Professional Documents
Culture Documents
High
Conceptual Design
Detailed Engineering
Procurement
Ability to
Influence Construction
Safety
Start-up
Low
Stage
Project Schedule
IN-CORPORATING SAFETY ASPECTS - COST
Start-up
High
Construction
Detailed Engineering
Cost Procurement
towards Conceptual Design
Safety
Low
Stage
Project Schedule
Phases of Project Life Cycle- BD
• Business Development- We share our HSE
performance- Statistics, Awards, Accolades
&Credentials
HSE Committee
formation
Listing of Activities
Preparation of
IER/IOHSR
Prioritization of
Risks/Hazards &
Phases of Project Life Cycle- Planning/Design-
HSE Plan
Listing control for all the significant
procedures
hazards/risks & aspects/Impacts- Procedures are
provided by corporate HSE
Social issues
Step-7 Finishing
Step-3 Shuttering
Step-2 Plotting
Step-8 Tilting
Risk ( N*L*S)- is
reduced in precast
work Step-9 Storage Step-1 Cleaning
- Labour license
• CTO/CTE-Batching plant
Soil Types :-
1) Stable rock :-
It is natural mineral matter. It is solid. Identified as Granite or Sand.
5) Layered
Combination of the above
Excavation Hazards
Excavation
• Drivers/Operators Competency
• Rest shelters – (resting below vehicles?)
• Handling/Storage of HSD
• Illumination
• Emergency Action
• Regular inspection
• Loose material on the edges, cave-in
• Material stacking & disposal of soil
• Work at nights
• Work in Monsoon
• Loading & Unloading of tippers
Soil Collapse - Fatality
WORK
LOCATION
Construction Vehicles
& Equipments
evolved much
but…………
Operator's Mind?????
Construction Vehicles & Equipments
Operator/Driver can
not see Grey area
Reinforcement Works
• Method of concrete
• Positioning of pump
• Ground condition
• Operator Competency
• Overhead power lines/obstructions if any
• Signaler
• PPEs
• Ball passing
• Electrical cable layouts, lighting masts, DBs, ELCBs
• Electrical Vibrators/compactors
• Electrical Safety
• PPEs
Column/Slab Casting
• Selection of Formwork
• Area for storage
• Carpentry workshop location
• Nailing & de nailing
• Lifting/shifting of formwork/shuttering materials
• Fixing of formwork/shuttering
• Mechanical lifting – Lifting tools Tackles/Equipments
safety
• Supporting arrangements – ground conditions,
bracings
• Access to deck
Column/Slab Casting
• Area Cordoning
• PPEs
• De-nailing
• Material Stacking
• Floor cleaning – waste collection/disposal
• Use of Crane? – Lifting tools/Tackles/Equipments Safety
• Operator/Signaler/Slinger competency
• Area cleaning, collection/disposal of waste
• Stacking of de shuttered materials
• Access ways
Work at height
• Fall prevention
• Fall protection
• Overhead protection around the building & entrance
• Tower crane /Material/Passenger Hoist installation
• Anchors, earthing, structural braces
• Rigging plan, team competecny
• Safe slinging
Free Fall
Guardrail constructed of
steel pipe (Handrail, Mid rail
& Toe guard provided
Fall Protection
Fall Protection
Safe stopping of a person already falling. To do so Personal
Fall Protection System to be used.
Anchoring
Lanyard 2m
Length
Total fall distance
Height of
Worker 1.8m
Height of 1.8m
Safety Worker
1m
Factor Safety 1m
Factor
Total = 4.8m
Total =
6.35m
Anchoring point should be above the head for minimizing fall distance
Life- Line
A component consisting of a flexible line for connection to an anchorage at one
end to hang vertically (vertical lifeline), or for connection to anchorages at both
ends to stretch horizontally (horizontal lifeline), and which serves as a means
for connecting other components of a personal fall arrest system to the
anchorage.
