changes into the project’s scope, plans and environment
Generating project data ( cost, schedule, quality and progress) for reporting and
forecasting
Implementing approved process improvement activities
Managing stakeholders
Documenting lessons learned

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 34
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3.1 Direct and Manage Project Work Inputs


Project Management
4.3.1.1 See Section 4.2.3.1
Plan

Corrective Actions
Approved Change
4.3.1.2 Preventive Actions
Requests
Defect Repairs
Organizational, company or customer culture and structure
Enterprise Existing infrastructure
4.3.1.3 Environmental Personnel administration policies and guidelines
Factors Stakeholder risk tolerances
Project Management Information System (PMIS)
Standardized guidelines and work instructions
Communication requirements and policies
Organizational Issue and defect management procedures
4.3.1.4
Process Assets Process measurement database
Files and information from previous projects
Issue and defect management database

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 35
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3.2 Direct and Manage Project Work Tools &


Techniques

4.3.2.1 Expert Judgment Previously defined

Project Management
4.3.2.2 Information System Previously defined
(PMIS)
Meetings are held to discuss topics pertinent to the project:
Information exchange
4.3.2.3 Meetings Problem solving
Option evaluation
Decision making

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 36
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3.3 Direct and Manage Project Work Outputs

4.3.3.1 Deliverables

Raw data on the activities being performed to accomplish the project work. This
typically includes, but is not limited to:
Start and finish dates of activities
Deliverables that have been completed and those not completed
Work Costs authorized and incurred
4.3.3.2 Performance
Percent physically complete of the in-progress schedule activities
Data
Documented lessons learned posted to the lessons learned knowledge base
Resource utilization detail
Number of defects
Number of change requests

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 37
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3.3 Direct and Manage Project Work Outputs


(cont’d)

Corrective Action
Change Preventive Action
4.3.3.3
Requests Defect Repair
Documentation Updates

Project
4.3.3.4 Management Subsidiary project plans
Plan Updates

Project Requirements
4.3.3.5 Document Stakeholder Register
Updates Risks Register

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 38
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work Terms

An action to bring expected future project performance into conformance with


Corrective Action the project management plan

An action to ensure the future project performance does not deviate from the
Preventive Action project management plan.

An imperfection or deficiency in a project component where that component


Defect does not meet its requirements or specifications and needs to be either repaired
or replaced.

Defect Repair The action to modify a defective product or product component.

The learning gained from the process of performing the project. Also considered
Lessons Learned a project record to be included in the lessons learned knowledge base.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 39
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.3 Direct and Manage Project Work Terms


An estimate, expressed as a percent, of the amount of work that has been
completed on an activity or a work breakdown component.
50/50 Rule: Task is 50% complete when it starts and gets credit for the
remaining 50% upon completion
Percent Complete
20/80 Rule: Task is 20% complete when it starts and gets credit for the
remaining 80% upon completion
0/100 Rule: A task does not get credit for partial completion, only full
completion

A unique and verifiable product, result or capability to perform a service that


Deliverable must be produced to complete a process, phase or project.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 40
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:

As the Project Manager for Go Green Airlines you know that you
need to manage Project Execution. Which is the best response to,
define Direct and Manage Project Execution?

A. Project Charter
B. Quality Management Plan
C. Perform activities to accomplish project requirements
D. Managing people doing the work and implementing approved
changes

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 41
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Monitor and Control Project Work Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Execution Integrated
Change
Control

Across Project Management Process Groups

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 42
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4 Monitor and Control Project Work


Definition: “The process of tracking, reviewing, and reporting the
progress to the meet the performance objectives defined
in the project management plan.”
PMBoK® Guide, 5th Edition, p. 86

PMBoK® Guide, 5th Edition, p. 86

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 43
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4 Monitor and Control Project Work


Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 87

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 44
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4.1 Monitor and Control Project Work Inputs

4.4.1.1 Project Management Plan Described in Section 4.2.3.1

Described in Section 6.7.3.2


4.4.1.2 Schedule Forecasts Can be expressed in Earned Value terms or variances of planned
finish dates vs. forecasted finish dates
Described in Section 7.4.3.2
4.4.1.3 Cost Forecasts Can be expressed in Earned Value terms or variances of planned vs.
actual expenditures and forecasted final costs

Described in Section 8.3.3.2


4.4.1.4 Validated Changes
Ensures approved changes were implemented

Work Performance Analyzed data is transformed into information that can be used for
4.4.1.5
Information decision making

