You are on page 1of 110

HSE Management System

• HSE management in Project life cycle of


Construction Project
Training Module Project life cycle Construction
Project
SL# Contents of the Training Module
1 Introduction of HSE management in Project Life cycle
Concept
2 Important stages of life cycle of Construction project
3 Important HSE requirements in various phases of the project
4 Business Development & Importance of HSE performance
5 Contractual HSE requirements- Cost Implications
6 Pre-Construction HSE requirements
7 HSE requirements during Construction Phase
8 HSE requirements at hand over phase
9 Quiz
10 Assessment
Introduction of Project Life cycle Concept
IN-CORPORATING SAFETY ASPECTS - TIME

High
Conceptual Design

Detailed Engineering

Procurement
Ability to
Influence Construction
Safety
Start-up
Low

Stage
Project Schedule
IN-CORPORATING SAFETY ASPECTS - COST

Start-up
High
Construction
Detailed Engineering

Cost Procurement
towards Conceptual Design
Safety

Low

Stage
Project Schedule
Phases of Project Life Cycle- BD
• Business Development- We share our HSE
performance- Statistics, Awards, Accolades
&Credentials

• Understand the Contractual HSE terms & Conditions-


Allocate the budget for HSE expenditure under guidance
from corporate/regional HSE team.

• Pain & gain policy for HSE performance by client- Weigh


the implications

• Communicating the HSE requirements of client to project


team before start of the project.
• Communicate SPCPL standards to client
Phases of Project Life Cycle- Planning/Design-
HSE Plan
• Preparation of HSE plan based on the contract with the client,
to be prepared by HSEO under guidance of PIC

 Assigning Roles &


Responsibilities related to
HSE

 HSE Committee
formation

 Listing of Activities

 Preparation of
IER/IOHSR

 Prioritization of
Risks/Hazards &
Phases of Project Life Cycle- Planning/Design-
HSE Plan
 Listing control for all the significant
procedures
hazards/risks & aspects/Impacts- Procedures are
provided by corporate HSE

 Request for preparation of new procedure, if any through


amendment request form

 Labour welfare measures at site & labour camp-


Standard labour camp design is to be released by
Corporate team.
 Admin control for labour/staff- Biometric for better safety
and social welfare
Phases of Project Life Cycle- Planning/Design- HSE
Plan
 Material logistic plan

 Office layout plan- Include HSE park & induction


room( with T.V & DVD facility), First Aid room,
Ambulance room, Toilets for site staff

 Vehicle logistic plan-


• Vehicle speed display
• Control of unauthorized vehicle by admin
• License/PUC/Registration/Insurance at the gate

 Material stacking plan/Other critical storage like


diesel/Gas cylinders etc.
Phases of Project Life Cycle- Planning/Design-
HSE Plan

 Canteen (More than 250 workers)


 Kick off meeting with the project team
 PPE start up stock , Fire extinguishers
 HSE Staff deployment
 Inspection of Plant & Equipment
 Underground/Overhead utilities
 Obtaining drawing from concerned
agencies
 Hazardous waste storage area –
identify
 Emergency assembly area-
Identify
Phases of Project Life Cycle- Planning/Design-
HSE Plan
 Scrap storage
 HSE Signage & posters
 Fencing requirements
 Temporary works coordinator
 Sedimentation tank for Batching plant, Sprinkler system for
aggregates
 Edge/floor openings protection requirements-Plan
 Life line provision planning at critical locations like tower crane, height
works, Batching plant
 Type washing area
 forest -Plantation area identification
Phases of Project Life Cycle- Planning- HSE
Plan- Labour Camp
 Camp Boss deployment

 Trained First aider provision

 Fire Safety Plan

 Anti Social Activity Check- Alcohol/drugs Plan


Phases of Project Life Cycle- Planning/Design-
Emergencies
• Preparation of Emergency Plan:
 Assess local environmental conditions like wind speed (for
Tower Crane/Height Work), Rainfall data ( From IMD for
flooding), Proximity to coastal area ( For cyclone), Seismic
zone ( For earthquake), Type of Soil ( for planning
excavation), Danger of Wildlife, Ground water Availability &
quality

