The document provides step-by-step instructions for starting up, disconnecting, and performing a black start operation of a rectifier inverter system. To start up, various circuit breakers and switches must be closed in a specific sequence. For disconnection, the reverse process is followed by opening switches and breakers. Black start operation involves using the battery power to start the inverter without mains power by closing certain breakers and switches briefly.
The document provides step-by-step instructions for starting up, disconnecting, and performing a black start operation of a rectifier inverter system. To start up, various circuit breakers and switches must be closed in a specific sequence. For disconnection, the reverse process is followed by opening switches and breakers. Black start operation involves using the battery power to start the inverter without mains power by closing certain breakers and switches briefly.
The document provides step-by-step instructions for starting up, disconnecting, and performing a black start operation of a rectifier inverter system. To start up, various circuit breakers and switches must be closed in a specific sequence. For disconnection, the reverse process is followed by opening switches and breakers. Black start operation involves using the battery power to start the inverter without mains power by closing certain breakers and switches briefly.
SS PRJ -10024 Inverter Start up STATUS REMARKS 1. Make sure that all circuit breakers and switches are open 2. Close the circuit breaker QE 3. Make sure that manual bypass change over switch QBY is on position1 (AUTO) 4. Close the UPS A/B output breaker Q4A (Q4B) 5 Set to ON position the selector switch on the ALR card 6. Close the rectifier output switch QRA (QRB) 7. Close the charger output to battery switch QBTA (QBTB) 8. Close the mains incoming circuit breaker Q1A (Q1B) 9.Set to ON position the selector switch on the ALI, LCID and ALS card 10.Close the circuit breaker CPCA ( B)until the led on the inverter control logic box are illuminated 11.Close the inverter input switch QIA (QIB) 12.Open the circuit breaker CPCA (CPCB) 13. Close the battery circuit breaker QB on the battery isolator box 14. Set the key switch SA1 to close position
15. Wait the AC UPS system is started
16. Close the battery switch Q2
17. Close the on-load switch Q3A (Q3B)
18. Close the QD A AND QD B
19. Close the QI 230A and 230B
20. Close the QI 110 A and 110B 21. Close the Q0 230A and 230B 22. Close the Q0 110 A and 110B 23. Keep Open the QC1 QC2 and QC3 24. All out going load MCB’S close Step by step 2. RECTIFIER INVERTER DISCONNECTION SS PRJ -10024 Inverter Start up STATUS REMARKS 1. All out going load MCB’S open step by step 2. Keep Open the QC1 QC2 and QC3 3. Open the Q0 110 A and 110B 4. Open the Q0 230A and 230B 5. Open the QI 110 A and 110B 6. Open the QI 230A and 230B 7. Open the QD A and QD B
8. Open the on-load switch Q3A (Q3B)
9. Open the battery switch Q2
10. Set the key switch SA1 to Open position
11. Open the battery circuit breaker QB on the battery isolator box 12.Open the inverter input switch QIA (QIB) 13.Set to off position the selector switch on the ALI, LCID and ALS card 14. Open the mains incoming circuit breaker Q1A (Q1B) 15. Open the charger output to battery switch QBTA (QBTB) 16. Open the rectifier output switch QRA (QRB) 16. Set to OFF position the selector switch on the ALR card 18. Open the UPS A/B output breaker Q4A (Q4B) 19. Open the circuit breaker QE 3. BLACK START OOPERATION FOR THE BLACK START OPERATION PROCEED AS FOLLOWS:
Black Start up STATUS REMARKS
1. Make sure that the inverter input switch QIA (QIB) is open 2. Close the circuit breaker QB on the battery isolator box 3. Set the key switch SA1 to close position 4. Close the circuit breaker CPCBT 5. Close the battery switch Q2 6. Open the circuit breaker CPCBT 7. Set the key switch SA1 to open position 8. Make sure that manual bypass change over switch QBY is on position1 (AUTO) 9. Set to ON position the selector switch on the ALI, LCID and ALS card 10. Close the UPS A/B output switch Q4A (Q4B) 11. Close the switch CPC/A (CPC/B) until the led on the inverter control logic box are illuminated 12. Close the inverter input switch QIA (QIB) 13. Open the switch CPC/A (CPC/B)