You are on page 1of 41

Course Code: CEE406A

Course Title: Construction Management and


Engineering Economics
Course Leader:
Mr. Akshayakumar V. H.
akshayakumar.ce.et@msruas.ac.in

Lecture 04: Project Planning in Construction cont..


Delivered by: Mr. Akshayakumar V. H.

1
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Lecture Objectives

At the end of this lecture, student will be able to:

– Explain Project Control with respect to construction projects


– Discuss the concept of S-curve and Earned Value
Management(EVM)

2
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Project Monitoring and Control
Monitoring
• Establishing progress of the project
• Periodic review of current status
Control
• Comparing the planned v/s actual
progress
• Identifying deviations and reasons for
such deviations
• Analyzing the effect on time, cost and
performance parameters of the
project
• Corrective actions
• Updating plans
3
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Project Control
Base Plan Actual status Deviations
-schedule -schedule -schedule
-budget -budget -budget
-scope -scope -scope

Replace
Base plan Impact on Schedule, Budget & Scope

Revised Plan
-schedule
Corrective Actions
-budget
-scope

4
Faculty
©M. S. of
Ramaiah
Engineering
University
& Technology
of Applied Sciences © Ramaiah University of Applied Sciences
Project control

Project Control process


5
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Controllable elements in project

• Schedule/time/progress control
• Cost control
• Quality control

6
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Schedule/time/progress control

• Establish ‘targets’ or ‘milestones’ – times by which identifiable


complete sections of work must be completed

• As each target event occurs, compare actual against targeted


performance

• Assess the effect of performance to date on future progress

• If necessary, re-plan so as to achieve original targets or to reach


as close as possible in achieving them

• Request appropriate action from those directly responsible for


the various activities 7
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Monthly Progress Report

• Reviewing of monthly progress


• Sets targets for the following month (on the basis of actual
performance till then)
• Job status for the project (or for critical structures in the
project) for reporting to higher management
• Updated continuously for regular review.

8
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Measuring Progress at Site

• Quantities installed
• Percent complete
• Effort by support services
• Milestones reached
• Tied to contract terms of payment
• Two-point measurements
• Single-point measurement

9
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Typical Reports to Aid Progress Review

• Actual versus planned bar-chart schedules and time analysed


network reports

• Activity status reports with early and scheduled starting and


completion dates, for current and balance activities, and floats

• Activity reports generated by departments, resources, costs


and sales

• About two to three months’ look-ahead plan

10
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Typical Reports to Aid Progress Review

• Report on critical activities

• Report on slipping tasks

• Report on achievement of milestone activities

• A format of three bars showing original plan, revised


plan and actual achievement till date

11
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control

•Different ways employed in a construction project


•Important aspects are:
•simplicity of the system

•low response time

12
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control

•Project cost control, a 3 step process:

•Observe cost expended for an item


•Compare with standards (ACE)
•Compute variance of observed and standard

(Warnings followed by corrective action)

13
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control

•Importance of simple system:

–Less people, less response time


–Variance found before completion of activity

14
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control

•Collection of cost for a project involves:


–Planning and Billing Engineer
–Plant and Equipment Engineer
–Time keeper and store keeper
–Accountant and office staff
•Looks simple but difficult to coordinate
•It is very difficult to detect variance in cost among different
activities.

15
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control

•Process of cost code generation, allocation and


comparison are difficult in real life

•Different control systems employed based on


requirements

16
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems
Profit/ loss at completion of contract:
•Very simple – hardly a cost control system
•Information used for future (data bank)

•Used for very small projects

Stage-wise completion of cost:


•Cost calculation – different stages (milestones)

•On completion – each stage compared with standard cost


of each package

17
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems (Contd…)

Standard costing:
•Common in manufacturing industries

S Curve:
•Monitor cost of construction project

•Depicts progress profile of construction project


• Slow at beginning
• Rapid progress in middle

• Slow again at end

18
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Cost control systems (Contd…)

– Invoiced and actual bill also monitored in S curve

– On awarding contracts:
•Based on activity – estimation of distribution of value
done (on a monthly basis) – Planned curve
•2nd curve – based on actual work done

19
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Planned Vs actual bill value

Cumulative
Contract Sum
Under spend

Overall delay

Time

20
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S-curve

– Amount billed till day of monitoring < planned

•Hence, the 2nd curve runs below


•Under spend condition
– Overall delay – indicates project running behind schedule

– Continuous curve possible


•If estimation of value of work is done in detail

21
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S-curve

– Bar chart derived from project network

•Estimated cost for activities (weekly/ monthly basis)


– S CURVE – budgeted, revised & actual cost
•Based on early start or late start of activities

•Accordingly two sets of cost are available


•Consider cost details of example project

22
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
S curve – Budgeted, revised & actual cost (Contd.)
350