 Local political issues

 Social issues

 Tie up with Fire services


Phases of Project Life Cycle- Planning of
Emergencies
 Tie up with Local police station

 Tie up with Hospital for Emergencies,

 Tie up for regular Medical check up of workers/operators/drivers

 Tie up for Availability of Ambulance at the site

 Liaison with PCB authorities

 Liaison with Labour Inspector/Factory Inspector

 Liaison with Petroleum & Explosives Safety Organization (PESO) for


storing Fuel above 2500 liters
Phases of Project Life Cycle- HSE Plan- Identification
of Agencies
 For Environmental Monitoring/Disposal of
Hazardous/e/Biomedical waste

 For Water Quality testing as per IS


10500 code for drinking

 For Pest Control

 For Security at the site

 Third parties for calibration & testing of critical


equipment/machines/tools/tackles etc at the site
Phases of Project Life Cycle- Planning/Design

• Incorporate the safe & green features in the


planning phase
Examples of Engineering controls in design

 Scaffolding selection- Example PERI


 Form work selection- Example MIVAN/Geoplast
 Automatic bar bending & cutting machine
 Use of block work & transportation by fork lift
 Precast slab
 High frequency vibrator
 Debris chute
 Taps for curing at each floor
Advanced Scaffolding system

The PERI scaffold system is the modular reinforcement


scaffold for efficient work. A reinforcement scaffolding is a
special type of facade scaffolding. It is characterized by the
fact that no anchors are required
Advanced Scaffolding system
• With proper support system, the use of plywood
is minimized
• It is reusable and minimizes wastage of resources;
Plywood consumption is 84% less in modular scaffolding
as compared to conventional scaffolding for columns &
100 % timber is saved in modular scaffolding system.

• Time and motion improvements can slash costs.


• Cleaning and maintenance can be done by BIO
Clean agents.
• Safety- Provision for safe access, egress, fall protection
( toe board, guard rail, anchoring is provided in design)
Advanced Formwork

Uses of Mivan Formwork:


 3S – System of Construction – Speed, Strength,
Safety
 Column and beam construction are eliminated
 Walls and slabs are cast in one operation
 Specially designed, easy to handle light weight pre-
engineered aluminium forms
 Fitting and erecting the portion of shuttering
 Carrying out concreting of the walls and slabs
together
Automatic Bar bending & Cutting machine

• Reduction in wastage of steel by 2-3%

• Reduction in the hazards & risks involved in the bar


bending & cutting operation

• 40% Less number of workers as compared to


conventional machine

• Improvement in productivity & precision


Precast Technology
Step-6 Concreting

Step-5 Stacker Chamber


Step-4 Reinforcement

Step-7 Finishing

Step-3 Shuttering

Step-2 Plotting

Step-8 Tilting

Risk ( N*L*S)- is
reduced in precast
work Step-9 Storage Step-1 Cleaning

N- No of person Pre-Cast Technology Process @ SP E&C site


L- Likelihood
Precast Technology- Advantages
• No Use of Ply for casting the slab saves lot of wood
which would have been used in absence of the
technology.
• Minimum transportation of pre-cast slabs is
assured to save on fuel.
• Technology helps in saving around 90% of water as
compared to prevailing slab casting technology
• Enviro friendly totally re-locatable, recyclable, 90%
waste free and minimizes double handling and transport
via on- site manufacturing.
• Generation of concrete waste during the slab
casting process is abysmal.
Precast Technology- Advantages
• Technology has an option to provide a fully packaged, fully
scoped thermal solution, delivering both exceptional
savings and environmental benefits for your building
project both during construction and post construction
‘maintenance’ stage. The thermal package can help to
reduce the running cost of your building by 30 to 50%.
• REDUCED COSTS in running and maintenance of the
building – up to 50% post construction
• Safety- Precast blocks reduces height work and are lifted
by mechanical means
• Reduces fall/trip hazard due to less formwork/scaffolding
at the site
• Reduces hazards/risks involved in curing activity
Debris Chute for Safe Disposal
Important points for PIC before starting the
Project
• Identification of legal contractual requirements

