Underwater Inspection

In Lieu of Drydocking (UWILD)

By Nguyen Be Chinh
Marine Supervisor - FPSO/FSO Department
Classification Society
 Responsible to verify marine structures compliance with regards to design, construction
and periodic survey against Rules (IACS).

 Noncompliance with the Rules and the recommendations will result with class
suspension or cancellation.

Road Tax

Certificate of Classification
Page  2
Dry-dock

 A narrow basin or vessel that can be flooded to allow a load to be floated


in, then drained to allow that load to come to rest on a dry platform.

 Dry-docks are used for the construction, maintenance, and repair.

Page  3
What is Underwater Inspection In Lieu Dry-docking (UWILD)
 Due to permanently moored at location and continuous operation, dry-docking is not
possible for FPSOs and FSOs.

 Underwater Inspection is equivalent to Dry-docking Inspection provided that all


arrangements and equipment meet the requirements specified by classification society.

Page  4
What is Underwater Inspection In Lieu Dry-docking (UWILD)

 The survey shall be conducted every 2.5 (Intermediate Survey) and 5 years (Special
Survey) in conjunction with any subsea structural inspection in the vicinity.

 Summary of scope of inspection to be cleaned and examined, where applicable:

I. Submerged Hull Areas


II. Corrosion Protection System - Underwater Body
III. Mooring System
IV. Import System
V. Export System

Page  5
Submerged Hull Areas

Export System

Corrosion Protection System

Import System

Mooring System

Page  6
Submerged Hull Areas

Visual Inspection (VI) started from the bow to the stern in zig-
zagging with 5m increments.

(1m x 1m) x 12

Page  7
Submerged Hull Areas

UT reading carried out UTG completed after cleaning – Visual inspection before
by diver Weld Seam cleaning

Page  8
Submerged Hull Areas

Bilge keel Sea chest (SC) after Overboard discharge after


cleaning cleaning

Page  9
Corrosion Protection System – Underwater Body
 The CP reading on Impressed Current Cathodic Protection (ICCP) anode material is taken
by divers hand held Bathycorrometer.

 To confirm that the cathodic protection system is operating within design limits.

ICCP Anode at Port Side Aft Sacrificial Anode at chain table

ICCP Anode at Port Side Bow CP reading at ICCP


Page  10
Mooring System
 The chain link were clean at five (5) or more spot at each different elevation of (-) 10m, (-)
20m, and (-) 30m by air diver for:
1. Visual inspection
2. Chain link thickness (>12% of original thickness – UTG / Vernier Caliper / Go no go
filler gauge)
3. Angle of chain (inclinometer)

Page  11
Mooring System

Chain near Mean Seawater Line

The middle of the chain


Page  12
Import System
 Visual inspection will be carried out to all flexible riser from Mean Seawater Line (MSL)
toward the Pipe Line End Manifold (PLEM).

 Visual inspection on the mid water arch will be carried out also to inspect the bouyancy
tanks, gravity base structure and chain connecting the mid water arch and gravity base
structure.

Page  13
Export System
 The visual inspection will be done on the floating hose from first flange connected to FSO /
FPSO and moving towards barbell which consist of hose strings, winker lights, Marine
Breakaway Coupling (MBC), barbell and flanges and bolts & nuts.

Page  14
THANK YOU