DETAILED ESTIMATE

OF RCC FRAMED
STRUCTURES :
2. DETAILED ESTIMATE :

 IT IS THE ACCURATE ESTIMATE PREPARED BY WORKING OUT QUANTITIES OF


EACH ITEMS OF WORK.
 IT CONSISTS OF ;
 DETAILS OF MEASUREMENTS ;
 CALCULATION OF QUANTITIES;
 ABSTRACT OF ESTIMATED COST – SUB-HEAD WISE
 3% TO 5% OF ESTIMATED COST IS ADDED TO COVER MISCELLANEOUS
EXPENDITURE (CONTINGENCIES)
 ADD FOR GST DETAILED ESTIMATE IS PREPARED WORK-WISE.
 ADD FOR DEPARTMENTAL CHARGES AS AGREED MUTUALLY BETWEEN
ADMINISTRATIVE DEPARTMENT (SUCH AS AMU) AND EXECUTION DEPARTMENT
SUCH AS CPWD/HSCL OR ANY OTHER DEPARTMENT )
 DETAILED ESTIMATE CONSISTS OF –
 REPORT :
 GENERAL SPECIFICATIONS;
 DETAILED SPECIFICATIONS ;
 DETAILED DRAWINGS AND DEVELOPMENT PLAN;
 SRUCTURAL DRAWINGS PREFERABLY BUT NOT MANDATORY.
 DETAILED CALCULATION (DETALES OF MEASUREMENTS)
 ANALYSIS OF RATES FOR MARKET RATE ITEMS ;
 APPROVED COST INDEX (AVAILABLE ELSE SEEK APPROVAL OF COMPETENT
AUTHORITY)
 PURPOSE OF FRAMING DETAILED ESTIMATE ;
 ACCORD OF TECHNICAL SANCTION OF COMPETENT AUTHORITY;
 FLOATING OF NIT ;
 FINALISATION OF CONTRACT ;
 REGULATION OF BUDGET ;
DETAILS OF MEASUREMENTS AND CALCULATION OF QUANTITIES :
1. QUANTITY OF BASE CONCRETE - (1:4:8)
= 4*1.50*1.50*0.15 + 2*3.73*0.50* 0.15+ 2*2.73*0.5*0.15
= [9.0+3.73+2.73] * 0.15
= 15.46*0.15
= 2.32 CU M ;

2. QUANTITY OF CONCRETE IN FOUNDATION AND PLINTH - (1 : 1.5 : 3)


A. QUANTITY OF RCC CONCRETE IN ONE FOUNDATION :
= 1.20*1.20*0.15+ [1.2*1.2+0.65*0.65+√{(1.2)^2 * (0.65)^2} ]/ 3 * 0.3
= 0.216 + 0.264
= 0.480 Cu M
QUANTIY OF CONCRETE IN 4 NUMBER FOOTINGS :
= 4* 0.48025
= 1.921 Cu M
B. QUANTITY OF RCC IN COLUMNS BELOW PLINTH BEAM :
LENGTH(HEIGHT) OF COLUMN BELOW PLINTH LEVEL = (3.0-0.45-0.15)
= 2.40 M
QUANTITY OF RCC IN ONE COLUMN BELOW PL = 0.35 * 0.35 * 2.40
= 0.294 CU M
QUANTITY OF CONCRETE IN 4 NO. COLUMNS = 0.294 * 4
= 1.176 CU M
  C. QUANTITY OF RCC IN PLINTH BEAM :
= 17.54 * 0.345 * 0.30
= 1.82 CU M
  TOTAL QUANTITY OF RCC BELOW PLINTH LEVEL = 1.92 + 1.176
= 3.10 CUM
3. QUANTITY OF RCC(1: 1: 3) IN BEAMS AND SLABS ABOVE PLINTH LEVEL :
A. QUANTITY OF RCC (1: 1: 3) IN BEAMS UNDER THE SLAB
= 17.54 * 0.23 *0.50 = 2.02 CU M
 B. QUANTITY OF R.C.C(1: 1: 3) IN SLAB = 5.0 *4.0 *0.15
= 3.0 CU M
QUANTITY OF RCC IN BEAMS AND IN PLINTH BEAMS = 2.02 +1.82 = 3.84 CUM
QUANTITY OF RCC (1: 1: 3) BEAMS + SLAB + PLINTH BEAMS
= 2.02 + 3.0 + 1.82 = 6.84 CU M
4. QUANTITY OF R.C.C (1 :1.5 : 3) IN COLUMNS ABOVE PLINTH ;
= 4 * 0.35 * 0.35 * 3.90
= 1.911 CU M
 
5. CENTERING & SHUTTERING WITH STRUTTING AND PROPPING :
(A) IN FOUNDATIONS AND PLINTH :
= FOOTINGS + COLUMN BELOW PL :
= 4 (NO. OF FOOTINGS)* 1.20 (LENGTH OF ONE SIDE OF FOOTING)* 4 (NO. OF
SIDES IN EACH FOOTING)* 0.15 ( THICKNESS OF FOOTING) + 4 * 0.35 * 2.40 *4
=
= 2.88 + 11.60
= 14.48 Sq M
(B) SHUTTERING IN BEAMS AND PLINTH BEAMS :
  = 17.54 [0.30 + 0.30 + 0.345] + 17.54 [ 0.50+0.30 + 0.23 ] = 1.975 *17.54
= 34.64 SQM
(C) SHUTTERING IN SUSPENDED FLOORS AND SLABS ;
= 5.0 * 4.0 = 20.0 SQM
(D) IN COLUMNS ABOVE PLINTH LEVEL ;
= 4 *0.35 *3.90* 4= 21.84 SQ M
6.0 QUANTITY OF STEEL REINFORCEMENT :
= REINFORCEMENT IN FOUNDATION + BEAMS + COLUMNS +SLAB
= 1.921 * 100 KG (FOOTINGS)+ 3.84 * 120 KG (BEAMS + PLINTH BEAMS )+
2.911 * 150 KG + 3.00 * 80 (SLAB)
= 192.10 KG + 461 KG + 436.65 + 240.0
= 1329.55 KG
= 1.33 MT
TAKE 3 % WASTAGE =1.03 * 1.33 = 1.37 MT
SAY 1.40 MT