Objectives
To provide an on-line system to report,
analyze,and correct non conformities as
required by ISO 9001 and the LHC Quality
Assurance Plan:
Method
Use the EDMS and its web interface.
Use a document, the nonconformance
report.
Use a specific document type, QN.
NC Status
Production
Makes analysis
Manager Proposes solution, including
UNDER APPROVAL
corrective action There is a problem
Solution found
Waiting for approval
Project Engineer Verifies and
Project Management Approves solution ACCEPTED (RELEASED)
There is a problem
Solution approved
Production Implements solution
Manager Correction in-progress
CLOSED (OBSOLETE)
Production Manager Implementation complete There was a problem
Project Engineer Stops NC process It has been corrected
Confidentiality
Inspector and Production Manager
May only see NC’s related to their contract
Project Engineer
May see NC’s related to all his contracts and to
all related equipment
Project Management
May see all NC’s related to the project
Web interface
Specific form to store and search for
NC’s:
To clearly segregate NC’s, as processes, from
documents.
To display NC status and hide the NCR document
status.
To automatically assign the doc type.
Pre-defined search as for ECR’s
Search by status, like ECRs.
PE (or secretary)
Completes point 14 or 15 of the form and faxes it to
Production Manager
Creates an empty (no file attached) NC Report
Changes the status of NC to IN-PROGRESS
When Implementation is completed:
Scans the completed form and stores it in EDMS
Change status to CLOSED
LHC-PM-QA-509.00