To effectively prepare a fire protection plan for a storage occupancy, the following steps should be
followed:
Determine the commodity classification.
Identify the storage arrangement.
Determine the storage height and clearance from the top of storage to sprinklers.
Develop a protection scheme (automatic sprinkler system).
NFPA13,2019Ed YOUTUBE
FIRE TECH.
LEC-03
Design Sheet-1
NFPA13,2019Ed
YOUTUBE
Design Sheet-2
NFPA13,2019Ed
YOUTUBE
20.6.1 Ceiling Slope. The sprinkler system criteria specified in Chapters 20 through 25 are intended to apply
to buildings with ceiling slopes not exceeding 2 in 12 (16.7 percent) unless modified by a specific section in
Chapters 20 through 25.
WHY?
NFPA13,2019Ed
YOUTUBE
Flat Ceiling
NFPA13,2019Ed
YOUTUBE
Flat Ceiling
NFPA13,2019Ed
YOUTUBE