- Registration under BOCW 1996/98 within 60 days of


commencement of the work ( more than 10 workers
preceding 12 months)- Form III

- Labour license

- Interstate migrant workers 1979- more than 5 workers


from other states
Important points for PIC before starting the
Project
- Registration of beneficiaries under BOCW
- ESI for employees with salary less than Rs 15000
- Labour license
- Workmen Compensation policy
- Interstate migrant workers 1979- more than
5 workers from other states
- Labour Camp Mandatory facilities/ location)
• Suitable Accommodation(35 Sq.ft/person-
SPCPL)
• Utilities- Toilets- 1 toilet per 25 person
• Washing/ Bathing area- Shall be Covered in
case of projects in cold areas.
Important points for PIC before starting the
Project
4. Separate toilets for female workers

5.Creche for children in case of more than 50 female


workers

6. Recreation area with T.V & indoor games

7.Dining & kitchen area- no cooking inside the room shall


be allowed

8.Medical check up of workers- ENT, B.P, Vertigo, skin


Epileptic, diseases for cook
Consents to be taken before starting the
Project
• Consent to operate (CTO)/Consent to Establish (CTE)-
DG

• CTO/CTE-Batching plant

• Storage of diesel- more than 2500 liters- License


required

• Construction water- Borewell- Permission from ground


water department, Pay water cess if water taken from
municipal corporation

• Storage of Gas Cylinders


Project Life Cycle
Major HSE Concerns
• Excavation Works
• Construction Vehicles/Equipments
• Reinforcement Works
• Formwork/Shuttering
• Concreting Works
• De-shuttering
• Height works – Edge Protection/Floor Opening/Fall
• Scaffolds
• PNM – Machine Guarding, Electrical Safety , LOTO,
• Flammable storage
• Lifting Tools/Tackles & Equipments – Cranes & Slings
• Passenger/Material Hoists
• Glass façade/Plaster/Painting works
Excavation

Soil Types :-
1) Stable rock :-
It is natural mineral matter. It is solid. Identified as Granite or Sand.

2) Type A: - (1.5 T /sq. ft)


Cohesive soil - Example:- Clay, Silty clay, Clay lime.( If it is Fissured, subject to
vibration or previously Disturbed it is not A)

3) Type B (0.5 to 1.5 T/sq ft)


Cohesive soil - Example:- Angular gravels, Silt, or Previously disturbed soil.

4) Type C (<0.5 T/sq ft)


Cohesive soil with an unconfined compressive Strength less than 0.5 ton/ sq.ft
Example:- Gravels, Sand, Submerged soil, Soil Where water is seeping.

5) Layered
Combination of the above
Excavation Hazards
Excavation

• UG & Over head utilities


• Nomination of Project Engineer – Weekly Inspections
• Warning signs, notices & barricades
• Stability of nearby structures
• Piling, shoring, bracing – Type of Soil
• Safe Access, Egress
• Positioning and use of machinery
• Dewatering arrangements/Monsoon plan
• Vehicle Equipments fitness & movement (avoid
reversing)
Excavation

• Drivers/Operators Competency
• Rest shelters – (resting below vehicles?)
• Handling/Storage of HSD
• Illumination
• Emergency Action
• Regular inspection
• Loose material on the edges, cave-in
• Material stacking & disposal of soil
• Work at nights
• Work in Monsoon
• Loading & Unloading of tippers
Soil Collapse - Fatality

WORK
LOCATION

Fatality due to Soil collapse


Construction Vehicles & Equipments

Construction Vehicles
& Equipments
evolved much
but…………

Operator's Mind?????
Construction Vehicles & Equipments

• All vehicles/equipments shall be fitted with -


– Reverse horn, side mirrors, back light, indicators, head
lights
• Only Operator to sit in cabin
• Reverse under helper direction
• Do not park on excavation edges/slopes/no parking zone
• Maintain daily routine inspection
• No resting below vehicles
• Abide by speed limits
• No unauthorized driving
The Signaler & his
position
5X5 – Five feet
away and five
feet behind the
driver’s side rear
corner

