Extra
Extra
THIRD FLOOR
4 Neurology – 40 Beds, Cardiology – 40 Beds
(2731 SQM)
FIFTH FLOOR
6 (2691 SQM) OT’S – 05 NOS., Cathlab, ICU – 12 Beds
TERRACE
7 (359 SQM) AHU’S
SERVICE Block
8 Ground Floor ESS, HVAC, MGPS.
(471 SQM)
Present Status
Physical Progress :- 35.00 %
Hindrances
Sl. No Descriptions
1 Initial delay in handing over clear site by Client. Existing hospital blocks (Septic
ward, ICU, NHRM office) dismantled and shifted on 09.12.16.
( 3 months after start of work.)
2 Further delay occurred due to Pan/Grocery shop and Medical Shop exists in the
area of main blocks, which could be vacated by Client on 02.03.17.
( 6 months after start of work.)
3 One Medical shop is still exists which will hinder the external development works.
Client informed that Court-stay order has obtained by the shop keeper. Client is
pursuing to vacate the same and referred this matter to their Legal advisor.