Professional Documents
Culture Documents
On March 2, 1973, the Skyline Plaza apartment building collapsed while it
is under construction.
The collapse extended vertically through the building from the 24th floor
Leaving an appearance of the structure as two separate high rise buildings
with a gap between them.
The collapse tore a 18.3-m wide gap through the building all the way to
the ground
The National Bureau of Standards (NBS, now the National Institute of
Standards and Technology, NIST) carried out an investigation on behalf
of the Occupational Safety and Health Administration (OSHA).
The NBS investigation team determined that punching shear failure at
the 23rd floor caused a partial collapse that propagated to the ground.
Skyline Plaza In Bailey's Crossroads
FORMWORK
The investigation quickly established the idea to
determine the location and state of the formwork
would be important for finding the cause
NBS concluded that stripping was in progress on the
22nd floor
Which would not leave sufficient support under the
fresh concrete on the 24th floor.
Stripping the 22nd-floor shores would leave only one
floor of shores under the fresh concrete.
Skyline Plaza In Bailey's Crossroads
Photos taken just before the collapse also showed few or no shores
under the 22nd floor.
There were witness statements to the effect that the shores between
the 22nd and 23rd floors came loose and toppled over
Which would be consistent with the 22nd floor dropping after its
support was removed
Estimated Concrete Strength Cold weather delays strength gain of
concrete.
Therefore, in cold weather, basing construction rates on a time, such
as one floor per week, may be unsafe.
Field-cured cylinders, which are stored next to the fresh concrete at
roughly the same temperature, provide a better estimate of the
concrete strength in the structure than laboratory-cured cylinders
Skyline Plaza In Bailey's Crossroads
Legal notes that the collapse raised the issue of the extent of the
engineer of record’s responsibility for the success and safety of
formwork design and inspection.
While the engineer’s contract specifically stated that he had no
responsibility for field inspection, nevertheless a jury found him
negligent.
This was so because the pertinent code required that “a
competent architect or engineer” must provide supervision
“where requested by the building official.”
Often, owners are not willing to pay engineers for the site visits.
It is observed that the federal jury found both the architect and
engineer negligent and awarded large damages.
Skyline Plaza In Bailey's Crossroads
The collapse of the flat-plate Harbour Cay Condominium building in Cocoa Beach, Florida,
on March 27, 1981
It was caused by a punching shear failure that triggered a progressive collapse, much like
those at Skyline Plaza in Virginia.
11 workers were killed and 23 were injured.
As at Skyline Plaza, OSHA (Occupational Safety and Health Administration) asked NBS to
investigate on its behalf.
The NBS investigation team included two individuals who had investigated the Skyline
Plaza collapse.
The collapse happened while the roof slab was being placed.
Photos taken shortly after the collapse, while the debris was still intact, provided important
evidence.
Many of the columns were still standing, up to three or four stories high. The slabs were
stacked vertically on top of each other.
This evidence strongly suggested a punching shear failure mechanism, with no side sway
during the collapse.
Some samples were obtained for subsequent coring and materials testing.
Harbour Cay Condominium
Another fact that was very disturbing was the indication that the
design engineer was made aware of severe cracking of the floors and
big deflections of the slabs several days prior to the collapse.
The cracks were described as “spider-web-type cracks”.
There were reports of deflections as large as 44 mm several days prior
to the collapse.
The structural engineer was requested to recheck his design, which he
did, reporting back that it was “OK.”
Description of Structure and Construction
The structure was a five-story flat-plate residential building
The slabs spanned up to 6.75 and 8.43 m in the two directions.
Interior columns were 254 *457 mm
Exterior columns were 254 * 305 mm
Harbour Cay Condominium
Lessons Learned
Punching shear is the most common failure mode for concrete flat- slab buildings and
must be checked.
The minimum depth requirements of the ACI code must be met toprovide adequate
strength and limit deflections.
Top and bottom reinforcing bars should be placed directly within the column periphery
to provide additional resistance to progressive collapse.
https://www.youtube.com/watch?v=dq0vof6TjD0
https://www.miamiherald.com/news/local/communit
y/miami-dade/miami-beach/article215352400.html
Harbour Cay Condominium
Harbour Cay Condominium
Harbour Cay Condominium