October 19, 2015


Vehicles/Equipments

Operator/Driver can
not see Grey area
Reinforcement Works

• Lay out of the stack yard/ cutting Bending yard


• Positioning of Cutting, Bending Machines
• Use makeshift pin for bending machines
• Electrical lay out
• Scrap yard & disposal
• Rest Shelter
• PPEs
• Shifting/Lifting of Steel (Manual/Mechanical)
• Tying of steel
• Walkway on steel
• Stability of vertical steel skeleton
• Reinforcement bar end-caps
Process Reference

SP-O-2.2/11-36 Bar bending and Cutting


`
Concrete Works

• Access ways – ground conditions


• Concrete pouring plan
• Positioning of Pumps
• Transit Mixer Operator working hours/rest
• Installation of concrete pipe line
• Pipe line Supports
• Use of concrete buckets (Crane Safety)
• Concrete bucket locking arrangement
• Signaler
• Lighting arrangements – earthing for light posts
Concrete Works

• Method of concrete
• Positioning of pump
• Ground condition
• Operator Competency
• Overhead power lines/obstructions if any
• Signaler
• PPEs
• Ball passing
• Electrical cable layouts, lighting masts, DBs, ELCBs
• Electrical Vibrators/compactors
• Electrical Safety
• PPEs
Column/Slab Casting

• Selection of Formwork
• Area for storage
• Carpentry workshop location
• Nailing & de nailing
• Lifting/shifting of formwork/shuttering materials
• Fixing of formwork/shuttering
• Mechanical lifting – Lifting tools Tackles/Equipments
safety
• Supporting arrangements – ground conditions,
bracings
• Access to deck
Column/Slab Casting

• Edge protection – life line (provision for hard


barricades?)
• Floor openings barricading
• Access & walkway
• Electrical cable, lights layout-earthing
• Staircase - temp. handrail provision
• Provision for TC anchoring
• Inspections – pre-during-post concrete
• Curing water line location
• Hard barricading for slab edges
• Waste concrete – green stage washing
De-shuttering

• Area Cordoning
• PPEs
• De-nailing
• Material Stacking
• Floor cleaning – waste collection/disposal
• Use of Crane? – Lifting tools/Tackles/Equipments Safety
• Operator/Signaler/Slinger competency
• Area cleaning, collection/disposal of waste
• Stacking of de shuttered materials
• Access ways
Work at height

HAZARDS – Work at Height


1. Fall of person
2. Falling objects
3. Slip, trip & fall

• Fall prevention
• Fall protection
• Overhead protection around the building & entrance
• Tower crane /Material/Passenger Hoist installation
• Anchors, earthing, structural braces
• Rigging plan, team competecny
• Safe slinging
Free Fall

1.2m 0.5 Sec A body in motion (free fall) can


cover vast distance in a short span
4.9m 1 Sec of time. A body in free fall can
travel:
 1.2 m (4ft) in 0.5 seconds.
19.6m 2 Sec  4.9m.(15ft.) in 1 second
 19.6 m.(58ft) in 2 seconds
Fall – Prevention, Protection

Fall Prevention Fall Protection

Fall prevention is any means Safe stopping of a person already


used to reasonably prevent falling. To do so Personal Fall
employee exposure to a fall Protection System to be used.
hazards
Personal Fall
 Guardrails Protection System
 Safety nets consist of
 Covers
 Anchorage points
 Fences
 Lanyard
 Barricades
 Snap hooks
 Life lines
 Body harness
Guardrails/Edge protection

Guardrails – Most common form of protection

Flags shall be provided on wire rope to increase visibility

 A handrail between 910mm and


1.15 m
 Toe board at least 150mm high
 Space between toe board and
handrail not more
than765mm
 Must withstand 90 kg
pressure
Guardrails/Edge protection

Guardrail constructed of wooden


plank (Hand rail, Mid rail
provided but Toe guard missing)

Guardrail constructed of
steel pipe (Handrail, Mid rail
& Toe guard provided
Fall Protection

Fall Protection
Safe stopping of a person already falling. To do so Personal
Fall Protection System to be used.
Anchoring

Before Anchoring ?? Before


Fall After Fall Anchorage Anchorage
Fall After Fall
Calculation Calculation
Height of
Lanyard 2m 1.8m
Length Worker