d
lin use
e
Li rab
th G
fe
w i pe
Ro
Horizontal Life Lines
General Rules for safety net
Hazard due to floor opening /hole can be safe guarded by providing covers
as shown above
Floor Opening
3:31:14 PM
Scaffold
Scaffold
Electrical Layout
Regular ELCBs, Earth Resistance Testing
Electrical Panel boards, DBs, Matt, Danger stickers, Gloves
Workshop/Plant/Machinery Layout
Lathe, grinder & other machine guarding
Plants – Lock out Tag out
Waste Oil/Filters/batteries management
Waste water management
Schedule of preventive maintenance of Equipments/cranes
Drivers/Operators/Electricians Competency, Medical
Electrical Safety
Terminology
• Current – the movement of electrical charge
• Resistance – opposition to current flow
• Voltage – a measure of electrical force
• Conductors – substances, such as
electricity
• Insulators – substances, such as wood, rubber,
glass, and Bakelite, that have high resistance
to electricity
• Grounding – a conductive connection to the earth
which acts as a protective measure
Electrical Shock
I = V/R
= 230 / 100000 A (Dry
Condition)
= 0.0023 A
= 2.3 mA
= 230 / 5000 (Wet Condition)
= 0.046 A
= 46 mA
Hazards of Electricity
Practice of makeshift DB with no weather Practice of safe DB under shed with 3 pin
protection, inserting bare wires in to fuses for sockets and plugs under use with ELCB
connections. No ELCB
• Protective shed & double visible Body earthling for each DB & equipment
• Provide & Maintain Earth pit & Earth resistance checking monthly
• For portable power tools power supply should be taken through
ELCB - 30 mA sensitivity for 30 milliseconds
• Test the ELCB regularly and record it.
• Use HRC fuse
• Avoid Loose connection of cables & insulate joints appropriately
• Use male female sockets
• Ensure Fire Extinguisher of correct type for Electrical panel rooms
• Inspect portable power tools
• Use double insulated power tools
• Cables shall be either underground or overhead
Machine Guarding
• Rigging plan
• Crane condition
• Lifting tools tackles SWL
• TPI certificate
• Operator, slinger, signaler competency
• Illumination
• Safe distance
• Wheel chocks
• Travel road condition
• Guy ropes
• Cordon off
• Tandem Lifting
• PPEs
Lifting Tools/Tackles
• Tyre/crawler/outrigger condition
• Cordon off - suspended load
• The operator should not use
• (i) a limiter as means of stopping a motion &
• (ii) a working load limiter as normal means to
determine that load can be lifted
• No Dragging load
• Wind speed
• Overlapping tower cranes
• Stopper for rail mounted cranes
• Alarm for rail mounted crane for movement
Tower Crane over lapping & Gantry Crane collision
Lifting Tools/Tackles
DISTANCE
At 45 degrees, H = L
As the angle becomes less than 45
degrees,
H will be less than L
Therefore ensure that H is always = or > L
Passenger/Material Hoist
•Location
•Overhead protection – loading point Barricades, gate at
floor levels Communication system, door limit switche
Third party certification
•SWL marking Fire
extinguisher
•Material loading platforms stability Entrance
platform guarding to Hoist
Mechanical, Electrical & Plumbing- (Servicing
Work)
5S Housekeeping - Fundamentals
Seiri Sort
Remove unnecessary items as appropriate
Seiton Set
Prefix a place for everything and put everything in place
Seiso Shine
Cleaning not for beautification alone but with a sense of
purpose
Seiketsu Standardize
Develop standards/evaluation criteria.
Shitsuke Sustain
Create awareness of all 4Ss and train to implement
Housekeeping
Material Stacking
Project Safety Initiatives
Induction Training
Tool Box Talks
Work Permits
HSE Lecture
HSE Walk
Speak & spread
Sport
Safety
Trainings/Mock
drills/Fire
demos
Safety Motivation - Safety Award/safety week
celebration Stop Work/Safety Warnings/penalties
Demobilisation and Project Completion
Major Activities during part/ final demobilization
• Demolition Works
• Dismantling of Heavy Plants and Equipment's
• Dismantling of temporary structures (Site offices, Stores,
hutments, workshops etc.)
• Loading / Shifting of surplus materials to other sites in
Trucks/ Trailers.
