34 ENGR CONSTR BDE

1
RE-EXCAVATION, EXPANSION, RENOVATION
AND DEV OF KHALS FOR MITIGATING WATER
LOGGING PROBLEM IN CHATTOGRAM CITY
AIM

TO APPRAISE YOU ABOUT THE VARIOUS ASPECT OF THE PROJ


SEQ

PROJ INFO
CURRENT PROJ PROGRESS
WK PLAN
FINANCIAL STATE
CHALLENGES
PROJ INFO
PROJ INFO
SPONSORING MINISTRY MINISTRY OF HOUSING AND PUBLIC WORKS

SOURCE OF FUND GOB

PROJECT AREA 103.596 KM


(CTG CITY AREA 160 SQ KM)

DURATION (DPP) 01 JULY 2017 TO 30 JUN 2020

DPP COST DPP : 5616.499 CR


CDA: 1773.2996 CR FOR LAND ACQUISITION &
OTHERS
MOU : 3843.1994 CR ( BD ARMY)
RECEIVED TK 1372.38 CR

PHYSICAL PROGRESS 48.70% (LAST PIC 31.15%)

FINANCIAL PROGRESS 38.31% (LAST PIC 35.40%)


6
PROJ INFO
• CONSTR OF 176 KM RCC RETAINING WALL
• CONSTR OF 85 68 KM KHAL SIDE RD
• CONSTR OF 54 X BR/CULVERT

• CONSTR OF 5 X REG
• CONSTR OF 3 X FLOOD WATER STORAGE POND

• CONSTR OF 42 x NEW SILT TRAP

• CONSTR OF 10.77 KM NEW DRAIN

• EXPANSION OF 15.50 KM RD SIDE DRAIN

• CONSTR OF 200 X CROSS DRAIN CULVERT


7
CURRENT PROJ PROGRESS
CURRENT PROJ PROGRESS( R/W)
TOTAL NO LENGTH OF COMPLETED COMPLETED PROGRESS PROGRESS REMARKS
OF KHAL R/W UPTO LAST IN LAST PIC
PIC

36 176 KM 33 KM 19.921 KM 18.75% 11.20 %

NO OF WILL BE LEFT FOR NEXT YR REMARKS


KHAL COMPLETED
BY JUN 2021

36 16 20 2 X KHAL CAN
NOT BE STARTED
WITHOUT LAND
AQUISITION
WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH OF R/W COMPLETED THIS YR UPTO LAST
PIC

TEKPARA .570 KM 780 M 490 M 290 M 62.82 % 34.61 % WILL BE


COMPLETED BY
JAN 2021

FIRINGIBAZAR .530 KM 1060 M 60 M 1060 M 5.66 % - WILL BE


COMPLETED BY
MAY 2021

SADARGHAT-1 .525 KM 750 M 120 M 630 M 16 % 08,00% WILL BE


M COMPLETED BY
MAR 2021

SADARGHAT-2 .424 KM 848 M 330 M 518 M 38.91 % 17.69 % WILL BE


COMPLETED BY
FEB 2021

MOGOLTULI 1,10 KM 2200 M 22 M 1000 M 1% - ONGOING


WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH OF R/W COMPLETED THIS YR UPTO LAST
PIC