Lanyard 2m
Length
Total fall distance
Height of
Worker 1.8m
Height of 1.8m
Safety Worker
1m
Factor Safety 1m
Factor
Total = 4.8m
Total =

6.35m
Anchoring point should be above the head for minimizing fall distance
Life- Line
A component consisting of a flexible line for connection to an anchorage at one
end to hang vertically (vertical lifeline), or for connection to anchorages at both
ends to stretch horizontally (horizontal lifeline), and which serves as a means
for connecting other components of a personal fall arrest system to the
anchorage.

d
lin use
e
Li rab
th G
fe
w i pe
Ro
Horizontal Life Lines
General Rules for safety net

 Safety nets must be installed as close


as
practicable under the surface on Drop test per IS 11057 :1984.
employees are working, but in no case more
which
than 30 feet below.
 The potential fall area must be unobstructed.
 Safety netsmust extend outward from the
outermost projection of the work surface as
follows:
Vertical distance Minimum required
from working level to horizontal distance of
horizontal plane of outer edge of net from
net the edge of the working
surface
Up to 5 feet 8 feet
5 to 10 feet 10 feet
More than 10 feet 13 feet
General Rules for safety net

• Inspect once a week


• Regular clean up
• Ensure border rope for webbing
• Ensure strong net connections
• No gaps in between
• No hot works
• Installation/shifting of nets under
Supervision
• Storage of nets
Floor Opening

A hole or opening in a floor, roof, or platform


that measures 300mm or more in its least
dimension, wide enough to permit a person to
fall or material to fall.

Holes & openings should be


made safe immediately
after they are formed.

Hazard due to floor opening /hole can be safe guarded by providing covers
as shown above
Floor Opening

Whenever it is not practically


possible to cover the floor
opening/hole, It shall be fenced
or barricaded
• By putting hard barricading
(Using steel pipes ,rods)
• By putting soft barricading
(Using ropes )
Overhead Protection

3:31:14 PM
Scaffold
Scaffold

• Scaffold construction – Types


• Ground strength- Base plates, Plumb, diagonal bracings
• Height to width ratio
• Tying with the structure
• Access
• Platforms, access, handrails, Materials on the platforms
• No material stacking on platforms
• Inspection – Scaff-tags
• Erection & Dismantling
• Competency of scaffolders
• Overhead power lines if any
Scaffold

• Arrangements for corner column casting in place?


• Exterior plaster/painting works
• Use of suspended work platforms
• Protection against fall of men & materials
• Access arrangements to reach work locations
• Non use of scaffold members in any lifting
operations
• Screening nets/safety nets for simultaneous works
Scaffold
Ladder

• Fabrication of ladder – Material, rungs, handrail


• Angle of ladder
• Tying of ladder
• Extension of ladder above platform
• Overreaching
• Use of ladder as platform
• 3 point contact
Plant and Machinery

Electrical Layout
Regular ELCBs, Earth Resistance Testing
Electrical Panel boards, DBs, Matt, Danger stickers, Gloves

Workshop/Plant/Machinery Layout
Lathe, grinder & other machine guarding
Plants – Lock out Tag out
Waste Oil/Filters/batteries management
Waste water management
Schedule of preventive maintenance of Equipments/cranes
Drivers/Operators/Electricians Competency, Medical
Electrical Safety

Terminology
• Current – the movement of electrical charge
• Resistance – opposition to current flow
• Voltage – a measure of electrical force
• Conductors – substances, such as

metals, that have little resistance to

electricity
• Insulators – substances, such as wood, rubber,
glass, and Bakelite, that have high resistance
to electricity
• Grounding – a conductive connection to the earth
which acts as a protective measure
Electrical Shock

• Received when current passes through


the body
• Severity of the shock depends on:
 Path of current through the body
 Amount of current flowing through
the body
 Length of time the body is in
the circuit
Body Resistance

Body area Resistance (ohms)


Dry skin 1,00,000 to 6,00,000
Wet skin 1000
Internal
body 400 to 600
Person
Hand foot
in touch
POWER with
SOURCE
live wire

I = V/R
= 230 / 100000 A (Dry
Condition)
= 0.0023 A
= 2.3 mA
= 230 / 5000 (Wet Condition)
= 0.046 A
= 46 mA
Hazards of Electricity