• Lifting and Shifting by Manual or Mechanical means.
• Segregation of reusable PPE’s and Safety Materials.
• Disposal of Hazardous Waste.
• Preserving Important HSE documents at RO / HO.
• Obtaining Project Completion Certificate from Client.
Safety in Demolition Works
• Involves many hazards associated with
construction
• Behavior of material different under
dynamic
loads of demolition
• Adequate preparation required for execution of
demolition task with regard to the health and
safety of the workers.
• Preparatory operations involve –
Overall planning of the demolition job
Methods to be used to bring the structure
down
Equipment necessary to do the job
Measures to be taken to perform the work
Safety in Demolition Works
Method Statement for Demolition
• Structural calculations as necessary
• Pre-weakening procedures
• Procedures for falling structures and/or lifting
of structural members
• Methods of cutting steelwork and removal of
debris
• Protection to be provided for operatives,
third parties, adjacent buildings, etc.
• Special procedures for dealing with asbestos,
lead, chemicals, storage tanks and any other
specialized structure or identified material
Dismantling of Heavy Plants and Equipment's
Safety Concern
• Equipment operated by Unskilled / Untrained /
Unauthorized operator
• Engaging Hire Equipment for short job,
• Use of untested / Scrap lifting tools and tackles
• Insufficient resources
• Lack of planning & Supervision
• Incorrect sitting or setup of Crane.
• Fail to calculate or estimate correct load.
• Failure to carryout the correct procedure
• Careless or Complacent.
• Faulty devices or machines
• Lack of proper maintenance
Dismantling temporary structures
Safety Concern
• Temporary works considered as low risk work
and executed by junior staff.
• Due to unavailability of required equipment for
dismantling, demolition is done manually by
hammer, chisel etc.
• No methodology is prepared for dismantling
work.
• Activity not considered under HIRA.
• Unsafe / unstable platforms are used for
dismantling.
• Non use of PPE
Shifting of Materials
Temporary shifting of heavy
material
• Assuming the short distance materials are not
secured properly.
• Over head utilities not inspected on road.
• Operator Overconfidence
• Non availability of proper transport vehicle.
• Improper use of lifting equipment.
Shifting of Materials
Shifting of material manually
• Multitasking work carried out from workers.
• Lack of coordination.
• Not following kinetic method of lifting.
• Untrained / Unskilled workforce for temporary
shifting work.
• Lifting movements are not coordinated
• Non use of required PPE.
• Lack of Supervision
• Materials not separated out before being
lifted
• Lack of concentration while lifting
• Poor housekeeping and stacking of materials
Segregation of reusable PPE’s and Safety Materials
After completion of Project, site should segregate given
below reusable materials
• Requisite PPE like Helmets, Hand gloves, Goggles, Safety
Shoes, Full Body Harness etc.
• Safety Nets
• Sign Boards
• First Aid Box
• Safety Park
• Fire extinguishers
• Flashback arrestors
• Trolley for gas cylinders
• Earth Leakage Circuit Breakers (ELCB),
Type of Waste & Disposal
Common Hazardous Waste
• Used Oil
• Oil & Grease soaked cotton
• Contaminated drums, cans, other containers
• Battery
• Cement Bags
Bio Medical Waste
Cottons, Bandages, Expiry medicine, dressing
materials, syringe etc.
E- Waste
• Electrical wire, plug, bulb
• Electronic chip
• Switchboard, Panel board
• Computer accessories
General HSE Concerns
• Multitasking work
• Non availability of Safety Staff at Projects near completion
• Lack of Planning
• Lack of Supervision
• Lack of Coordination
• Leaving the job on Subcontractor.
• Limited resources
• Low budget at the end
• Use of unmaintained plant (Temporary hired Plant)
• Low priority for safety
• Poor welfare measures
• Poor Housekeeping
• Low awareness (Lack of trainings)
Project Completion Requirements
The HSE documents are really the manifestation of the
process in that it becomes the repository of all the relevant
documentation.
Any documents pertaining to legal implications has to
be preserved. Eg. Consents, fatality reports etc.
Awards details