RAJAKHALI -1 2.70 KM 5400 M 3600 M 1800 M 66.67 % 28.33 % WILL BE


COMPLETED
BY MAR 2021

RAJAKHALI-2 1.365 KM 2730 2550 M 180 M 93.40 % 75.82 % WILL BE


MM COMPLETED
BY JAN 2021

RAJAKHALI-3 1.580 KM 3160 M 1150 M 2010 M 36.39 % 21.83 % WILL BE


COMPLETED
BY MAY 2021

BAKOLIA 2.10 KM 4200 M 60 M 500 M 1.43 % - ONGOING

CHAKTAI 2.70 KM 4775 M - 1000 M - - MOB


DIVERSION ONGOING
WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH OF R/W COMPLETED THIS YR UPTO LAST
PIC

MOHESH 6.697 7952 M 1435 M 1448 M 18.32 % 11.60 % ONGOING


KHAL KM

RAMPUR 2.95 KM 4350 M 282 M 698 M 6.48 M % 3.47 % ONGOING

AZOBBAHAR 1.06 KM 1120 40 M 1080 M 12,5 % % 3.50 % WILL BE


COMPLETED
BY MAY
2021
NASIR 1.774 M 2059 M 340 M 989 M 16.51 % 13.11 % WILL BE
COMPLETED
BY JUN 2021

GOINACHARA- 3.30 KM 6600 M 600 M 1400 M 9.10 % 6.45 % ONGOING


1
WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH OF R/W COMPLETED THIS YR UPTO LAST
PIC

GOINACHARA-2 0.70 KM 1350 M 910 M 440M 67.40 % 42.22 % WILL BE


COMPLETED BY
FEB 2021

NOA KHAL 5.79 KM 11580 M 90 M 3200 M 1.00 % - ONGOING

BAMUNSHAI 4.85 KM 9000 M 2800 M 5400 M 31.10 % 24.88 % ONGOING

SHITOLJHORNA 6.73 KM 12870 M 780 M 6000 M 6.10 % 2.33 % ONGOING

UTTARA 1.30 KM 2700 M 630 M 2070 M 23.33 % 20.76 % WILL BE


COMPLETED BY
JUN 2021
WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH OF R/W COMPLETED THIS YR UPTO
LASST PIC

MIRZA 2.78 KM 5560 300 M 500M 5.40 % 5.40 % ONGOING


,NEEDS L/A

TRIPURA 2.64 KM 3545 M 1866 M 2414 M 52.63 % 40.90 % ONGOING

NAYARHAT 0.458 916 M 102 M 764 M 11.13 %% 5.60 % WILL BE


KM COMPLETED BY
MAY 2021

GUPTA 2.2 KM 3475 M 1604 M 1871 M 46.15 % 20.14 % WILL BE


COMPLETED BY
FEB 2021

RUBY 0.60 KM 900M 113 M 847 M 12.55 % 5.90 % WILL BE


CEMENT COMPLETED BY
JUN 2021
WK PLAN AND PROGRESS (R/W)
TOTAL LENGTH SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
KHAL NAME LENGTH OF R/W COMPLETED THIS YR UPTO LAST
PIC

CHAKTAI 5.845 KM 5825 M 90 M 1500 M 1.54 % 0.34 % ONGOING,NEED


S L/A

KALABAGICHA 0.336 KM 508 M 360 M 148 M 70.86 % 59 05 % WILL BE


COMPLETED BY
MAR 2021

MORIOMBIBI 0.944 KM 1400 M 800 M 600 M 57.14 % 42.14 % WILL BE


COMPLETED BY
MAR 2021

ZAMALKHAN - - - - - - NEEDS L/A

BADORKHALI - - - - - - NEEDS L/A


WK PLAN AND PROGRESS (R/W)
KHAL NAME TOTAL LENGTH OF SO FAR PLAN FOR PROGRESS PROGRESS REMARKS
LENGTH R/W COMPLETED THIS YR UPTO LAST
PIC

HIJRA 2.475 KM 4000 M - 300 M - - ONGOING


,NEEDS L/A

DOMKHALI 5.24 KM 8300 M 2370 M 2000 M 28.55 % 15.55 % ONGOING

MOHESH 3.264 KM 3264 M 120 M 2000 M 3.67 % 1.84 % ONGOING


KHALI

BIRZA 2.542 KM 2030 M 460 M 1570 22.67 % 8.57 % WILL BE


COMPLETED
BY JUN 2021
BR/CULVERTS
NO OF DESIGN C0MPLETED COMPLETED WK ONGOING
BR/CULVERT TO RECEIVED UPTO LAST
BE CONSTRUCTED PIC

48 X BR ALL 18 X BR 23 X BR 05 X BR
6 X CULVERT 12 X CULVERT 19 X CULVERT 07 X CULVERT

47x BR DESIGN IS
44 X CULVERT LEFT FOR
38 X CULVERT ADDITIONAL
WILL BE INCL IN BR AND
RDPP CULVERTS
CONSTR OF BR
NAME OF KHAL BR/CULVERT PRESENT STATE