– 240 Volts can kill • Regulations made under the Act:


– Electricity can cause: – Electricity Act & Rules
• Shock • Systems to be safe
• Burn • Use of safe systems of work
• Explosion • Live Working
• Falls • Competence
• Fires
• Unexpected start-ups etc.
• Unsafe installations can kill
Maintain min clearance 15 feet for Overhead
lines
Effects of different levels of current on the human body

• 1 mA: Can be felt by the body


• 2-10mA: Minor shock, might result in a fall
• 10-25 mA: Loss of muscle control, may not be able to let go
• 25-75 mA: Painful, may lead to collapse or death
• 75-300 mA: Last for 1/4 second, almost always immediately fatal
Temporary Electricals

Practice of makeshift DB with no weather Practice of safe DB under shed with 3 pin
protection, inserting bare wires in to fuses for sockets and plugs under use with ELCB
connections. No ELCB

Not using electrically


insulated hand gloves
while working on
panels/ DB’s
Use of HRC fuses
DBs
Temporary Electricals

• Protective shed & double visible Body earthling for each DB & equipment
• Provide & Maintain Earth pit & Earth resistance checking monthly
• For portable power tools power supply should be taken through
ELCB - 30 mA sensitivity for 30 milliseconds
• Test the ELCB regularly and record it.
• Use HRC fuse
• Avoid Loose connection of cables & insulate joints appropriately
• Use male female sockets
• Ensure Fire Extinguisher of correct type for Electrical panel rooms
• Inspect portable power tools
• Use double insulated power tools
• Cables shall be either underground or overhead
Machine Guarding

Dangerous moving parts in these


basic areas require
safeguarding:
• Point of operation
• In running nip points
• Pinch points
• Power transmission
• Other moving parts
Powered Hand tools

• Do not remove guards


• Use double insulated hand tools
• Match the wheel RPM with M/c
• Use industrial plugs for connection
• Get it inspected
• Do not lift the tool with the cord
• Do not use gloves on rotating machines
• Use PPEs
Loto & Flammable Storage

6 Step LOTO Procedure


• Prepare for Shutdown
• Shutdown Equipment
• Isolate all energy sources
• Place Locks & Tags
• Release Stored Energy
• Verify Equipment Isolation
• No hot operation on empty drum
Flammable Storage • Do not roll cylinders
• Quantity –License requirements • Use cylinder trolley, cylinders cap & chain
• Location, shed • Mark cylinders Full or Empty
• Spill control • Do not cross electric cables over cylinders
• Ventilation, Illumination • Store cylinders separately as per contents
• Electrification
• Fire Prevention, Protection
• Flash back arrestors
Lifting Equipments
Crane Signals

Ensure Signalman/Slinger is well


versed with the signals
Operator & signaler/slinger
competency
Medical/eye check up
Identification of signaler/slinger
Means of communication
Crane Hazards
• Contact with power lines]
Overturns
Falls
Mechanical failures
Collisions/entanglement – Overlapping Tower cranes Instability
– unsecured load, load capacity exceeded, or ground not level or
too soft
Lack of communication - the point of operation is a distance from
the crane operator or not in full view of the operator
Lack of training
Inadequate maintenance or inspection
Lifting/Shifting

• Rigging plan
• Crane condition
• Lifting tools tackles SWL
• TPI certificate
• Operator, slinger, signaler competency
• Illumination
• Safe distance
• Wheel chocks
• Travel road condition
• Guy ropes
• Cordon off
• Tandem Lifting
• PPEs
Lifting Tools/Tackles

• Tyre/crawler/outrigger condition
• Cordon off - suspended load
• The operator should not use
• (i) a limiter as means of stopping a motion &
• (ii) a working load limiter as normal means to
determine that load can be lifted
• No Dragging load
• Wind speed
• Overlapping tower cranes
• Stopper for rail mounted cranes
• Alarm for rail mounted crane for movement
Tower Crane over lapping & Gantry Crane collision
Lifting Tools/Tackles

Lifting Tools Tackles & Equipments Construction & use


Test & periodical examination
Operator competency & medical check up
Lifting Tools/Tackles

Wear exceeds 15%


of a link diameter.

