Professional Documents
Culture Documents
Lecture
Topics Today:
Control Costs
Control Costs is the process of monitoring the status of the project to update
the project costs and managing changes to the cost baseline. The key benefit
of this process is that the cost baseline is maintained throughout the project.
This process is performed throughout the project. The inputs, tools and
techniques, and outputs of this process are depicted in Figure 7-10,
Figure 7-11 depicts the data flow diagram of the process.
2
7.4 Control Costs
Inputs Tools & Outputs
Techniques
1. Project management plan 1. Work performance
● Cost management plan 1. Expert judgment information
● Cost baseline 2. Data analysis 2. Cost forecasts
● Performance 3. Change requests
● Earned value
measurement baseline 4. Project management
analysis
2. Project Documents updates
● Variance analysis
● lessons learned register ● Cost management plan
● Trend analysis
3. Project funding ● cost
baseline
● Reserve analysis
requirements
3. To-complete ● Performance measurement
4. Work performance data baseline
performance index
5. Organization process 5. Project documents updates
assets 4. Project
management ● Assumption log
● Cost estimates
● Lessons learned register
● Risk Register
Figure 7-10. Control costs: Input, Tools & Techniques, and Outputs 3
Project Management
Plan 7.4 Control Costs
Project management plan updates
● Cost management plan 4.5
● Cost baseline Monitor and Control
● Work performance
● Performance measurement Project Work
baseline information
4.6
Project Documents ● Change request Perform Integrated
Change Control
● Lessons learned register
7.4
7.3 Control Costs Project Management
Determine Budget Plan
Project management plan components include but are not limited to:
5
Control Costs : Inputs
7.4.1.2 Project Documents
Work performance data contains data on project status such as which costs
have been authorized, incurred, invoiced, and paid.
6
Control Costs : Inputs
7.4.1.5 Organizational Process Assets
The organizational process assets that can influence the Control Costs
process include but are not limited to:
7
Control Costs : Tools and Techniques
7.4.2.1 Expert Judgment
Examples of expert judgment during the Control Costs process include but
are not limited to:
Variance analysis,
Forecasting, and
Financial analysis.
8
Control Costs : Tools and Techniques
7.4.2.2 Data Analysis
Data analysis techniques that can be used to control costs include but are not
limited to:
Earned Value Analysis(EVA). Earned value analysis compares the
performance measurement baseline to the actual schedule and cost
performance. EVM integrates the scope baseline with the cost baseline
and schedule baseline to form the performance measurement baseline.
9
Control Costs : Tools and Techniques
11
How to Control Project Cost
15
Actual value of completed or in-process work
Performance Measurement Baseline
PV and BAC
EV
Chart
PV EV AC
AC PV
January 0 0 0
June 62000
July 70700
16
Schedule Variance
PV = $42, 000
EV = $ 38,000
AC= $ 48,000
SV = EV – PV
17
Cost Variance
PV = $42, 000
EV = $ 38,000
AC= $ 48,000
CV= EV – AC
18
Variances
CV Cost The amount of budget deficit or The difference between the CV=EV-AC Positive=Under planned cost
Variance surplus at given point in time, value of work completed to a Neutral=On planned cost
expressed as the difference point in time, usually the data Negative=Over planned cost
between the earned value and date, and the actual costs to
the actual cost. the same point in time.
SV Schedule The amount by which the The difference between the SV=EV-PV Positive=Ahead of Schedule
Variance project is ahead or behind the work completed to a point in Neutral=On schedule
planned delivery date, at a time, usually the data date, Negative=Behind Schedule
given point in time, expressed and the work planned to be
as the difference between the completed to the same point in
earned value and the planned time.
value.
Index
CPI Cost A measure of the A CPI of 1.0 means the project is exactly CPI=EV/AC Greater than 1.0=Under
Performance cost efficiency of on budget, that the work actually done so planned cost
Index budgeted resources far is exactly the same as the cost so far. Exactly 1.0=On planned cost
expressed as the Other values show the percentage of how Less than 1.0=Over planned
ratio of earned much costs are over or under the cost
value to actual cost. budgeted amount for work accomplished.
SPI Schedule A measure of An SPI of 1.0 means that the project is SPI=EV/PV Greater than 1.0=Ahead of
Performance schedule efficiency exactly on schedule, that the work schedule
Index expressed as the actually done so far is exactly the same Exactly 1.0=On schedule
ratio of earned value as the work planned to be done so far. Less than 1.0=Behind schedule
to planned value. Other values show the percentage of how
much costs are over or under the
budgeted amount for work planned.
19
PV = $42, 000
EV = $ 38,000
AC= $ 48,000
CPI= EV / AC
= $ 38,000 / $ 48,000 = $0.79
$0.79 worth of work was actually done for each $1.00 spent
20
Earned Value Calculations for One Activity After Week One
ACTIVITY WEEK 1
21
Project Management Question EVM Performance Measures
-How efficiently are we using our resources? -Cost Performance Index (CPI)
22
Practice Qs
Your organization has won a Govt. funded four week project. Details of Budget
approved are given below,
Week 1
Week 2
CV, SPI,
Week 4
Week 3
23
Practice Qs
Today is end of 3rd week and following work could be performed till date:
24
Thank You