Professional Documents
Culture Documents
Structure presentation on
SPILLWAY CONSTRUCTION
By Eyasu Tafese
GSR111/12
Presentation outline
• Introduction
• Spillway construction program
• Construction flood
• Reservoir levels during construction stages
• Spillway construction stages
• Discharge characteristics of partly constructed spillways
• Flow downstream of partly constructed spillways
Introduction
• The spillway is a hydraulic structure intended to discharge the excess
water from the reservoir, during times of flood, in such a manner as to
insure the safety of the dam and appurtenant works at all times. The
construction of major and medium multipurpose projects extends over
several years.
• Construction schedules of large projects are governed by many factors
such as volume of excavation, foundation treatment, earthwork or
concreting that can be handled in a season, stage–wise building of
irrigation/power potential, allocation of funds, etc
Cont.……..
• The construction phasing of spillways involves additional
factors such as safe passage of floods during construction and
the process of acquiring land under submergence and for the
rehabilitation of the project affected population.
SPILLWAY CONSTRUCTION PROGRAM
Although the construction program of spillways is an integral part of the project
construction, it involves considerations, some of which are exclusive to the spillway
and some are linked with other components of the project.
4. Ensuring safety of the other elements of the project during passage of floods over
the partly constructed spillway.
CONSTRUCTION FLOOD
• The flood discharge to be handled during the period of construction is
defined as the construction flood and is different than the diversion flood.
• While many countries have regulations laying down the flood return
period for which the diversion works must be designed, there are no
guidelines on the determination of construction flood.
• The criteria for selection vary between countries and among the projects of
different magnitudes
Cont….
The results were compared with those obtained from the model study and the agreement
Q= ∑C (W -2KH )H 3/2
Cont.…..
• Where K is the end contraction coefficient, in the case of monoliths
adjacent to non-flowing blocks/abutments, etc. and the coefficient C has to
be obtained from the Figure
• The value of K is traditionally taken to be 0.10 for each contraction. Also,
if the submergence over the crest due to downstream water level H1
exceeds about 0.67 or so, the submerged crest coefficient Cs (on above
figure), has to be considered
FLOW DOWNSTREAM OF PARTLY CONSTRUCTED SPILLWAYS
eddies pick up loose material from the downstream, bring it inside the