Introduction

Select a new project which as National Conference.

Our organization "EVENT MANAGEMENT" took over this


event.

Constructed at Dhaka College.

Follow the process of Critical Path Method (CPM) 


List Of Activities And Data Table
Activity Indicating Letter Activity Immediate Predecessor Estimated Normal Time
  (days)

Select a conference date A A - 1


   

Confirm lead speaker and topic B B - 5


   

Prepare brochure C C - 2
     

Send letters to other speakers D D A, C 2


     

Get confirmation from speakers E E D 5


   

Send letters to participants F F D, E 2


   

Obtain travel plans from speaker G G E 2


   

Arrange for accommodation for speakers H H G 1


 

Get Handout from speakers I I G 4


   

Finalize registrations J J H, I 10
   

Arrange Hall K K J 1
   

Conduct of programmed L L K 1
   
Precedence Diagram And Network Diagram
Using CPM Method

Figure 01 : Precedence Diagram

Figure 01 : Precedence Diagram Figure 02 : Network Precedence Diagram


Possible Path ,Slack Time And Gantt Chart
POSSIBLE PATHS SLACK TIME
A-D-F = 5 A=1 G=0
A-D-E-F= 10 B=22 H=0
A-D-E-G-H-J-K-L= 23 C=0 I=0
A-D-E-G-I-J-K-L= 26 D=0 J=0
B=5 E=0 K=0
C-D-F=5 F=16 L=0
C-D-E-F= 10 EXPECTED TIME DURATION
C-D-E-G-H-J-K-L= 24 27 Day
C-D-E-G-I-J-K-L= 27
CRITICAL PATH
C-D-E-G-I-J-K-L
Project Exclusion
Personal Introspective
Speakers’ Quiz
Food & Drinks
Transportation
Talent Show
The Solution Room
Gamification