Professional Documents
Culture Documents
NTPC-SAIL CO.CO.LTD.
POWER PVT. LTD
2X250MW BHILAI
2X250MW BHILAI EXPANSION
EXPANSION PROJECT
Presented by
Nagamalleswararao
Emp.No.100047
Presented by
P N M RAO
250MW GENENERATOR FAILURE& RESTORATION
250MW BHEL Make Turbo Generator
Event: Unit-1 tripped on Generator differential
Protection on 18.11.2018, 9:12 Hr.
Experiences
Visual Images at different stages
Restoration process
MILESTONE ACTIVITIES
Total outage-80 days
Mobilization – with in 5days
Dismantling- with in 4days
Removal of physically damaged bars- 2days
Removal of top bars- with in 8days
Removal of bottom bars- with in 2days
Core cleaning & stator readiness- with in 5days
Connecting bus bars readiness- 3days
Bottom bars laying- with in 9days
Top bars laying- with in 7days
Nose joints brazing & insulation- with in 13days
Assembly, Oil flushing & ATT- with in 8days
ROTOR TREAD OUT
Soot deposits Molten copper particles
16 Top
15 Top
14 Top
13 Top
12 Top
Completed on day-51
HV AC TESTING
Normal joints
U-loop joints
Terminal Bushings
IPBD CTs
IPBD CT
ROTOR REPAIR AT HARIDWAR
Rotor Rewinding
Rotor Test bed