You are on page 1of 8

Auto SYNCHRONIZING SCHEME IN CHP

SYNCHRONIZING LOGIC
SYNCHRONIZING UNIT WIRING DIAGRAM
AUTO SYNCHRONIZER RELAY CIRCUIT FOR GCB
CONTROL INPUTS

Enable/Release CB
Terminal 3
• Terminal 6 = "Enable/Release control"
If terminal 3 is energized, the operation of the power circuit breaker is enabled. Circuit breaker operation will
be disabled when terminal 3 is de-energized.
• Reply:
CB is open
Terminal 4
The status of the CB must be transmitted to the control unit through this input. The input must be energized
if the CB is open. (The status of this input is checked for plausibility and is indicated with the LED "Gen CB -
ON".)
Enable: Isolated
operation/dead bus
start
Terminal 5
Energizing terminal 5 will enable a dead bus start if the circuit breaker is open. If this input is energized and
the circuit breaker is closed, the frequency and voltage controllers are enabled for isolated operation.
Enable control
Terminal 6
If "terminal 6 is configured for "Enable control" the frequency and voltage controllers are enabled when this
input is energized
No load control
Parameter 9 Automatic idle running /Automatic no load control is kept OFF i.e., the generator
frequency and voltages are maintained at the configured set points when the circuit breaker is
open only when terminal 6 is energized.
Parameter 10 Function Terminal 6 is Enabled i.e., The controller is enabled when terminal 6 is
energized. The power circuit breaker is only enabled when terminal 3 (Enable CB) is energized.
The status of the discrete inputs ‘’Reply : CB Open’’ (terminal 4) and ‘’Enable CB’’ (terminal 3) are
displayed on the face of the controller via the LEDs ‘’ Gen CB – ON’’ and ‘’Gen CB free’’
respectively.
Discrete inputs of both the Terminal 6 ‘’Enable/Release control’’ and Terminal 3 ‘’Enable
CB’’ are enabled/made high through Push Button.
PROPOSED SCHEME
POST SCADA IMPLEMENTATION

You might also like