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 45
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4.1 Monitor and Control Project Work Inputs


Government or industry standards
Enterprise Environmental Company work authorization system
4.4.1.6
Factors Stakeholder risk tolerances
Project Management Information Systems
Organization communication requirements
Financial controls procedures
Organizational Process Issue and defect management procedures
4.4.1.7
Assets Risk control procedures
Process measurement database
Lessons learned database

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 46
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4.2 Monitor and Control Project Work Tools &


Techniques

Previously defined
4.4.2.1 Expert Judgment

Used to forecast outcomes:


Regression analysis
Root Cause Analysis
Failure Mode Effect Analysis
4.4.2.2 Analytical Techniques
Fault Tree Analysis
Earned Value Management
Variance Analysis

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 47
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4.3 Monitor and Control Project Work Outputs


Corrective action
4.4.3.1 Change Requests Preventive action
Defect repair

Project documents that report work performance information that is used to


Work Performance communicate project progress and generate decisions or activity.
4.4.3.2
Reports

Schedule Management Plan


Project Management Cost Management Plan
4.4.3.3
Plan Updates Quality Management Plan
Baselines: Scope, Schedule, Cost

Forecasts
Project Document
4.4.3.4 Performance Reports
Updates
Issues log

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 48
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.4 Monitor and Control Project Work Terms


A management methodology for integrating scope, schedule and resources and
for objectively measuring project performance and progress:
Earned Value Performance is measured by determining the budgeted cost of work
Management performed (the earned value) and comparing it to the actual cost of worked
performed (the actual cost)
Progress is measured by comparing the earned value to the planned value

An approved plan for the project work against which project execution is
compared and deviations are measured for management control. The project
Performance measurement baseline typically integrates scope, schedule, and cost
Measurement parameters of a project, but may also include technical and quality
Baseline parameters.
The project baseline may be changed by formally approved changes

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 49
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:
If a Project Manager is concerned with the process of tracking,
reviewing and regulating the progress to meet performance
objectives as defined in the project management plan, which
should she/he concentrate on:

A. Communication plan

B. Continuous monitoring

C. Project management information system

D. Scope management plan

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 50
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Perform Integrated Change Control Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Execution Integrated
Change
Control

Across Project Management Process Groups

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 51
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5 Perform Integrated Change Control


Definition: “The process of reviewing all change requests, approving
changes, and managing changes to the deliverables,
organizational process assets, project documents, and the
project management plan and communicating their
disposition.”
PMBoK® Guide, 5th Edition, p. 94

PMBoK® Guide, 5th Edition, p. 94

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 52
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5 Perform Integrated Change Control


Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 95

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 53
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5 Perform Integrated Change Control


Integrated Change Control includes the following:
Identifying that a change needs to occur or has occurred
Influencing the factors that circumvent integrated change control so that only approved
changes are implemented
Reviewing, analyzing and approving requested changes
Managing the approved changes by regulating the flow of requested changes
Maintaining the integrity of baselines by releasing only approved changes
Reviewing and approving all recommended corrective and preventive actions
Controlling and updating the scope, cost, budget, schedule, and quality requirements
based on approved changes
Documenting the impact of requested changes
Validating defect repair
Controlling project quality to standards based on quality reports

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 54
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5 Perform Integrated Change Control


The Project Manager should be concerned with:

Ensuring the change is beneficial


Determining if change is needed
Looking for alternatives to change
Minimizing the negative impact of change
Notifying stakeholders affected by the change

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 55
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5.1 Perform Integrated Change Control Inputs


4.5.1.1 Project Management Plan Defined in Section 4.2.3.1

Work Performance
4.5.1.2 Defined in Section 4.4.3.2
Reports
Corrective Action
4.5.1.3 Change Requests Preventive Action
Defect Repair

Enterprise Environmental
4.5.1.4 Project Management Information System
Factors

Change control procedures


Change approval and authorization procedures
Organizational Process
4.5.1.5 Process measurement database
Assets
Project files
Configuration management knowledge base

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 56
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5.2 Perform Integrated Change Control Tools &


Techniques
4.5.2.1 Expert Judgment Previously defined

Change Control Board Meetings:


Roles and responsibilities defined in the change control procedures
Membership on the board will include major stakeholders
4.5.2.2 Meetings The customer may be included for projects being done under
contract
Reviews change requests
Approves or rejects change requests

Used to manage change requests and the final disposition of those


4.5.2.3 Change Control Tools requests.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 57
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Who can approve changes?

