Professional Documents
Culture Documents
1
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Lecture Objectives
2
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Project Monitoring and Control
Monitoring
• Establishing progress of the project
• Periodic review of current status
Control
• Comparing the planned v/s actual
progress
• Identifying deviations and reasons for
such deviations
• Analyzing the effect on time, cost and
performance parameters of the
project
• Corrective actions
• Updating plans
3
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Project Control
Base Plan Actual status Deviations
-schedule -schedule -schedule
-budget -budget -budget
-scope -scope -scope
Replace
Base plan Impact on Schedule, Budget & Scope
Revised Plan
-schedule
Corrective Actions
-budget
-scope
4
Faculty
©M. S. of
Ramaiah
Engineering
University
& Technology
of Applied Sciences © Ramaiah University of Applied Sciences
Project control
• Schedule/time/progress control
• Cost control
• Quality control
6
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Schedule/time/progress control
8
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Measuring Progress at Site
• Quantities installed
• Percent complete
• Effort by support services
• Milestones reached
• Tied to contract terms of payment
• Two-point measurements
• Single-point measurement
9
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Typical Reports to Aid Progress Review
10
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Typical Reports to Aid Progress Review
11
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control
12
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control
13
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control
14
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control
15
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control
16
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems
Profit/ loss at completion of contract:
•Very simple – hardly a cost control system
•Information used for future (data bank)
17
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems (Contd…)
Standard costing:
•Common in manufacturing industries
S Curve:
•Monitor cost of construction project
18
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems (Contd…)
– On awarding contracts:
•Based on activity – estimation of distribution of value
done (on a monthly basis) – Planned curve
•2nd curve – based on actual work done
19
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Planned Vs actual bill value
Cumulative
Contract Sum
Under spend
Overall delay
Time
20
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S-curve
21
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S-curve
22
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S curve – Budgeted, revised & actual cost (Contd.)
350
300
250
200
150
Actual cost
100 Revised cost
Budgeted cost
50
23
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Unit Costing
Unit costing:
– Project cost report prepared based on monthly basis
– Assists in reviewing cost every month
– Regularly assesses project cost and site contribution
– Comparison with ACE
•Matches bid rate or sales price – no profit or loss
•Lower than bid rate – estimated profit
•Higher than bid rate – estimated loss
24
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Unit Costing
25
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Steps involved – system of cost control
26
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Steps involved – system of cost control
28
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & technical performance
– Man hour
– Equipment hour
– Quantity of material etc.
29
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & technical performance
•Idea of EVM:
30
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & quality performance
(Contd.)
Involves concept of work package and earned value to analyze
performance
•Informs us regarding:
•Progress to be achieved on schedule
•Whether resources spent are commensurate with the budget
32
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Implementation of EVM
33
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Basics of EVM
34
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM
35
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)
36
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)
37
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)
Variances
•Schedule and cost variances (calculated in monetary terms)
•Schedule Variance
–SV = BCWP – BCWS
•Cost Variance
– CV = BCWP – ACWP
38
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)
Performance Indices
•SPI
• SPI = BCWP / BCWS
• If SPI < 1 – behind schedule
•CPI
• CPI = BCWP / ACWP
• If CPI < 1 – cost overrun
39
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Estimate at completion (EAC)
S. Expression for Remarks
No computing EAC
01 EAC = Actual Cost It assumes that all remaining work is
(ACWP) + Estimate to independent of the burn-rate incurred to
Complete (ETC) date.
02 EAC = ACWP/BCWP x BAC It assumes that the “burn-rate” will be
the same for the remainder of the
project.
03 EAC = BAC/CPI The formula is an extension of the
previous formula. It assumes that the
“burn-rate” remains constant for the
remainder of the project.
04 EAC = ACWP/BCWP x It assumes that the work not yet begun
[Work Completed and in will be completed as planned.
Progress] + [Cost of work
not yet begun]
05 EAC = ACWP + [ (BAC- This formula is a very subjective way of
BCWP)/CPI] calculating EAC. 40
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Summary
• Controllable elements in project
– Schedule/time/progress control
– Cost control
– Quality control
Unit costing:
– Project cost report prepared based on monthly basis
– Assists in reviewing cost every month
– Regularly assesses project cost and site contribution
– Comparison with ACE
•Matches bid rate or sales price – no profit or loss
•Lower than bid rate – estimated profit
•Higher than bid rate – estimated loss 41
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences