TRAINING OPERATION BORRI B 9000 FXS 200 KVA

FORMALIN PLANT – DOVER CHEMICAL


1.BORRI B 9000 FXS DESCRIPTION

 General Description

BORRI B 9000 FXS merupakan catuan daya Double-Convertion,dimana supply PLN (Source AC)
diconversi menjadi DC (Searah) oleh Rectifier dan kemudian diconversi kembali ke
Source AC(bolak-balik) oleh Inverter dan diteruskan ke load.
2.DIAGRAM BLOCK
3.DIAGRAM BLOCK (Lanjutan..)

 RCB = Rectifier Circuit Breakers


 BCB = Battery Circuit Breakers
 SBCB = Static Switch Circuit Breakers
 SB = Static Bypass
 SSi = Static Switch Inverter
 OCB = Output Circuit Breakers
 MBCB = Maintenance Bypass Circuit Breakers
4.DISPLAY PANEL
5.DISPLAY PANELS (lanjutan...)

 LED 1.8 and 9 = Supply PLN (Catuan Daya)


 LED 2 = Rectifier (Convertion AC to DC)
 LED 3 = Supply DC (Battery 12 V 100 AH,50 Block)
 LED 4 = Inverter (Convertion DC to AC)
 LED 5 = SSI (Static Switch Inverter)
 LED 6 = Output UPS
 LED 7 = SSB (Static Switch Bypass)
 LED 10 = EPO (Emergency Power Off)
6.DISPLAY PANELS (lanjutan...)
LED 1 : lit-up green = Rectifier Input Mains Present
Otherwise off

LED 2 : Lit-up green = Rectifier running Correctly


Lit-up red = Rectifier operation error

LED 3 : Lit-up green = Battery OK.


Lit-up orange = Battery discharging
lit-up red = battery test failed,BCB Open,battery not operating

LED 4 : Lit-up green = Inverter OK


lit-up red = Inverter failure

LED 5 : Lit-up green= load fet by inverter


Off = Ssi Open

LED 6 : lit-up green= OCB Closed and output voltage OK


Otherwise Off

LED 7 : Lit-up orange = Load fed bypass


Otherwise Off

LED 8 : Lit-up green= Supply line OK


Otherwise Off

LED 9 : lit-up orange = MBCB Closed


Otherwise Off

LED 10 : Lit-up red = EPO push-button pressed


Otherwise Off
7.SINGLE LINE DRAWING B 9000 FXS
8.SINGLE LINE DRAWING B 9000 FXS (Lanjutan...)
9.SINGLE LINE DRAWING B 9000 FXS (Lanjutan...)
10.SINGLE LINE DRAWING B 9000 FXS (Lanjutan...)
11.SINGLE LINE DRAWING B 9000 FXS (Lanjutan...)
12. BASIC TROBLESHOOTING
12.1 Basic Trobleshooting Procedure

12.1.1 MAINS OK LED OFF (Orange)


Step #1
1. Ceck the phasa rotation (Sequence Phasa)of supply voltage.
2. Make sure the input Voltage and frequeny are within tolerance.
3. Ceck the rectifier protection fuses F1,F2,F3;

After step #1 the UPS stop the starting sequence and shows one or more alarm message.
1. Ceck the alarms indicated on the display and remove their causes.
2. Close RCB and try to restart the UPS.

12.1.2 RECTIFIER TROUBLE LED ON (Orange)


Step #1
1. Ceck Fuse
2. Ceck temperature
3. Rect- Overload ( Setting Ampere current 0.1x C1 (battery Capacity)

12.1.3 BATTERY TROUBLE LED ON (Orange)


Step #1
1. Ceck the protection fuses of Battery swicth (BCB).
2. Ceck temperature battery
3. Battery Discharge (Battery ON)

12.1.4 INVERTER TROUBLE LED ON (Orange)


Step #1 1. Ceck Supply DC.
2. Ceck temperature
3. Ceck Load (Overload)
13.STANDART OPERATIONAL PROCEDURE

13.1 START-UP PROCEDURE


1. Close Breaker RCIB
2. Tunggu sampai LCD display menyala dan ikuti perintah yang ditunjukan
oleh LCD display

13.2 SHUT-DOWN PROCEDURE

1. Open OCB
2. Open BCB
3. Open SBCB
4. Open RICB
14.STANDART OPERATIONAL PROCEDURE (Lanjutan...)
14.1 MAINTENANCE BYPASS PROCEDURE

1. Push-on Toggle Switch bypass to BYPASS Position


2. Close MBCB UPS to BYPASS Position
3. Open OCB
4. Open BCB
5. Open SBCB
6. Open RCB

14.2 PROCEDURE MAINTENANCE Bypass to NORMAL OPERATION

1. Close RCB
2. Tunggu dan ikuti perintah Display Panel UPS
15. BASIC MAINTENANCE

15.1. Maintenance Unit and Battery:

1. Measurement BLOCK Battery Voltage 6 bulan sekali.


2. Cleaning Battery BLOCK and BANK BATTERY
3. Test ON Battery,secara berkala sebanyak 6 bulan
16. FORM MONITORING BORRI B 9000 FXS
MAINTENANCE AND SERVICE

PT DAYA PERKASA ABADI


GRAHA VEKTOR
Jalan Citarum cideng no 8-9 Jakarta
Jakarta Pusat

Email :
support@dpa.co.id
goksa@dpa.co.id ( Tech. Maintenance)
sagita@dpa.co.id (Sales Maintenance)
agung@dpa.co.id (Supv. Engineer)

HOTLINE : 082299358274

Created : Goksa