The monthly report from Bounty Farms summarizes progress made in March 2016 on installing layer houses three, four, and five at their San Pascual Farm location. House three installation was 100% complete, while house four installation was ongoing since February 10. House five was still in the flooring stage. The report provides percentage completion details for each part of the installation process for house three, such as the cage frame, wire partition, and drinker system all being 100% complete.
The monthly report from Bounty Farms summarizes progress made in March 2016 on installing layer houses three, four, and five at their San Pascual Farm location. House three installation was 100% complete, while house four installation was ongoing since February 10. House five was still in the flooring stage. The report provides percentage completion details for each part of the installation process for house three, such as the cage frame, wire partition, and drinker system all being 100% complete.
The monthly report from Bounty Farms summarizes progress made in March 2016 on installing layer houses three, four, and five at their San Pascual Farm location. House three installation was 100% complete, while house four installation was ongoing since February 10. House five was still in the flooring stage. The report provides percentage completion details for each part of the installation process for house three, such as the cage frame, wire partition, and drinker system all being 100% complete.
The following presentations/reports focus on the monthly installation development of Layer house three of San Pascual Farm located at Barangay San Pascual, Tarlac City in the month of February 3 to March 17, 2016. House three (100%). Date started, January 4, 2016 House four ( on going installation. Date started, February 10, 2016). House five (on flooring) Parts of Installation
Cage frame 100%
Cage wire partition 100%
Cage back wall 100%
Drinker system 100%
Manure Belt Support 100%
Cable Rod attachment 100%
Cage Floor 100%
Chest Protection 100%
Manure Belt attachment 100%
Manure belt stitching 25%
Trap door attachment 100%
Feeding Trough 95%
Guide Rail Down 97%
Cross manure installation 60%
Picture Presentation House three House four THANK YOU