Professional Documents
Culture Documents
• Use of Competitive
Bidding
WHAT ARE GOODS?
BID TECHNICAL
PW: XXXX
TECHNICAL
FINANCIAL
FINANCIAL
PW: XXXX
WHO ARE ELIGIBLE BIDDERS?
COA
DULY RECOGNIZED POST-QUALIFICATION BID EVALUATION
PRIVATE SECTOR
GROUP
NGO
on
COMPETITIVE
BIDDING PROCEDURE
AND REQUIREMENTS
STANDARD COMPETITIVE BIDDING PROCEDURE
FOR GOODS AND SERVICES
Pre-Procurement Advertisement Pre-Bid
Conference 7 Conference
cd as
ncessary
cd
65 cd
❑ BAC
Mandatory for projects ❑ BAC Secretariat
Conducted prior to with ABC above Php2M ❑ TWG
advertisement or for Goods ❑ Consultants for the subject
posting of the IB and above Php5M for procurement project, if any
Infra Projects ❑ End-user unit
❑ Other Officials
REFERENCE TO BRAND NAMES
TIMELINE
7
calendar days
www.xxxx.gov.ph
continuously
PRE-BID CONFERENCE
TIMELINE
PURPOSE
at least
12
To discuss, clarify and explain,
among other things, the eligibility
requirements and the technical
and financial components of the
calendar days
contract to be bid
before deadline for questions clarifications
including and
bid submission but not raised by the prospective bidders
earlier than 7 CDs
from the before and during the Pre-Bid
PhilGEPS posting Conference
SUPPLEMENTAL/BID BULLETINS
TIMELINE PURPOSE
issued at least
7
Issued by the BAC, duly
BID BULLETIN signed by BAC
Chairperson, to:
❑ Answer requests
for clarification or
calendar days interpretation
before deadline for
bid submission. ❑ Clarify or modify any
Queries should be submitted provision of
to the BAC 10 CDs before
deadline for bid submission. Bidding Documents
SUBMISSION AND RECEIPT OF BIDS
BID VALIDITY
120
Financi
al
Propos
al
calendar days
from the date of the
opening of
bids
SUBMISSION AND RECEIPT OF BIDS
Date of submission should not be later than the
following periods from the last day of posting of For bids submitted
IB: electronically, the PEs
shall generate a Bid
GOODS INFRA INFRA receipt page for the
official time of
45 50 65
submission which can
be saved or printed by
the bidder, upon receipt
calendar days calendar days
of the first and second
calendar days envelope
above Php50M Php50M below
GPPB RESOLUTION
NO. 09-2020
OPENING AND PRELIMINARY EXAMINATION OF BIDS
The BAC shall open the bids in public immediately after the deadline for the
submission and receipt of bids
❑ presence or
absence Only bidders
Only 2nd Envelopes
❑ checklist of whose 1st and 2nd
of bidders whose 1st
required envelopes were
Envelope was rated
documents rated “PASSED”
❑ non-discretionary “PASSED” shall be
will be ranked as
“pass/fail” opened
read
criterion
OPENING AND EVALUATION OF 1ST ENVELOPE
TECHNICAL COMPONENT
Eligibility Technical
Requirements Requirements
Class “A”
✔Legal Documents Bid Security
✔Technical Documents
✔Financial Documents
Class “B”
Project Requirements
✔Joint Venture Agreement
CLASS “A”
CLASS “A” CLASS “A”
TECHNICAL CLASS “B”
LEGAL Documents FINANCIAL Documents
Documents
Net Financial In case of Joint
PhilGEPS Certificate of Statement of All
Contracting Venture, JV
Registration (PLATINUM Ongoing
Capacity (NFCC) Agreement entered
MEMBERSHIP) Contracts
or CLC (for Goods) into by the parties
OR
SEC Certificate of Statement of Single
Registration / DTI Largest Completed
Registration Contract (SLCC)
Mayor’s Business
Permit
Valid PCAB License / Special PCAB
Tax Clearance
License for JVA (for Infra)
Audited Financial
Statement
LEGAL ELIGIBILITY REQUIREMENTS (CLASS “A”)
SERVICES &
25% market research,
applying the general
contracts aggregate
amount at least equivalent
NON-EXPENDABLE to required percentage;
rule will likely result to:
SUPPLIES and largest of the similar
FAILURE OF contracts amounts to at
50% BIDDING
or
least 50% of required
percentage.
MONOPOLY
TECHNICAL ELIGIBILITY REQUIREMENTS (CLASS “A”)
❑ The SLCC’s value should be at least 50% of the ABC to be bid upon
adjustment to current prices using the PSA consumer price indices
=
value of all outstanding or uncompleted portions of the
NFCC projects under ongoing contracts, including awarded
contracts yet to be started, coinciding with the contract to be
bid.
7
Bid (LCB) , by: consideration of:
❑ Establishing correct ❑ Completeness of bids;
calculated prices of and
bids; and ❑ Minor arithmetical
❑ Ranking calculated corrections calendar days
from the deadline for
total bid prices from
Results shall be contained receipt
lowest to highest in the ABSTRACT OF of proposals
BIDS
POST-QUALIFICATION
PURPOSE METHOD TIMELINE
should be completed within
To determine whether
12
the LCB complies with A non-discretionary
and is responsive to all pass or fail criterion
requirements and shall be used to
conditions as specified “VERIFY, VALIDATE calendar days
in the Bidding AND ASCERTAIN” all
TI
Documents, to be statements and
ME
declared the Lowest documents submitted
LI
Calculated and by the LCB
NE
Responsive Bid (LCRB)
should be
complete
d within
4
AWARD OF CONTRACT
15
LCRB within 3 CD from the issuance of the resolution
recommending award.
calendar days
APPROVE or
DISAPPROVED by the HoPE
AWARD OF CONTRACT
POSTING REQUIREMENT
NOTICE OF
AWARD
within
3
calendar days
www.xxxx.gov.ph
7
CONTRACT
within
15
calendar days
from the date of approval of
the contract
calendar days
All notices called for by the from the date of issuance
terms of the contract shall be
effective only at the time
www.xxxx.gov. ph
of receipt thereof by the
successful bidder.
WARRANTY SECURITY
PURPOSE WARRANTY PERIOD
To guarantee that the
contractor shall perform PERMANENT STRUCTURES
his responsibilities and 15 (Types 4 and 5; Ex. steel, iron,
shall answer for a liability years concrete)
arising due to:
SEMI-PERMANENT STRUCTURES
❑ improper construction (Types 1,2 and 3; Ex. roads, concrete
5
river control, drainage, irrigation lined
years
canals)
❑ use of inferior
quality/standard
OTHER STRUCTURES
2
❑ any violation of the (Ex. wooden bridges, spring
contract plans years developments)
and specifications
FAILURE OF BIDDING
BAC shall DECLARE A
WAY FORWARD:
FAILURE OF BIDDING, when:
❑ Mandatory review shall be
No bids are received;
conducted by BAC