OEE - Lean
OEE - Lean
Effectiveness
The objective of OEE
OEE Combines three factors:
1. Availability (a)
2. Performance (p)
3. Quality (q)
OEE = a*p*q
The Six Big Losses
Planned output
1. Breakdowns
Gross output 2. Set-ups & Changeovers
3.Idling
Net output 4. Reduced speed
5. Start up
Valuable
scrap
output 6. Scrap
The Six Big Losses
Planned output
1. Breakdowns
Gross output 2. Set-ups & Changeovers
3.Idling
Net output 4. Reduced speed
5. Start up
Valuable
scrap
output 6. Scrap
Example
What is the Overall Equipment Effectiveness (OEE) ?
Workers scheduled 150 hours Waiting 7
Changeover and 8 hrs Speed 90% when
set up time running
Breakdowns 5 hrs Defect rate 5%
Theoretical output
= Availability rate (a)
Potential output
Actual output
= Performance rate (p)
Theoretical output
Good product
= Quality rate (r)
Actual output
OEE = a * p * r
Example
What is the Overall Equipment Effectiveness (OEE) ?
Workers scheduled 150 hours Waiting 7
Changeover and 8 hrs Speed 90% when
set up time running
Breakdowns 5 hrs Defect rate 5%