Professional Documents
Culture Documents
Fs14 Lesson 14 - Earthwork & Mass Diagram
Fs14 Lesson 14 - Earthwork & Mass Diagram
Quantities
Excavation- the amount of material
that needs to be removed from the
grade.
Embankment- the amount of
material that needs to be added to
the grade.
Excavation and embankment are
calculated with cross sections using
the average end area method.
𝑽 𝑬= (
𝑨 𝟏+ 𝑨 𝟐
𝟐
𝑳 )
Engr. ROSELLA C. ALGADO, CE
EARTHWORK
ℎ𝑅
ℎ𝐿 𝑐
𝑽 𝑬= (
𝑨 𝟏+ 𝑨 𝟐
𝟐
𝑳 ) Where:
w – width of the road
hL – height left
hR – height right
c – height of center line
dL – distance from centerline to the left
dR – distance from centerline to the right
𝑽 𝒑= ( 𝑨𝟏 +𝟒 𝑨 𝒎+ 𝑨 𝟐
𝟔 ) 𝑳
Engr. ROSELLA C. ALGADO, CE
EARTHWORK
𝑽 𝒑=(𝑨𝟏 +𝟒 𝑨 𝒎+ 𝑨 𝟐
𝟔 )
𝑳
𝑳
𝑪𝒗 =
𝟏𝟐
( 𝑪 𝟏 − 𝑪𝟐 ) ( 𝒘 𝟏 −𝒘 𝟐 )
𝑽 𝑷 =𝑽 𝑬 − 𝑪 𝒗
NOTE:
FIGURE:
7.00m
𝐶𝐿
1 .5 ℎ 𝐿 1 .5 ℎ 𝑅
1.5:1
ℎ𝐿 𝐸𝑙𝑒𝑣 𝑃𝑅 (𝑠𝑢𝑏𝑔𝑟𝑎𝑑𝑒)=152 𝑚
2m
10%
ℎ𝑅
𝐸𝑙𝑒𝑣 𝑔𝑟𝑜𝑢𝑛𝑑 =150 𝑚
𝑑 𝐿 𝑑 𝑅
2m
SOL’N:
2m
2m
STA.10+200
6.0 0 6.9
+2.0 X +2.6
STA.10+200
6.0 0 6.9 FIGURE:
+2.0 X +2.6
Engr. ROSELLA
Engr. ROSELLA C.
C. ALGADO,
ALGADO, CE
CE
EXAMPLE #2 EARTHWORK
SOL’N:
FIGURE:
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EXAMPLE #3 EARTHWORK
SOL’N:
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EXAMPLE #3 EARTHWORK
SOL’N:
Station Cross Section
9.0 4.5 4.5 6.0
1+020 +2.0
+3.0 +4.0 +1.5 +1.0
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EARTHWORK
Total Quantities
Topsoil- topsoil quantities are not calculated into the
excavation or embankment. This is a separate value
that has to be dealt with separately.
Imported topsoil is needed if the stripping volume
acquired does not fulfill the quantity of topsoil that is
proposed.
𝐹𝑖𝑙𝑙
𝐴𝑑𝑗𝑢𝑠𝑡𝑒𝑑 𝐹𝑖𝑙𝑙=
( 1− 𝑠ℎ𝑟𝑖𝑛𝑘𝑎𝑔𝑒 𝑓𝑎𝑐𝑡𝑜𝑟 )
= 2308 cu. yd
Mass Ordinates
Mass ordinates are the cumulative total of the
excavation and embankment on the project.
Mass Ordinates
Volume
FIGURE:
Economical Haul = 450 m
Overhaul Vol
Free Haul = 50 m
Vol. Waste Vol. Borrow
50 𝑚2 a
b 2+948.03
2+440 2+713.12 2+740 c 3+040
d
2+763.12
2+498.03
70 𝑚2
23.12
58.03 215.09 26.88 184.91
91.97
241.97 208.03
300 m 300 m
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EXAMPLE #4
EARTHWORK: MASS DIAGRAM
SOL’N:
HAUL
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EXAMPLE #4
EARTHWORK: MASS DIAGRAM
SOL’N:
HAUL
Engr. ROSELLA
Engr. ROSELLA C.
C. ALGADO,
ALGADO, CE
CE
EARTHWORK: MASS DIAGRAM
STA. VOLUME
EXAMPLE #5: CUT FILL
10+000 +200
The following data represents a single
10+040 +100
summit mass diagram of proposed
10+080 +150
expansion of the Tolosa Expressway. 10+120 +140
Free haul distance = 50 m 10+160 +110
10+200 +190
Limit of Economical Haul = 400 m 10+240 +50
Mass ordinate of initial limit of free 10+280 -40
haul distance --------- +910 cu. m. 10+320 -120
10+360 -90
Mass coordinate of initial limit of 10+400 -80
econimical haul -------- +350 cu. m. 10+440 -200
10+480 -220
a. Compute the volume of waste
10+520 -110
b. Compute the volume of overhaul 10+560 -320
10+600 -280
c. Compute the volume of borrow
Engr. ROSELLA C. ALGADO, CE
EARTHWORK: MASS DIAGRAM
STA. VOLUME
SOLUTION:
CUT FILL
10+000 +200 +200
+940
10+040 +100 +300
+910 10+080 +150 +450
F.H.D. = 50 m 10+120 +140 +590
+350 10+160 +110 +700
E.H.L. = 400 m 10+200 +190 +890
+200 10+240 +50 +940
10+280 +900 -40
10+000 10+320 +780 -120
10+360 +690 -90
+940
+910
F.H.D. = 50 m
+350
E.H.L. = 400 m
+200
10+000
-520
Engr. ROSELLA
Engr. ROSELLAC.
C.ALGADO,
ALGADO, CE
CE
EARTHWORK
BORROW PIT
During construction of roads, airports, dams, and
other projects involving earthwork, it is often
necessary to or borrow earth from a designated
area near the project in order to construct
embankments.
In construction and civil engineering, a borrow pit,
also known as a sand box, is an area where
material (usually soil, gravel or sand) has been dug
for use at another location