SHAMSAR PARA-1 COMPLETED

MIRZA KHAL KALARPOOL-1 NEXT DRY SEASON

HADU MAJI PARA COMPLETED


MOHAMMADPUR COMPLETED

GAYANACHHARA RAILWAY POLICE LINE COMPLETED


KHAL-2
GAYANACHHARA FOILATOLI BAZAR 1 COMPLETED
KHAL-1
FOILATOLI BAZAR 2 COMPLETED
DOMKHALI KHAL CHANDER BARI ONGOING
PATHANIA GODA COMPLETED
SAHID PARA SANGJASTHOL COMPLETED
BAS TARMINAL-1 COMPLETED
BAS TARMINAL-2 COMPLETED
CONSTR OF BR
NAME OF KHAL BR/CULVERT PRESENT STATE

DOMKHALI KHAL BAS TARMINAL-3 COMPLETED


BAS TARMINAL-4 ONGOING

HIZRA KHAL PROBORTOK CIRCLE COMPLETED


MAHESHKHALI KHAL COMMISSIONER POOL COMPLETED
LONGAPARA ONGOING
KALIMONDIR COMPLETED
RUPALI R/A COMPLETED
SOSHANGHAT COMPLETED
SHITOL JHARNA AND LOHAR POOL ONGOING
BAMUNSHAI KHAL HAJIR POOL NEXT DRY SEASON
ANONNA ABASIK COMPLETED
RLY BR WILL BE IMPLEMENT BY BD
RLY
DURRAPUR MAJAR GATE NEXT YR
KHODOKIA KHAL CHINARPOOL COMPLETED
PURBO MHORA CULVERT COMPLETED
CHAKORIA PARA COMPLETED
NATUNPARA COMPLETED
CONSTR OF BR
NAME OF KHAL BR/CULVERT PRESENT STATE

BAKOLIA OMAR ALI MATBOR RD TO BE DONE AFTER DPP


FIRINGIBAZAR A B DAS LANE TO BE DONE AFTER DPP

MORIOM BIBI PATHORGHATA BAYS HIGH SCHOOL TO BE DONE AFTER DPP

MOGOLTULI NEAR CCC GARBAGE SHADE TO BE DONE AFTER DPP

TEKPARA JALILGONJ PATHORGHATA TO BE DONE AFTER DPP

CHAKTAI DIDERSION BORO MIA MOSQUE TO BE DONE AFTER DPP

NEAR SAYED SHAH RD TO BE DONE AFTER DPP

LOHARPOOL SARAIPARA TO BE DONE AFTER DPP

GOINACHARA KHAL OPPOSITE TO PAHARTOLI THANA TO BE DONE AFTER DPP

MOUSUMI R/A TO BE DONE AFTER DPP

X
CONSTR OF BR
NAME OF KHAL BR/CULVERT PRESENT STATE

MOHESH KHAL PURBO SHUNDUBI PARA COMPLETED

ARTY STEEL BR COMPLETED

BGB GATE NEXT DRY SEASON

TULATOLI KHAL TULATOLI BR ONGOING

MAYORGOLI MOGOLTOLI -1 ONGOING

MOGOLTOLI -2 NEXT DRY SEASON

TRIPURA KHAL RAIL BR -1 BD RLY DEPT WILL


IMPLEMENT
RAIL BR -2 BD RLY DEPT WILL
IMPLEMENT
TOTAL NO OF BR TO 47 X BR
BE CONSTR
CONSTR OF CULVERTS
NAME OF KHAL BR/CULVERT PRESENT STATE

AIR BASE -1 COMPLETED

MIRZA KHAL AND AIR BASE -2 WILL BE STARTED SOON


GUPTA KHAL AIR BASE -3 WILL BE STARTED SOON

AIR BASE -4 ONGOING

AIR BASE -5 COMPLETED


NAYARHAT KHAL CULVERT -1 ONGOING
CULVERT -2 WILL BE STARTED SOON
HIJRA KHAL NEAR SONALI BANK ONGOING
NEAR SONALI BANK NEXT YR
MORIOMBIBI KHAL PATHORGHATA COMPLETED
RAMPUR KHAL EIDGAH MUNSIPARA COMPLETED
TRIPURA KHAL AMIN JUTE MILL GATE
AMIN JUTE MILL BEHIND ONGOING
UTTARA KHAL DHALIAPARA TURNING
DOMKALI KHAL WASA GATE COMPLETED
CONSTR OF CULVERTS
NAME OF KHAL BR/CULVERT PRESENT STATE