Hooks should be removed from service if


they have been opened more than 15% of
the normal throat opening, measured at
the narrowest point,
Lifting Tools/Tackles

Remove from service if the


following are present:

Ten randomly distributed


broken wires in one lay, or
five broken wires in one
strand in one rope lay.

Wear or scraping of outside


wires reducing the
individual ire diameter by
1/3rd

Evidence of heat damage

Corrosion of rope or end


attachment
Lifting Tools/Tackles

DISTANCE

DIAMETER OF THE BOLT


Lifting Tools/Tackles
A synthetic fiber web sling must be removed from service when any of
the following circumstances occurs:
– The length of an edge cut exceeds the web thickness.
– The penetration of abrasion exceeds 15% of the webbing thickness when
taken as a proportion of all piles.
– Abrasion occurs on both sides of the webbing and the sum of the abrasion
on both sides exceeds 15% of the webbing thickness when taken as a
proportion of all piles.

Identification: Synthetic fiber web slings must be permanently identified


with the:
– Manufacturer's name or mark.
– Manufacturer's code or stock number.
– Working load limits.
– Type of synthetic web material.
If The Identification Tag Is Missing, The Sling Should Not Be Used
Sling Angle

At 45 degrees, H = L
As the angle becomes less than 45
degrees,
H will be less than L
Therefore ensure that H is always = or > L
Passenger/Material Hoist
•Location
•Overhead protection – loading point Barricades, gate at
floor levels Communication system, door limit switche
Third party certification
•SWL marking Fire
extinguisher
•Material loading platforms stability Entrance
platform guarding to Hoist
Mechanical, Electrical & Plumbing- (Servicing
Work)

• Fire hazard – paints/solvents & other materials


• MEP – Multiple agencies at work
• Ducting open end barricades
• Simultaneous works
• Electrical hazards
• Finishing works
• Coordination
Housekeeping – 5 S

5S Housekeeping - Fundamentals

Seiri Sort
Remove unnecessary items as appropriate

Seiton Set
Prefix a place for everything and put everything in place

Seiso Shine
Cleaning not for beautification alone but with a sense of
purpose

Seiketsu Standardize
Develop standards/evaluation criteria.

Shitsuke Sustain
Create awareness of all 4Ss and train to implement
Housekeeping
Material Stacking
Project Safety Initiatives

Induction Training
Tool Box Talks
Work Permits
HSE Lecture
HSE Walk
Speak & spread
Sport
Safety
Trainings/Mock
drills/Fire
demos
Safety Motivation - Safety Award/safety week
celebration Stop Work/Safety Warnings/penalties
Demobilisation and Project Completion
Major Activities during part/ final demobilization
• Demolition Works
• Dismantling of Heavy Plants and Equipment's
• Dismantling of temporary structures (Site offices, Stores,
hutments, workshops etc.)
• Loading / Shifting of surplus materials to other sites in
Trucks/ Trailers.
• Lifting and Shifting by Manual or Mechanical means.
• Segregation of reusable PPE’s and Safety Materials.
• Disposal of Hazardous Waste.
• Preserving Important HSE documents at RO / HO.
• Obtaining Project Completion Certificate from Client.
Safety in Demolition Works
• Involves many hazards associated with
construction
• Behavior of material different under
dynamic
loads of demolition
• Adequate preparation required for execution of
demolition task with regard to the health and
safety of the workers.
• Preparatory operations involve –
 Overall planning of the demolition job
 Methods to be used to bring the structure
down
 Equipment necessary to do the job
 Measures to be taken to perform the work
Safety in Demolition Works
Method Statement for Demolition
• Structural calculations as necessary
• Pre-weakening procedures
• Procedures for falling structures and/or lifting
of structural members
• Methods of cutting steelwork and removal of
debris
• Protection to be provided for operatives,
third parties, adjacent buildings, etc.
• Special procedures for dealing with asbestos,
lead, chemicals, storage tanks and any other
specialized structure or identified material
Dismantling of Heavy Plants and Equipment's
Safety Concern
• Equipment operated by Unskilled / Untrained /
Unauthorized operator
• Engaging Hire Equipment for short job,
• Use of untested / Scrap lifting tools and tackles
• Insufficient resources
• Lack of planning & Supervision
• Incorrect sitting or setup of Crane.
• Fail to calculate or estimate correct load.
• Failure to carryout the correct procedure
• Careless or Complacent.
• Faulty devices or machines
• Lack of proper maintenance
Dismantling temporary structures

