You are on page 1of 19

INDUSTRIAL TRAINING PROJECT

PRESENTATION
CONSTRUCTION OF NON – TEACHING
STAFF QUARTERS

PRESENTED BY : J. Mukesh (20018 - C - 079)


TRAINING INDUSTRY : Andhra Pradesh Medical Service &
Development Corporation
INDUSTRIAL INCHARGE : M. Ravi Kumar (A.E)
INTERNAL GUIDE : Dr .K.THASILU M.Tech, Lecturer In

Department of Civil Engineering.

SITE DETAILS : Located in the premises of Sri


Padmavathi Medical College for
Women at Tirupati.
INTRODUCTON

• The Aim of the project report is to construct Non


Teaching Staff Quarters.
• It is easily accessible to the staff for residence.
• The amount for the construction of Non Teaching
Staff
Quarters is 6,34,75,847Rs.
CONTENTS
Earthwork Excavation
Plain Cement Concrete
Footings
Plinth Beam
Form Work
Columns
Beams
Slabs
Brickwork
Plastering
Curing
PLAN OF NON TEACHING QUATERS
EARTHWORK EXCAVATION

• Earthwork Excavation is a process of moving earth or rock.


• It depends upon the soil bearing capacity.
• The depth of earth work excavation for foundation is up to 3 m.
PLAIN CEMENT CONCRETE (PCC)

• Plain Cement Concrete is a cement mixture commonly used for


paving.
• The nominal mix of concrete used in this construction is (1:4:8)
• and the thickness of PCC is 15 cm.
FOOTINGS
• The footings are constructed to distribute the load from the columns to
the ground evenly.
• As per soil report 30 T/sq.m SBC is considered at a depth of 2.5 m for
footing design.
• The grade of concrete used in the execution of this work is M25.
• Both isolated and combined footings are used in the execution of work.
PLINTH BEAM
• A plinth is a base or platform that supports a pedestal, column, or
structure.
• Structurally, the plinth distributes the weight and pressure coming
down
through a column evenly across a wider space.
COLUMNS

• Column is a structure it transmits load from beam to foundation. It resists


the compression force, so it is also called as compression member.
• The grade of cement & steel used in columns are M25 (1:1:2 ) & Fe500,
minimum yield strength of Fe500 is 500 Mpa .
Form work

• Form work is used to form concrete into structural shapes like beams, columns,
slabs for building.
SLABS
• A slab is a structural element, made of concrete, that is used to create flat
horizontal surfaces such as floors, ceilings.
• The thickness of slab in this construction is 150 mm.
• 10 mm dia bars is used as both main bars and distribution bars.
•The spacing between main bars is 220 mm.
• The spacing between distribution bars is also 220 mm.
• The grade of concrete is used in this execution of work is M25.
BRICKWORK
• Masonry work in CM (1:4) prop with Flyash Cement solid blocks of size 230x 110

x70 mm.
• Compressive strength of this brick is 40 Kg/Sq.cm.
• Flemish bond is used in the execution of work.
PLASTERING
• Plastering is the process of covering rough walls and uneven surfaces in the
construction of houses and other structures with a plastic material called
plaster, which is a mixture of lime or cement concrete and sand along with
the required quantity of water

• Plastering with 12mm thick in two coats is provided for inner walls.
• The first coat is 1:6 proportion cement mortar with 8mm thickness.
• The second coat is 1:4 proportion cement mortar with 4mm thickness.
• Plastering with 20 mm thick in two coats is provided for outer walls.
• The first coat is 1:6 proportion cement mortar with 16mm thickness.
• The second coat is 1:4 proportion cement mortar with 4mm thickness.
CURING
• Curing is also called as watering.
• It develop the potential strength and durability of concrete will be fully
developed only if concrete is properly cured.
• The curing is done for a period of 28 days for slabs, columns and
beams,
• and 7 to 14 days for brick masonry and plastered walls.
Conclusion

In this training period I have learnt the construction procedure,


• Preparation of Estimates.
• Reading plans and drawings.
• Supervising civil works with respect to quality.

From this training period I got the experience practically in working site
and the implentation of theoretical knowledge in working site.
THANK
YOU

You might also like