MAJAR GATE

CHOSMA KHAL RLY STA COMPLETED

LGED

EDU BOARD

FOREST GATE ONGOING


RSRM
MURADPUR
N MOHAMMADPUR
BAMUNSHAI KHAL SHAHIDULLAPARA ONGOING
BANIARPOOL COMPLETED
TOTAL NO OF CULVERT 25 X CULVERT
OVER KHALS
CONSTR OF CULVERTS
NAME OF CULVERT PRESENT STATE
KHAL/AREA

NASIRABAD NASIRABAD -102 COMPLETED


NASIRABAD -103 COMPLETED

NASIRABAD -126 COMPLETED

TEKBAZAR TEKBAZAR -127 COMPLETED


SHOLOKBAHAR SHOLOKBAHAR -121 COMPLETED
SHOLOKBAHOR -132 COMPLETED

SHOLOKBAHAR - 138 COMPLETED

KAPASGOLA KAPASGOLA -141 COMPLETED

KAPASGOLA -145

NEVAL ACADEMY NAVAL ACADEMY -160 COMPLETED

CHANDGAON CHANDGAON - 146 COMPLETED


OXYGEN OXYGEN MOR -154 ONGOING
CONSTR OF CULVERTS
NAME OF KHAL/AREA CULVERT PRESENT STATE

NORTH HALISHAHAR NORTH HALISHAHAR -161


NORTH HALISHAHAR -162

NORTH HALISHAHAR -163

NORTH HALISHAHAR -164

BOGAR BILL BOGAR BILL - 171 COMPLETED

SHAMOLI H/S GATE SHAMOLI H/S GATE-173

JAMIA MADRASA JAMIA MADRASA-174

TOTAL NO OF 19 X CULVERT
CULVERT OVER
DRAIN
CULVERTS/ BRS
CULVERTS/BRS
CULVERTS/ BRS
CULVERTS/ BRS
CULVERTS/ BRS
PROGRESS OF REGULATORS (05)
SER NAME OF REGULATOR WK ONGOING
NO

1 MOHESHKHAL REGULATOR ( 12 VENT) CASTING OF WALL IS ONGOING

2 TEKPARA REGULATOR (2 VENT) CASTING OF WALL ONOING

3 KALABAGICHA REGULATOR (2 VENT) WALL CASTING IS GOING ON

4 MORIOMBIBI REGULATOR (2 VENT) STRUCTURAL PART COMPLETED

5 FIRINGI BAZAR REGULATOR (2 VENT) WALL CASTING ONGOING


CONSTR OF REGULATOR
PRESENT PROGRESS PROGRESS IN LAST PIC

TEKPARA REGULATOR TEKPARA REGULATOR


CONSTR OF REGULATOR
PRESENT PROGRESS PROGRESS IN LAST PIC

FIRINGIBAZAR REGULATOR FIRINGIBAZAR REGULATOR


CONSTR OF REGULATOR
PRESENT PROGRESS

MOHESH REGULATOR MOHESH REGULATOR


CONSTR OF REGULATOR
PROGRESS IN LAST PIC

MOHESH REGULATOR MOHESH REGULATOR


CONSTR OF REGULATOR
PRESENT PROGRESS PROGRESS IN LAST PIC

KALABAGICHA REGULATOR KALABAGICHA REGULATOR


CONSTR OF REGULATOR
PRESENT PROGRESS PROGRESS IN LAST PIC

MORIOMBIBI REGULATOR MORIOMBIBI REGULATOR


PROGRESS OF SILT TRAP (42)
SER NAME OF SILTRAP WK ON GOING
NO

1 GOINACHARA KHAL -2 ONGOING

2 TIGERPASS -1 ONGOING

3 SHITOLJHORNA ( INFRONT OF ONGOING


DOHS )

4 TULATOLI SILT TRAP-1 ONGOING

5 AZOB BAHAR KHAL ONGOING


PROGRESS OF SILT TRAP (42)
SER NAME OF SILTRAP WK ON GOING
NO
6 KHONDOKIA KHAL-1 ( INSIDE WILL BE STARTED
CANTT ) SOON

7 KHONDOKIA KHAL -2 ( Katakhali ) L/A IN PROCESS

8 KHONDOKIA KHAL -3 L/A IN PROCESS

9 CHOSMA KHAL L/A IN PROCESS

10 MIRZA KHAL-1 L/A IN PROCESS


PROGRESS OF SILT TRAP (42)
SER NAME OF SILTRAP WK ON GOING
NO

11 MIRZA KHAL -2 ( BESIDE N L/A IN PROCESS


MOHAMMAD )