300

250

200

150
Actual cost
100 Revised cost
Budgeted cost
50

23
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Unit Costing

Unit costing:
– Project cost report prepared based on monthly basis
– Assists in reviewing cost every month
– Regularly assesses project cost and site contribution
– Comparison with ACE
•Matches bid rate or sales price – no profit or loss
•Lower than bid rate – estimated profit
•Higher than bid rate – estimated loss

24
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Unit Costing

– Basic input – Cost statement


– Planning Er. – Project cost report
– Site Accountant – Input cost statement
– Close coordination required for this purpose

25
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Steps involved – system of cost control

•Step 1 – Setting up cost code

•Step 2 – Preparation of cost statement

26
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Steps involved – system of cost control

•Step 3 – Preparation of project cost report


– Prepared by Planning Er.

– Steps are as follows:


•Estimate to date: Ed=Cd / Qd
•Estimate for balance quantity: Eb=Cb/Qb

•Revised estimates: Er=Cr/Qr=(Cd+Cb)/(Qd+Qb)


•Original estimate: Eo= Co/Qo
•Variance: V= Eo- Er
27
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Sample project cost report

Source: Construction Project Management by Neeraj Kumar Jha

28
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & technical performance

•EVM integrates schedule and cost control aspects

•Determines schedule, cost and technical performance


– Compares with planned or budgeted performance
•Comparison done in monetary terms:

– Man hour
– Equipment hour
– Quantity of material etc.

29
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & technical performance

•Idea of EVM:

– Value of product increases as tasks are completed


– Measure of the real progress of project

30
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Control of schedule, cost & quality performance
(Contd.)
Involves concept of work package and earned value to analyze
performance
•Informs us regarding:
•Progress to be achieved on schedule
•Whether resources spent are commensurate with the budget

Used to forecast likely course of project – extrapolation


•Possible to forecast project completion date
•Probable cost at completion

PM can take action to avoid unwanted variances 31


Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Implementation of Earned Value Management
(EVM)

Defining scope of works


– Frozen at an early stage in project life cycle
WBS – Work Breakdown Structure
– Project broken down to logical groupings and levels
Project Master Schedule
– Details of scheduled start
– Completion of entire work

32
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Implementation of EVM

•Allocation of cost to work packages


• Principal cost elements – labour, material and P&E
•Establish – Practical way of measuring completed work
•Select performance measurement baseline
• Indicates plan to spend in different time periods for all work
packages over planned duration

33
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Basics of EVM

The three ‘S’ curves

34
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM

Budgeted cost for work scheduled (BCWS)


•Defined as budget or plan for all planned work
packages
•Derived from WBS, project budget & project master
schedule
•Cost of each package calculated
•Cumulative cost also calculated

Indicated in Master Schedule

35
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)

Budgeted cost of work performed (BCWP)


•Planned cost of the work allocated to completed activities
•Known as EARNED VALUE
•Earned Value = Percentage project complete x Project Budget

36
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)

Actual cost of work performed (ACWP)


•Real cost of works charged against completed activities
•Found by actual measurement of work completed
•Actual costs recorded from

– Invoices & workmen’s time sheets


•Appears daunting – but simple with proper planning

37
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)

Variances
•Schedule and cost variances (calculated in monetary terms)
•Schedule Variance
–SV = BCWP – BCWS
•Cost Variance
– CV = BCWP – ACWP

38
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Terminologies of EVM (Contd…)

Performance Indices
•SPI
• SPI = BCWP / BCWS
• If SPI < 1 – behind schedule
•CPI
• CPI = BCWP / ACWP
• If CPI < 1 – cost overrun

39
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Estimate at completion (EAC)
S. Expression for Remarks
No computing EAC
01 EAC = Actual Cost It assumes that all remaining work is
(ACWP) + Estimate to independent of the burn-rate incurred to
Complete (ETC) date.
02 EAC = ACWP/BCWP x BAC It assumes that the “burn-rate” will be
the same for the remainder of the
project.
03 EAC = BAC/CPI The formula is an extension of the
previous formula. It assumes that the
“burn-rate” remains constant for the
remainder of the project.
04 EAC = ACWP/BCWP x It assumes that the work not yet begun
[Work Completed and in will be completed as planned.
Progress] + [Cost of work
not yet begun]
05 EAC = ACWP + [ (BAC- This formula is a very subjective way of
BCWP)/CPI] calculating EAC. 40
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences
Summary
• Controllable elements in project
– Schedule/time/progress control
– Cost control
– Quality control
Unit costing:
– Project cost report prepared based on monthly basis
– Assists in reviewing cost every month
– Regularly assesses project cost and site contribution
– Comparison with ACE
•Matches bid rate or sales price – no profit or loss
•Lower than bid rate – estimated profit
•Higher than bid rate – estimated loss 41
Faculty of Engineering & Technology © Ramaiah University of Applied Sciences

You might also like