Professional Documents
Culture Documents
Navana Construction: Group No. 18
Navana Construction: Group No. 18
Construction
Group no. 18
Case Summary
• Navana Construction with a project of $5.4mill for the Pran –RFL- Group.
• Deadline for the construction is 47 weeks
• Failing to meet the deadline would result in a penalty of $300,000
• If the project is completed within 40 weeks the company will be rewarded $150,000
• Project manager is Engr. Abul Kalam Azad
• Now its up to him to figure out, if it is feasible to finish the project within the 40 weeks
time frame.
• He is considering PERT/CPM to find the project’s feasibility.
Difference between PERT and CPM
PERT CPM
PERT is a project management technique, whereby planning, scheduling, CPM is a statistical technique of project management in which planning,
organizing, coordinating and controlling uncertain activities are done. scheduling, organizing, coordination and control of well-defined activities take
place.
PERT is a technique of planning and control of time. CPM is a method to control costs and time.
PERT is evolved as a research and development project. CPM is evolved as a construction project.
PERT technique is best suited for a high precision time estimate. CPM is appropriate for a reasonable time estimate.
PERT deals with unpredictable activities. CPM deals with predictable activities.
PERT is used where the nature of the job is non-repetitive. CPM involves the job of repetitive nature.
PERT is best for research and development projects. CPM is for non-research projects like construction projects.
The crashing concept is not applicable to PERT. Crashing is a compression technique applied to CPM, to shorten the project
duration, along with the least additional cost.
Activity list for Navana Construction
Limited project
Activity Activity Description Imme Optimistic Most Likely Pessimistic Time Time (Crash) Cost $ (Normal) Cost $ Maximum
diate Estimate Estimate Estimate (Normal) (Crash) Reduction in Time
Predece- a m b
ssors
A Excavate - 1 2 3 2 weeks 1 weeks 180,000 280,000 1 week
B Lay the foundation A 2 3 8 4 weeks 2 weeks 320,000 420,000 2 weeks
C Put up the rough wall B 6 9 18 10 weeks 7 weeks 620,000 860,000 3 weeks
D Put up the roof C 4 5 10 6 weeks 4 weeks 260,000 340,000 2 weeks
E Install the exterior C 1 4 5 4 weeks 3 weeks 410,000 570,000 1 weeks
plumbing
F Install the interior E 4 4 10 5 weeks 3 weeks 180,000 260,000 2 weeks
plumbing
G Put up the exterior siding D 5 6 11 7 weeks 4 weeks 900,000 1,020,000 3 weeks
2. What is the total time required to complete the project if no delays occur?
3. When do the individual activities need to start and finish (at the latest) to meet this
project completion time?
4. When can the individual activities start and finish (at the earliest) if no delays occur?
5. Which are the critical bottleneck activities where any delays must be avoided to
prevent delaying project completion?
6. For the other activities, how much delay can be tolerated without delaying project
completion?
8. If extra money is spent to expedite the project, what is the least expensive way of
attempting to meet the target completion time (40 weeks)?
1. Graphical Representation of The Project
2. Time Needed to Finish the Project
B 4 1
C 10 4
E 4
F 5 1
J 8 1
L 5 1
N 6
Project duration
(In weeks)
44 47
(Mean) (Deadline)
J 2 weeks 30,000 * 2
F 2 weeks 40,000 * 2