SMSS 28 NO.
TBSS 34 NO.
COMMISSIONED:
TRANSMISSION LINES 138.60 KM
SMSS 05 NO.
TBSS 01 NO.
CAPITALIZATION (2019 – 20)
CAPITALIZATION
DESCRIPTION JULY 2019 – DEC. 2019 EXPECTED JANUARY 2020
– JUNE 2020
MILLION RUPEES MILLION RUPEES
TRANSMISSION LINES / 425 2,800
SMSS
DISTRIBUTION LINES 1,686 2,137
TOTAL 2,111 4,937
8 61.188 6 241,619
6 79.77 8 137,042
4 25.826 10 45,539
12 300
2 23.160
16 5,500
1 43.938
Total 430.00
Total 285.130
Capitalization = PKR 1,686 Million Capitalization = Approx. PKR 2,137 Millions
Note:
Expected Capitalization is based on unit construction cost of FY 2018-2019 and 70 % budget utilization.
Transmission Line & SMS Capitalization
(1st July – 31st Dec 2019)
Description Date of Commissioning Actual Capitalization up to
Dec – 19
PKR Millions
8” Ø x 11.5 KM Adhi – Sukho Transmission Line 13.09.2019 297,580,120
24” Ø x 93 KM Punjab Power Plant Line 21.09.2019
SMS Cherat Cement Factory (30 MMCFD) 14.12.2019 85,494,476
SMS Bara Kahu (10 MMCFD) 30.11.2019 14,134,212
SMS cum CMS Punjab Power Plant 16.10.2019
SMS Rojhan (5 MMCFD) 03.10.2019 28,516,136
Total Capitalization Rs. 425,724,944
3. Daud Khel (Rep. Station F3) to Mianwali 10 50.70 99.39% ROW = 50.70 Km
Line Welding = 50.70 Km
Lowering = 49.77 Km
Construction work is in progress.
Testing of 47.2 km has been completed
6. Transmission Line for SMS Margalla, Isd. 8 0.40 100% Line has mechanically been completed and under
testing.
INFRASTRUCTURE DEVELOPMENT 24"Ø LINE
TOTAL LENGTH: 145.65 KM
SR. TITLE DIA. LENGT PROGRE REMARKS
# (Inch) H SS
(Kms) (% age)
1. Kohat to Dakhni Line 24 54.30 78.74% ROW = 54.308 Km (Completed)
[remaining portion out of 54.30 Km, from Welding = 38.055 Km
Guruzai V/A to Khushal Garh V/A]. Lowering = 35.902 Km
Construction work resumed on 14.02.2020 and is in
progress.
3. Dhullian (FC-1) - Gali Jagir Line 24 40.15 100% Completed and commissioned.
TRANSMISSION LINES - UPLIFTING
SR. # TITLE DIA. LENGT PROGRESS REMARKS
(Inch) H (% age)
(Kms)
Detail
DETAIL SMSS & SMSS/CMSS IN PROGRESS
SR. NAME OF SMS COMMENTS
1. Jabba Khattak, Nowshera Ready for Commissioning.
5. Mandi Yazman Fabrication (98%) and installation (98%) and civil work (10%)
completed.
6. Mianwali Fabrication (90%) and installation (90%) completed. Work is in progress.
22. General Industries Sheikhupura Work stopped due to land problem. Installation is in progress.
Flooring and paint work in progress. Angle iron and Chain Link
Fencing material awaited from Head Office.
Total Km :- 104.50
Contract Lines
3. 18/60/000986 Mardan Khel-3 to Mardan Khel-1, Flow Line 8 7.50 04-Jul-19
4. 20/60/000501 Makori Deep-2, Flow Line 6 1.20 16-Nov-19
5. 19/60/000992 Gas Feeder Lines for Pak Arab Fertilizer Ltd 16 24.00 30-Nov-19
6. 19/60/000992 Gas Feeder Lines for Pak Arab Fertilizer Ltd 12 1.40 07-Feb-20
Total Km :- 34.10
DETAIL SMSS & SMSS/CMSS - COMMISSIONED FY
SR. 2019-20
NAME OF SMS COMMENTS
4. Rojhan 16-Oct-19