Project Sponsor who signed/approved the Project


Changes to Project Charter
Charter. The Project Manager can provide input.

Changes to Project Baselines The Change Control Board or Sponsor needs to be


or any Constraints involved. The Project Manager can recommend options.

Project Manager can make the change if the change is


Changes within the Project
within the Project Manager’s authority and does not
Plan
require changes to any project baselines.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 58
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

The Steps for Making Changes

Evaluate for impact on


Evaluate impact the Project Constraints:
Create Options • Scope
• Quality
Get internal buy in • Schedule
Get customer buy in (if necessary) • Budget
• Resources
Approve or reject change • Risk
Adjust project management plan and baselines
Notify stakeholders affected by change
Manage project to the new project
management plan and baseline

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 59
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5.3 Perform Integrated Change Control Outputs


Approved Change Requests
Corrective Actions
Approved Change Preventive Actions
4.5.3.1
Requests Defect Repair
Rejected Change Requests
Validated Defect Repair

4.5.3.2 Change Log Documents changes made during a project

Project Management
4.5.3.3
Plan Updates

Project Document
4.5.3.4
Updates

Approved Change Requests are INPUTS for


Directing and Managing Project Work

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 60
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Configuration Management
A documented procedure used to apply technical and administrative
direction and surveillance to:
Identify and document the functional and physical characteristics of an item
or system

Control any changes to such characteristics

Record and report the change and its implementation status

Audit the items and system to verify conformance to requirements

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 61
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.5 Perform Integrated Change Control Terms

Providing the basis from which the configuration of products is defined


Configuration
and verified, products and documents are labeled, changes are
Identification
managed, and accountability is maintained.

Configuration Capturing, storing, and accessing configuration information needed to


Status Accounting manage products and product information effectively.

Configuration
Establishing that the performance and functional requirements defined
Verification and
in the configuration documentation have been met.
Auditing
All requested changes must be either accepted or rejected by some
authority within the project management team or an external
Change Control organization representing the initiator, sponsor, or customer.
Board Oftentimes a Change Control Board is established to approve and
reject changes. The roles and responsibilities of the Change Control
Board are defined in the configuration and change control procedures.

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 62
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:

A change control process should be created:

A. As needed per the project plan


B. By the steering committee
C. As a formal documented procedure
D. Only if changes are expected

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 63
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Close Project Phase Process

Project Management Process Groups


Knowledge Area
Monitoring &
Initiating Planning Executing Closing
Controlling

4.4 Monitor and


Control Project
4.2 Develop 4.3 Direct and Work 4.6 Close
4. Project 4.1 Develop
Project Manage Project or
Integration Project
Management Project 4.5 Perform Phase
Management Charter
Plan Execution Integrated
Change
Control

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 64
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.6 Close Project or Phase


Definition: “The process of finalizing all activities across all of the
Project Management Process Groups to formally
complete the project or phase”

PMBoK® Guide, 5th Edition, p. 100

PMBoK® Guide, 5th Edition, p. 100

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 65
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.6 Close Project or Phase Data Flow Diagram

PMBoK® Guide, 5th Edition, p. 101

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 66
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.6.1 Close Project or Phase Inputs

Project Management
4.6.1.1 Described in Section 4.2.3.1
Plan

Accepted
4.6.1.2 Scope Verification: Formal acceptance of the completed project deliverables
Deliverables

Closure guidelines, requirements and procedures


Organizational
4.6.1.3 Historical information
Process Assets
Lessons learned database

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 67
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.6.2 Close Project or Phase Tools and


Techniques

4.6.2.1 Expert Judgment Previously defined

Analytical
4.6.2.2 Described in Section 4.4.2.2
Techniques

Lessons Learned
4.6.2.3 Meetings User Groups
Review Meetings

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 68
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

4.6.3 Close Project or Phase Outputs

Final Product, Transition of the project’s (or phase’s) product or result to:
4.6.3.1 Service, or Result The ongoing organization, or
Transition The next phase of the project

Lessons Learned
Organizational Corporate Knowledge Base
4.6.3.2 Process Assets Project Files
Updates Project or phase closure documents
Historical information

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 69
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Practice Question:

Once the project is complete, the complete set of project records


should be sent to the:

A. Project archives
B. Every stakeholder on the team
C. Document Imaging system
D. Project sponsor

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 70
Project Integration Management
PMP Prep Course – PMBOK 5th Edition – Version 1.0

Good Luck!!

©2013 Long Island Chapter of the Project Management Institute ALL RIGHTS RESERVED 71

You might also like