Professional Documents
Culture Documents
W5 & 6 Capital Budgeting
W5 & 6 Capital Budgeting
Capital
Budgeting
1
Learning objectives
2
Introduction
• Capital budgeting is the process of identifying,
evaluating, and implementing a firm’s investment
opportunities.
3
Key Motives
for Capital Expenditures
• Examples
– Replacing worn out or obsolete assets
– Improving business efficiency
– Acquiring assets for expansion into new products
or markets
– Acquiring another business
– Complying with legal requirements
– Satisfying work-force demands
– Environmental requirements
4
Steps in the Process
5
Steps in the Process
• Step 4: Implementation
– When to implement?
– How to implement?
• Step 5: Follow-Up
– Is the project within budget?
– What lessons can be drawn?
6
Independent versus
Mutually Exclusive Projects
7
Unlimited Funds
versus
Capital Rationing
8
Accept-Reject Decision
versus
Ranking Approaches
9
Conventional
versus
Nonconventional Cash Flow Patterns
A conventional cash flow pattern consists of an initial
outflow followed only by a series of inflows as shown
in the following Figure:
10
Conventional
versus
Nonconventional Cash Flow Patterns
12
The Relevant Cash Flows
• Major Cash Flow Components:
– Initial cash flows are cash flows resulting initially
from the project. These are typically net negative
outflows.
13
The Relevant Cash Flows
14
Methods of Investment Appraisal
• Payback period
– The length of time: cash proceeds recover the initial capital
expenditure
• Accounting Rate of Return (ARR)
– A return measurement by using average annual profits
• Net Present Value (NPV)
– The present value of the net cash inflows less the initial
investment
• Internal Rate of Return (IRR)
– A return measurement takes into account the time value of
money
15
Example
16
Data for the Projects
Project A Project B
Initial investment Tk.100,000 Tk.100,000
Cash inflows
Year 1 Tk.45,000 Tk.30,000
Year 2 Tk.40,000 Tk.30,000
Year 3 Tk.35,000 Tk.44,000
Year 4 Tk.30,000 Tk.46,000
• The depreciation is Tk.20,000 per year.
• The residual value for both projects is the same, Tk.20,000.
17
Payback Period
• The Payback period = the point in time at which cash
flows turn from negative to positive
18
Payback Period
19
Payback Period
20
ARR
Step 1: calculate annual profit
– Annual profit = net cash inflow – depreciation
21
ARR
• Project A
– Average profit = (25,000 + 20,000 + 15,000 + 10,000)/4 =
70,000/4 = 17,500
– Average capital invested = (100,000+20,000) /2 = 60,000
– ARR = 17,500/60,000 x 100 = 29%
• Project B
– Average profit = (10,000 + 10,000 + 24,000 + 26,000)/4 = 17,500
– Average capital invested = (100,000 + 20,000)/2 = 60,000
– ARR = 17,500/60,000 x 100 = 29%
22
NPV
• Assume that your company’s cost of capital is 10%
• Discount factors at 10% are:
– Year 1 0.909
– Year 2 0.826
– Year 3 0.751
– Year 4 0.683
23
NPV
Project A Cash flow Discount factor Discounted cash flow
24
NPV
Project B Cash flow Discount factor Discounted cash flow
25
IRR
• IRR: the discount rate when the net present value is zero
• Project A
– NPV = Tk.34,380 when the discount rate is 10%
– NPV = ? When the discount rate is 25%
26
IRR
• Project B
– NPV = Tk.30,172 when the discount rate is 10%
– NPV = ? When the discount rate is 25%
27
IRR
28
Project Selection
ARR Above the target rate With the highest ARR N/A
29
Advantages & Disadvantages
Method Advantages Disadvantages
Payback • simple and easy to understand and • ignores the time
use value of money
• objective – using cash flows • ignores cash flows
• liquidity – commercially realistic after the payback
• cautious & risk averse – ignores period
later cash flows
ARR • simple and easy to understand and • subjective – profit,
use not cash flows
• aids internal and external • ignores the time
comparisons value of money
• looks at the whole life of the project • difficulty in use when
•A useful tool to measure divisional with same ARR and
managerial performance various project sizes
30
Advantages & Disadvantages
31
NPV Vs. IRR
• Payback period
– Length of time until initial investment is recovered
– Take the project if it pays back in some specified period
– Doesn’t account for time value of money and there is an arbitrary
cutoff period
• Discounted payback period
– Length of time until initial investment is recovered on a
discounted basis
– Take the project if it pays back in some specified period
– There is an arbitrary cutoff period