12 MIRZA ( INFRONT OF L/A IN PROCESS


LORDS INN)

13 TULATOLI -2 L/A IN PROCESS

14 HIJRA KHAL UPSTREAM L/A IN PROCESS

15 MOZAFFOR NAGOR L/A IN PROCESS


PROGRESS OF SILT TRAP (42)
SER NAME OF SILTRAP WK ON GOING
NO
16 RAMPUR KHAL ( KARNAFULY L/A IN PROCESS
R/S)

17 GOINACHARA -1 L/A IN PROCESS

18 TRIPURA KHAL ( NEAR AMIN ONGOING


JUTE MILL )

19 DOMKHALI KHAL L/A IN PROCESS

20 AL FALAH GOLI L/A IN PROCESS


PROGRESS OF SILT TRAP (42)
SER NAME OF SILT TRAP WK ON GOING
NO
21 PAHARTOLI ALI AZAM RD L/A IN PROCESS

22 MOGOLTULI ( NEAR RLY LINE) WK IN PROGRESS

23 CHOSMA KHAL ( 2 NO GATE MOR) L/A IN PROCESS

24 BAMUNSHAI KHAL ( NEAR KOLOR L/A IN PROCESS


POLE )
25 PAKIJA KHAL ( MOHURIPARA) L/A IN PROCESS

26 BODORKHALI KHAL L/A IN PROCESS

27 CHAKTAI DIVERSION L/A IN PROCESS


PROGRESS OF DRAIN CONSTR
SER DRAIN NO OF T0TAL PRESENT PROGRESS
DRAIN LENGTH PROGRESS UPTO LAST
PIC

CONSTR OF 524 NOS 52.88 KM 95 % WK IS 75 % WK IS


1.
DRAIN FOR 22 COMPLETED COMPLETED
PTS

2. CONSTR OF RD - 15.50 KM COMPLETED. COMPLETED


SIDE DRAIN HANDING OVER
TO CDA IS IN
PROCESS

3. CONSTR OF - 10.77 KM ON GOING. WILL ON GOING


NEW DRAIN BE HANDED OVER
TO CDA BY FEB
2020
CONSTR OF SIDE DRAIN
CONSTR OF RCC DRAIN
CONSTR OF RCC DRAIN
CONSTR OF TEMPORARY CAMP
CONSTR OF TEMPORARY CAMP
CONSTR OF TEMPORARY CAMP
FINANCIAL STATE

 DPP Amount : 3843.19 CR


 Received Upto Jun 2020 : 1472.38 Cr
 Physical Progress : 47.48 (last PIC 46.72%)
 Financial Progress : 38.30% (last PIC 35.70%)
 ADP Allot for FY 2020-2021: 709.80 Cr ( Revised Allot
532.00 Cr )
FINANCIAL STATE

 RECEIVED UPTO JUN 2020 : 1472.38 CR


 CF FUND : 115.44 CR
 FDR : 108 CR
 PROJ FUND : 09.67 CR
MAJ CHALLENGES

 INSUFFICIANT MANPOWER AND EQUIPMENT AVAL IN WK


SITE
 DELAY OF LAND AQUISITION
 LACK OF PUBLIC AWARENESS HINDERING SUSTAINABILITY
IN COMPLETION OF THE PROJ
 PROCEDURAL DELAY IN SHIFTING UT LINES BY DIFFERENT
AGENCIES
DECISION PTS

 HANDING OVER OF 15.50 KM RD SIDE DRAIN TO CDA


 HANDING OVER OF 10.77 KM NEW RD TO CDA
 CAPACITY BLDG VISIT TO NETHERLAND BY APR 2021
 PIC WILL BE ARRANGED BY 1ST WEEK OF JAN 2021
 PSC WILL BE ARRANGED BY JAN 2021
 RDPP TO BE SENT BY FEB 2021
DECISION FROM PSC

 RDPP TO BE SENT BY FEB 2021


 CAPACITY BLDG VISIT TO NETHERLAND BY APR 2021
Thank You