Subject: Project Planning &
Management
Department: Petroleum & Natural
Gas Engineering
Teacher: Engr. Abdul Qadir Shaikh
Introduction To Project Time
Management
INTRODUCTION
Define
Define Activities
Activities
Project time management include the processes required to
ensure timely completion of project
Sequence
Sequence
Activities
Activities

Estimate Activity Resource's

Estimate Activity Duration


Project Time Management

Develop
Develop Schedule
Schedule

Control
Control Schedule
Schedule
Define Activities

Identifying

Define Process
Specific Project
Activities Actions Deliverables

Documenting

To break down work packages into activities that provide a


basis for estimating, schedule, executing, monitoring, and
controlling the project work.
Sequence Activities

Identifying

Sequence Process
Project
activities
Activities

Documenting

Define the logical sequence of work to obtain the greatest


efficiency given all project constraints.
Estimate Activity Resources

Type
Materials,

Estimate Process estimating


Human
Resources
Activity
Resources Equipment
Quantities

Identifies the type, quantity and characteristics of resources


required to complete the activity which allows more accurate
cost and duration estimates
Estimate Activity Duration

Estimate Process Estimating


Work Individual
Period Activities
Activity
Duration

Estimated
resources

Provides the amount of time each activity will take to


complete, which is a major input into the develop schedule
process
Develop Schedule

Sequence

Durations
Develop Process Analyzing Project
Schedule Schedule
Model
Resources

Schedule

By entering schedule activities, durations, resources, resource


availabilities and logical relationships into the scheduling tool, it
generates a schedule model with planned dates for completing
project activities
Control Schedule

Project
Monitoring Progress
Activities

Control Process Achieve


Schedule plan
Manage Schedule

Provides the means to recognize deviation from the plan and


take corrective and preventive actions, and thus minimize risk