Safety Concern
• Temporary works considered as low risk work
and executed by junior staff.
• Due to unavailability of required equipment for
dismantling, demolition is done manually by
hammer, chisel etc.
• No methodology is prepared for dismantling
work.
• Activity not considered under HIRA.
• Unsafe / unstable platforms are used for
dismantling.
• Non use of PPE
Shifting of Materials
Temporary shifting of heavy
material
• Assuming the short distance materials are not
secured properly.
• Over head utilities not inspected on road.
• Operator Overconfidence
• Non availability of proper transport vehicle.
• Improper use of lifting equipment.
Shifting of Materials
Shifting of material manually
• Multitasking work carried out from workers.
• Lack of coordination.
• Not following kinetic method of lifting.
• Untrained / Unskilled workforce for temporary
shifting work.
• Lifting movements are not coordinated
• Non use of required PPE.
• Lack of Supervision
• Materials not separated out before being
lifted
• Lack of concentration while lifting
• Poor housekeeping and stacking of materials
Segregation of reusable PPE’s and Safety Materials
After completion of Project, site should segregate given
below reusable materials
• Requisite PPE like Helmets, Hand gloves, Goggles, Safety
Shoes, Full Body Harness etc.
• Safety Nets
• Sign Boards
• First Aid Box
• Safety Park
• Fire extinguishers
• Flashback arrestors
• Trolley for gas cylinders
• Earth Leakage Circuit Breakers (ELCB),
Type of Waste & Disposal
Common Hazardous Waste
• Used Oil
• Oil & Grease soaked cotton
• Contaminated drums, cans, other containers
• Battery
• Cement Bags
Bio Medical Waste
Cottons, Bandages, Expiry medicine, dressing
materials, syringe etc.

E- Waste
• Electrical wire, plug, bulb
• Electronic chip
• Switchboard, Panel board
• Computer accessories
General HSE Concerns
• Multitasking work
• Non availability of Safety Staff at Projects near completion
• Lack of Planning
• Lack of Supervision
• Lack of Coordination
• Leaving the job on Subcontractor.
• Limited resources
• Low budget at the end
• Use of unmaintained plant (Temporary hired Plant)
• Low priority for safety
• Poor welfare measures
• Poor Housekeeping
• Low awareness (Lack of trainings)
Project Completion Requirements
The HSE documents are really the manifestation of the
process in that it becomes the repository of all the relevant
documentation.
 Any documents pertaining to legal implications has to
be preserved. Eg. Consents, fatality reports etc.

Awards details

Awards and Appreciation received from Clients or other


agencies shall be submitted to RO/ HO for company
records.
 Appreciation letters on quality work, Injury Free Million
Man Hours, adopting high safety standard etc.
 Awards from external agencies like NSC, CLI,
Greentech etc.
Project Completion Requirements

Defect Liability Period


Before handing over the completed site owner we need to see contract
to document for defect liability period.
• Ensure that there is adequate funding for executing the work during this time
including HSE requirements.
• List out the activities which are to be executed during defect liability period.
• Prepare the list of equipment and PPE’s required
• In case of high risk activities consult HSE department.
• Keep minimum resources (Manpower, PPE, safety gears etc) in stocks.
Demobilisation and Project Completion
After completion of site, Project Manager has fill Complete demobilisation form to
RO / HO declaring that records pertaining to the project activity as per the HSE
management system are destroyed which are having no legal implications and the
documents which could have potential legal implication should be retained at RO
with a copy to HO.

Declaring Complete demobilization of


13
Project
INCORPORATING SAFETY ASPECTS - Summary
• The earlier safety (along with
production, quality, project scope,
etc.) -more Positive influence
it will have on the total
project!

• It is effective to design safety into a process than


manage safety within a process that is inherently unsafe.
in HSE TO
IMPROVE

You might also like