Professional Documents
Culture Documents
AND
SLOPE
PROTECTION
GROUP 5
WHAT IS DRAINAGE?
• Defined as the means of collecting, transporting and disposing of
surface water originating in or near the right of way, or flowing in
stream crossings.
• About 25% of roadway funds are spent for culverts, bridges and other
drainage structures.
Erosion Control
• Ascertain the design will not create erosion or other unacceptable
environmental condition.
WHAT IS HYDROLOGY?
• Branch of physical geography that deals with water of the earth. The
branch of hydrology that concern highway engineers are:
By Statistical
By Simulation
Approach
RELATIONSHIP AND EFFECT OF
HYDRAULIC AND CONSTRUCTION
Highway existing natural drainage pattern. Water passing the natural
right construction disrupt of ways is often intercepted by roadcuts.
Any changes in the land use may alter the historical run-off or
un-gauge rural water shed that could be disastrous on wide
scale basis.
CARDINAL RULES ON DRAINAGE DESIGN
Critical Depth
• Occurs when velocity head is half the average depth.
10mm 25mm
25mm 50mm
50mm 75mm
LAYING THE CONDUIT PIPE
1. Installation of conduit pipes should start at the downstream end of
the conduit line.
2. The lower segment of the conduit pipe should be in contrast with the
shape throughout its full length.
3. The bell or groove ends of rigid conduits and outside circumferential
laps of flexible conduits are placed with longitudinal laps or seams at
side.
4. Paved or partially lined conduit pipes are laid with the longitudinal
centerline of the paved segment coincides with the flow line of
water.
5. Elliptical and elliptically reinforced conduits are placed with major
axis within 5 deg of vertical plan through the longitudinal axis of
conduit.
JOINING THE CONDUIT PIPE
1. In joining conduit pipes, the ends are fully entered into the inner
surface evenly flushed. Joints are connected by:
a) Portland cement mortar or grout.
b) Rubber gaskets.
c) Oakum and mortar or joint compound.
d) Plastic sealing compound.
e) A combined of these types or any other as may be specified.
2. Joint mortar for concrete pipes consists of 1 part by volume of Port
land cement and 2 parts of approved sand with water nessecary to
obtain a refined consistency.
BACKFILLING
• Backfilling follows after the laying of installation of conduit pipes under
the following:
1. Materials for backfill should be fine, readily compacted soil or
granular material selected from approved sources.
2. Backfill materials should be free from stones that would be retained
on 50 mm sieve, nor chunks of highly plastic clay and other
objectionable materials.
3. At least 95% of granular backfill material passes the 12.5 mm sieve
and not less than 95% of it are retained on a 4.75 mm sieve.
4. Oversized materials if present should be removed.
5. On top of trench, backfill materials ae placed at or near optimum
moisture content or compacted in layers not exceeding 15 cm.
6. For that portion above the trench on each side of the conduit pipe,
the width of the backfill is equal to twice the diameter of conduit or
3.5 meters whichever is smaller.
7. After being bedded and backfilled, all conduits are protected by
cover fill 1 meter high, before any heavy equipment is permitted to
cross during the construction of roadway.
DESIGN OF UNDERDRAIN
• Underdrain is categorized under item 501 of DPWH standard
specifications, which provides that:
1. The pipe is used to carry away collected water.
2. Filter materials with which the trench is backfilled or the opening in
the filter, should be fine enough so that the adjacent soil will not be
washed-out in the drain.
3. The top of underdrain should be filled with impervious soil to prevent
the entrance of surface water.
4. Intercepting drains must extend into the impervious zone.
5. The pipes are laid with the flow line at least 1.2 meters below the
finished grade and carefully bedded with gravel or filled materials.
GRANULAR BACKFILL FILTER
MATERIALS
BLIND DRAIN
• Trenches for blind drains are excavated to the width and depth as
shown on plans. The trench is filled with granular backfill material to
the required depth.
DEBRIS CONTROL
• Flood waters usually carries objectionable objects like brushes,
banana trunks, tree branches, etc. these floating debris clog culvert
entrances and raise the headwater elevation overflowing the road
and damaging adjoining properties.
• Another alternative is to extend the curtain wall separating the barrels
of the multi span culverts upstream, with its top slanting downward so
that in time of flood debris carried by flood water will ride up on this
wall.
• Another method proven effective is to install up stream debris racks or
wire, steel rail or piling.
THE LEGAL ASPECT
OF DRAINAGE
• Highway agency is legally responsible for any damage to private
property affected by the changes it makes in natural drainage
pattern within the limit the water must flow.
1. When as a result of the agency’s project, the flow of several streams
or creeks were concentrated into a single channel that resulted to
erosion, flooding of property.
2. When due to poor design or inadequate maintenance, water
backed against highway or embankment resulted to inundation of
land or property or caused injury or death.
3. Liability however, is limited to damages in direct consequences of
the improvement.
4. Engineering decisions if based on an accepted practice, do not
provide for a course of action. In any case, the responsibility of
highway agency would be determined through negotiations or
court litigations.
ROADWAY DESIGN AND
CONSTRUCTION FOR UNUSUAL
SOIL CONDITIONS
Capillarity
Stability of fill
Drainage and frost
sand slope
heave
Elasticity and
Permafrost
rusting
STABILITY OF FILLS AND SLOPE
1. Slides may happen during construction or at later date after the
road is in service.
2. If it is possible during the location surveys, areas that are threatened
by frequent slide, should be avoided.
3. Slides may be caused either by mudflows, slope adjustment, or
movement due to underground water or undercut rock strata.
4. Slides maybe controlled by removing large portion of the materials
above the slippage surface.
5. Water must always be intercepted before it lubricates the critical slip
surface.
CAPILLARITY
• Tendency of water to seek its own level as if in an open channel flows
through the pores and fine channels of the soil.
1. In roadway construction, moisture has to be controlled.
Oversaturation of soil in road structure reduces its strength.
2. Moisture in the roadway is brought about by the changes in
weather, seasons or by capillary actions of water.
3. Water movement due to capillarity action take place in any
directions, and an upward movement may create undesirable
conditions.
4. Consistency of soil varies from semi solid to plastic liquid if moisture
content is increased.
5. Voids in soils are of the same order of magnitude as the particle size.
Thus, the height of capillary rise would be greater in fine grain soils
than in coarse grain soils.
• Slide refers to the occurrence where the moving mass is defined and
separated from the underlying and adjacent earth by plane,
comprising a number of adjacent planes were seepage results.
Rotational slide
• Associated with natural slopes and constructed embankments of
materials possessing cohesion.
Translational slide
• Slope of layered materials where the mechanism of slippage occurs
along a weak plane that possesses a downward dip.